Wholesale data center advisory for tenants and landowners, from 1 MW to campus scale

Delivery model

Build-to-suit data centers: process, timeline and lease terms

In a build-to-suit, a developer designs and builds a data center to your specification and leases it to you for the long term. You get the building you would have built, without funding it. You also make commitments early that are expensive to change. Here is how it works.

Key takeaways

  • A build-to-suit (BTS) is a facility built for one tenant to that tenant's design, delivered under a long lease. The developer funds construction.
  • Rent is typically set from the total project cost and the developer's required return, so the scope you freeze early drives the rent you pay for the whole term.
  • Power decides the schedule. A site with a committed utility date can deliver years before a site that is still in a utility study.
  • Protect the delivery date: milestones, rent credits or liquidated damages for delay, and a termination right if the building is not delivered.

What is a build-to-suit data center?

A build-to-suit is a data center developed for a single tenant on a specific site, built to the tenant's specification and leased to that tenant, usually before construction starts. The developer, or the developer's capital partners, buys or controls the land, secures power, finances and builds the facility, then owns it as a leased asset. The tenant commits to a long lease that makes that financing possible.

It differs from the other wholesale models in who designs the building and when you commit:

  • Turnkey wholesale: you lease finished or planned halls in a building designed for many tenants. See turnkey data centers.
  • Powered shell: the landlord delivers building and power, and you design, fund and install the inside. See powered shell data centers.
  • Build-to-suit: the whole building is designed around your requirement, and the developer funds it.

When a build-to-suit makes sense

  • The requirement is large and durable enough to fill a building for the whole term.
  • The design is specialized: very high density, a specific liquid cooling architecture, unusual security or compliance needs.
  • You want to control the design without putting capital into a building you would rather not own.
  • You can commit to a long term and provide the credit a developer's lenders will require.
  • Your timeline allows for development. If you need power within months, energized turnkey capacity is usually the only realistic option.

The build-to-suit process and timeline

A build-to-suit runs through the same phases as any data center development. What changes is that you are committed from the start, so every phase's risk touches your schedule.

PhaseWhat happensWhat delays it
Site and powerLand control, utility studies and a service agreement for the loadUtility queues and large-load rules. The longest pole in most markets
EntitlementsZoning, site plan, environmental and air permits for generatorsRezonings, public hearings, local opposition
Design and scope freezeBasis of design, density, cooling, redundancy, phasingLate tenant changes, new hardware generations
ProcurementTransformers, switchgear, generators, UPS and cooling orderedLead times of one to two years on major electrical equipment
ConstructionShell, electrical and mechanical installationLabor, weather, equipment arrival
Commissioning and acceptanceIntegrated systems testing before the tenant accepts the spaceFailed tests, missing equipment, utility energization

How long it takes depends almost entirely on where the site starts:

  • Power is the long pole. Cushman & Wakefield puts the average time to secure power for new large loads at 5.0 years in the Americas (Global Data Center Market Comparison, May 2026). CBRE says grid interconnection can take 24, 36 or 48 months or more when new transmission or generation is needed, and that the old 12 to 18 month schedules no longer apply to large campuses (CBRE, December 2025).
  • Commitments come early. In Atlanta, CBRE reports build-to-suit capacity preleasing about 2.5 years before completion, against about 12 months for turnkey space (CBRE, H1 2026).
  • It can be fast when power is already secured. Applied Digital broke ground on its Polaris Forge 2 campus in August 2025, signed a 200 MW lease that October, and expected first capacity in the second half of 2026 (Applied Digital 10-K).

How build-to-suit rent is set

The developer recovers its construction cost through rent, usually over a lease of 15 to 20 years (King & Spalding, April 2025). In practice rent is set so the project earns the developer a target yield on its total cost. datacenterHawk describes yield-based rents targeting 7 to 14% (datacenterHawk, 2026 deal trends).

Why the cost basis matters

Cushman & Wakefield puts the average all-in cost of the most modern new US or Canadian data centers at $17.6 million per MW, excluding chips and GPUs (September 2026). At a 7% yield, that cost implies first-year rent of about $103 per kW per month. At 14%, about $205. Our arithmetic, for illustration: a real deal depends on what the cost includes, the term, the escalator and who funds your equipment. Our construction cost guide breaks that cost down. The point is that each million dollars of cost per MW, and each point of yield, flows straight into your rent for the whole term.

Real contracts show the mechanism. CoreWeave's annual report describes a lease covering 393 MW at a single site with rent based on the landlord's construction cost up to a cap, totaling $13.5 to $14.4 billion over 16 years (CoreWeave 10-K). A cap like that is what keeps cost overruns from becoming your rent.

Your credit changes the developer's cost of money, and so your rent. JLL reports construction loans for top hyperscalers at spreads in the low 200s of basis points with up to 85% loan-to-cost, while projects without a credit tenant pay 200 to 300 basis points more at 70 to 80% loan-to-cost (JLL, August 2026). Tenants with less credit history can offset that with security, a parent guarantee or a third-party backstop.

Large build-to-suits also come as joint ventures. Meta's Hyperion campus is owned by a joint venture that is 80% Blue Owl and 20% Meta, with about $27 billion of development cost. Meta leases it with a four-year initial term, extension options and a residual value guarantee for the first 16 years (Meta, October 2025).

Lease terms that protect the tenant

Delivery date and remedies
A guaranteed delivery date, interim milestones you can monitor, rent credits or liquidated damages for each day of delay, and a right to terminate if delivery slips past an outside date.
Rent and the cost basis
How rent is derived from project cost, which costs count, and whether there is a cap. Cost overruns the developer controls should not flow into your rent.
Change orders
How design changes after the scope freeze are priced and how they move the schedule. Agree the method before construction, not during it.
Specification and acceptance
The basis of design, the commissioning standard and what "delivered" means. Acceptance should follow integrated systems testing, not a certificate of occupancy.
Expansion land and power
Rights to additional phases on the same campus, with the power reserved and the pricing method agreed.
Operations and maintenance
Who operates which systems, to what standard, and how operating costs are passed through under a net lease.
Assignment, sublease and sale
Your rights to assign or sublease, and what happens to your protections if the developer sells the building, which is common once it is leased.
Credit support
The security the developer needs, such as a parent guarantee or letter of credit, sized to the risk rather than to the whole term.

For the terms every wholesale lease shares, from power minimums to holdover, see what a data center lease agreement contains.

Questions to ask a build-to-suit developer

  • Is the site under your control, and is it zoned for this use today?
  • What does the utility commit to, in writing, on megawatts and energization date?
  • Which long-lead electrical equipment is already reserved or on order?
  • What have you delivered before, at this scale, and how close to schedule?
  • Who are your capital partners, and is the financing committed or conditional on my lease?
  • How is rent calculated from cost, and what happens to rent if costs overrun?

Frequently asked questions

How long does a build-to-suit data center take?

It depends mostly on power and permitting. On a site with entitlements and a committed utility date, design and construction can run well under two years. On a site still waiting on a utility study or a rezoning, add years. The timeline section above shows how the phases stack up.

What is the difference between build-to-suit and powered shell?

In a build-to-suit the developer builds the complete facility to your design, including the critical infrastructure. In a powered shell the landlord delivers the building and power, and you build the inside.

How is build-to-suit rent calculated?

Usually from the total project cost, including land, power infrastructure, construction and financing, multiplied by the return the developer needs, then escalated over the term. Your negotiation is over the cost basis, the return, the escalator and who carries overruns.

Can a build-to-suit include expansion phases?

Yes, and it usually should. Reserve the land and the power for later phases in the lease, with the pricing method agreed now.

Sources

  1. Cushman & Wakefield, 2026 Data Center Development Cost Guide release, September 3, 2026, and 2026 Global Data Center Market Comparison, May 20, 2026.
  2. CBRE, US Real Estate Market Outlook 2026: Data Centers, December 2025, and Atlanta market chapter, H1 2026.
  3. JLL, Data center demand exceeds expectations in H1 2026, August 11, 2026.
  4. King & Spalding, Building data centers: key considerations, April 10, 2025.
  5. datacenterHawk, 2026 data center deal trends.
  6. CoreWeave, Form 10-K for 2025.
  7. Applied Digital, Form 10-K for the fiscal year ended May 31, 2026.
  8. Meta, Meta and Blue Owl Capital to develop Hyperion data center, October 21, 2025.

The rent implied by build cost and yield is our arithmetic, for illustration only.

Have a requirement measured in megawatts?

Send us the load, the markets and the date you need it energized. A senior advisor replies within one business day with the questions that matter and a plan for the search.

Our advisory is free to tenants. We are compensated by the provider you choose, and we disclose that on every shortlist. How we are paid