Wholesale data center advisory for tenants and landowners, from 1 MW to campus scale

Markets and policy

Data centers by state: compare development conditions

Pick a state to see its incentives, local moratoriums, utilities, power cost and who governs. Power costs cover all 50 states. Policy research covers 20 states and 30 cities and counties.

Start with your state

Pick a state to see only its conditions

Colors show each state's policy label from our 20-state review. Grey states have power costs only. Tap a state and the page narrows to it.

A label describes state incentives and recent restrictions, not site readiness or available power. What the labels mean.

Start your shortlist

Find and compare states

Compare incentives, utility obligations and local restrictions in 20 reviewed states.

What do the labels mean?

Coverage: 20 selected states. This initial research set is not a national ranking or a complete US directory. States outside this set are not assessed here. Base evidence snapshot: October 7, 2026. Texas has a targeted October 9 policy check; individual source dates still apply.

Which states are easier to apply in?

The incentive access score is 2 for an open application path, 1 for an additional approval process, or 0 for a pause. It does not measure incentive value or confirm eligibility. Permit and grid holds are shown first and kept separate when sorting. See the scoring rules and limits.

Default scenario: new facility, 50 MW utility demand. Unknown power, local approvals and incomplete utility coverage earn no points. States with unresolved incentive evidence are unscored.

Jump to a state and its sources

Use total facility utility demand, not IT load. Leave blank if unknown. MVA thresholds and load-factor conditions need separate confirmation.

For a new facility, check local permission, the serving utility's load threshold and a written power delivery date before relying on tax incentives. MW thresholds in the evidence refer to the stated utility or facility load; they are not interchangeable with IT load or MVA.

Policy labels describe state incentives and recent restrictions, not site readiness. Local rules still apply in an “Open” state. Industrial averages do not confirm your tariff or available power.

20 reviewed states, A to Z.

Alabama

Open with new conditions

Site approval and power unconfirmed.

Incentive application access
2 / 2: application path open. Rule and source

Compare Alabama utilities

Planning watchpointConfirm whether Alabama Power or a TVA distributor serves the site. Their obligations differ, and new incentive limits may affect the project schedule.

Industrial average
7.93¢/kWh
Listed facilities
45
Read evidence

Arizona

Tightening

Site approval and power unconfirmed.

Incentive application access
0 / 2: new applications paused. Rule and source

Compare Arizona utilities

Planning watchpointFor a new project, check incentive eligibility and the specific utility commitment before pricing land. Local siting decisions remain a separate hurdle.

Industrial average
7.66¢/kWh
Listed facilities
160
Read evidence

Site approval and power unconfirmed.

Incentive application access
2 / 2: application path open. Rule and source

Compare Arkansas utilities

Planning watchpointOpen state incentives do not establish local permission. Check the county or city moratorium and obtain utility terms for this project.

Industrial average
6.82¢/kWh
Listed facilities
12
Read evidence

Georgia

Open with new conditions

Site approval and power unconfirmed.

Incentive application access
2 / 2: application path open. Rule and source

Compare Georgia utilities

Planning watchpointConfirm local zoning and the utility delivery commitment first. An open incentive program does not establish that new power capacity is available.

Industrial average
7.99¢/kWh
Listed facilities
276
Read evidence

Illinois

Tightening

Site approval and power unconfirmed.

Incentive application access
0 / 2: new applications paused. Rule and source

Compare Illinois utilities

Planning watchpointCheck whether an incentive agreement already exists. New applications and large-load utility obligations need separate review.

Industrial average
10.24¢/kWh
Listed facilities
242
Read evidence

Indiana

Open with new conditions

Site approval and power unconfirmed.

Incentive application access
2 / 2: application path open. Rule and source

Compare Indiana utilities

Planning watchpointCheck the exact county and city rules, then the serving utility contract. The state incentive program does not override local pauses.

Industrial average
9.15¢/kWh
Listed facilities
125
Read evidence

Kentucky

Open with new conditions

Site approval and power unconfirmed.

Incentive application access
2 / 2: application path open. Rule and source

Compare Kentucky utilities

Planning watchpointCheck the local moratorium and the serving utility's load threshold. Contract length and collateral can materially affect the commitment.

Industrial average
7.50¢/kWh
Listed facilities
56
Read evidence

Louisiana

Open with new conditions

Site approval and power unconfirmed.

Incentive application access
1 / 2: additional approval process. Rule and source

Compare Louisiana utilities

Planning watchpointConfirm the current incentive application path and local siting rules before relying on state support. Request project-specific infrastructure terms.

Industrial average
6.65¢/kWh
Listed facilities
23
Read evidence

Mississippi

Open with new conditions

Site approval and power unconfirmed.

Incentive application access
2 / 2: application path open. Rule and source

Compare Mississippi utilities

Planning watchpointIdentify the serving utility before comparing costs. Check local permitting status and the requirements of the incentive program.

Industrial average
7.66¢/kWh
Listed facilities
25
Read evidence

Nevada

Tightening

Site approval and power unconfirmed.

Incentive application access
1 / 2: additional approval process. Rule and source

Compare Nevada utilities

Planning watchpointEstablish which incentive terms apply to the application and whether the local jurisdiction is accepting projects. Utility proposals still need approval.

Industrial average
8.43¢/kWh
Listed facilities
76
Read evidence

North Carolina

Tightening

Site approval and power unconfirmed.

Incentive application access
2 / 2: application path open. Rule and source

Compare North Carolina utilities

Planning watchpointBudget electricity separately from the equipment exemption. Check local pauses and the status of the proposed Duke large-load terms.

Industrial average
7.91¢/kWh
Listed facilities
97
Read evidence

Ohio

Tightening

Site approval and power unconfirmed.

Incentive application access
0 / 2: new applications paused. Rule and source

Compare Ohio utilities

Planning watchpointVerify the local moratorium and whether a prior incentive agreement covers the project. Confirm contract and exit obligations with the serving utility.

Industrial average
10.32¢/kWh
Listed facilities
240
Read evidence

Oklahoma

Open with new conditions

Site approval and power unconfirmed.

Incentive application access
2 / 2: application path open. Rule and source

Compare Oklahoma utilities

Planning watchpointCheck the load threshold, local or tribal jurisdiction and cooling-water approach. Separate pending utility tariffs from rules already in force.

Industrial average
6.69¢/kWh
Listed facilities
48
Read evidence

Pennsylvania

Tightening

Hold review required. Incentives do not clear the permit or grid-approval restriction. Rule and source

Incentive application access
1 / 2: additional approval process. Rule and source

Compare Pennsylvania utilities

Planning watchpointConfirm local approvals and the state permit and incentive pathway. Review the serving utility's load guarantees and upgrade security.

Industrial average
10.93¢/kWh
Listed facilities
174
Read evidence

South Carolina

Open with new conditions

Site approval and power unconfirmed.

Incentive application access
2 / 2: application path open. Rule and source

Compare South Carolina utilities

Planning watchpointCheck the county, serving utility and project size together. Incentive eligibility does not remove utility commitments or local restrictions.

Industrial average
7.85¢/kWh
Listed facilities
48
Read evidence

Tennessee

Open with new conditions

Site approval and power unconfirmed.

Incentive application access
2 / 2: application path open. Rule and source

Compare Tennessee utilities

Planning watchpointConfirm local permission and whether TVA service applies. Account for the capacity charge separately from ongoing electricity bills.

Industrial average
6.82¢/kWh
Listed facilities
65
Read evidence

Texas

Open with new conditions

Hold review required. Incentives do not clear the permit or grid-approval restriction. Rule and source

Incentive application access
2 / 2: application path open. Rule and source

Compare Texas utilities

Planning watchpointOpen for data center loads under 75 MW, which go through the local utility's approval process. ERCOT has paused energization of new loads of 75 MW or more. A separate directive holds TCEQ permits for data center projects of any size, so confirm which permits your site needs.

Industrial average
6.72¢/kWh
Listed facilities
537
Read evidence

Utah

Open with new conditions

Site approval and power unconfirmed.

Incentive application access
2 / 2: application path open. Rule and source

Compare Utah utilities

Planning watchpointCheck the serving utility's large-load rules, local jurisdiction and the timing of incentive changes. Confirm project-specific security and service terms.

Industrial average
8.58¢/kWh
Listed facilities
48
Read evidence

Virginia

Tightening

Site approval and power unconfirmed.

Incentive application access
2 / 2: application path open. Rule and source

Compare Virginia utilities

Planning watchpointModel the temporary electricity tax and applicable utility contract alongside incentives. Verify the county approval path for the particular site.

Industrial average
10.08¢/kWh
Listed facilities
674
Read evidence

Wisconsin

Open with new conditions

Site approval and power unconfirmed.

Incentive application access
2 / 2: application path open. Rule and source

Compare Wisconsin utilities

Planning watchpointConfirm utility territory and the local moratorium before using state incentives in a budget. Utility requirements are not uniform statewide.

Industrial average
9.39¢/kWh
Listed facilities
53
Read evidence

Listed facilities: Data Center Map, October 7, 2026; counts do not measure available capacity. Industrial prices: EIA, January-July 2026. Policy evidence and exceptions are linked in each state profile.

For landowners

Unlock your land's long-term value

Partner with a data center operator through a ground lease or development partnership. Our 25 years in data centers, deep industry roots and relationships with operator executives help landowners negotiate strong lease and partnership terms.

We have tenants lined up and ready to sign leases for the right locations, power capacity and delivery dates. Bring us your site so we can match it with active tenant demand and the operators positioned to deliver it.

Take the shortlist down to local approvals

Key cities and counties: compare the approval path

Search cities, counties and market areas, then compare up to three jurisdictions. Check who decides the land use, which restrictions are reported, and what evidence is still needed for your site.

30 selected jurisdictions across 11 states. Includes Northern Virginia, Phoenix, Atlanta, DFW, Central Ohio, Chicago, Charlotte, Hillsboro and selected contested locations. This is incomplete local coverage, not a nationwide ranking. Built October 10, 2026; each record retains its own evidence date. Oregon and Washington local entries do not add state-level policy assessments.

How to read local status and jurisdiction

Adopted moratorium: passage and operative text were reviewed; read the jurisdiction, exceptions and end conditions. Reported moratorium or ban: a source records a restriction; read its date, operative ordinance, exceptions and later amendments before applying it. Proposed restriction: no adopted outcome is established. Project decision: one case is not a blanket rule. Application path: a published process is not a claim that the site qualifies or that no restriction exists. Review needed: material evidence is unresolved.

A city, unincorporated county area, tribal jurisdiction and utility territory can have different boundaries. A metro name is a search aid, not a zoning authority. Regional tariff links do not confirm the serving utility, available capacity or a delivery date. Retained research was not fully re-audited; primary search excerpts are labeled when the full page could not be read.

30 local records, grouped by state.

Dates describe recorded hearings, votes or reported moratorium timing. They are not guaranteed reopening, project approval or energization dates. A general meeting is not a confirmed hearing for a data-center project.
City or countyLocal signal and evidence dateDates and next decisionApproval details
ChandlerArizona · City
Phoenix East Valley
Project decision

Retained city meeting records describe a denied data-center rezoning. The decision applies to that proposal.

2026-10-07 · Retained research

No next hearing or vote verified.

No next hearing or citywide moratorium endpoint established.

Authority, zoning, utilities and sources
Jurisdiction scope
City of Chandler; not a Phoenix-wide restriction.
Approval authority
Chandler City Council for the retained rezoning decision; planning staff for the current application path.
Zoning and approval route
Check the parcel's zoning and any required rezoning or special approval. A single denial does not establish a citywide ban.
Utility and water context
Confirm the provider, load threshold and power delivery date. SRP terms are regional background only.
Regional tariff research: Salt River Project (SRP). These entries do not assign the provider.
Dates and next decision
No next hearing or citywide moratorium endpoint established.
No next hearing or vote verified.
Evidence date and verification
2026-10-07. Retained research. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Get the case number, adopted vote and reasons, then the current rules for a different parcel.
PhoenixArizona · City
Phoenix metro
Zoning conditions

The city's July 2025 announcement establishes a Special Permit process addressing grid reliability, fire access and noise.

2026-10-10 · Primary source reviewed

No next hearing or vote verified.

No site-specific hearing date or subsequent ordinance change was verified.

Authority, zoning, utilities and sources
Jurisdiction scope
City of Phoenix; other Valley municipalities have their own rules.
Approval authority
City Planning and Development; Mayor and City Council adopted the July 2025 framework.
Zoning and approval route
Arrange early review with staff on facility location, power infrastructure and emergency response. A special permit is separate from an incentive certificate.
Utility and water context
Resolve the serving territory and large-load contract for the address. SRP is one retained Arizona tariff reference; this listing does not assign SRP to the site.
Regional tariff research: Salt River Project (SRP). These entries do not assign the provider.
Dates and next decision
No site-specific hearing date or subsequent ordinance change was verified.
No next hearing or vote verified.
Evidence date and verification
2026-10-10. Primary source reviewed. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Confirm the current ordinance text, permit decision authority and any large-water-user requirements.
Pinal CountyArizona · County
Phoenix / southern growth corridor
Project decision

Retained August 2026 county records describe a denied data-center rezoning, not a blanket prohibition across the county.

2026-10-07 · Retained research

No next hearing or vote verified.

No next project hearing verified.

Authority, zoning, utilities and sources
Jurisdiction scope
County zoning jurisdiction; incorporated cities must be checked separately.
Approval authority
Pinal County planning staff and Board of Supervisors for the retained rezoning vote.
Zoning and approval route
Resolve the jurisdiction and existing zoning before comparing the proposed use with the denied case.
Utility and water context
Electric and water providers vary by parcel. Obtain actual territory and capacity evidence; no provider assignment is made.
No regional utility entry linked; provider and terms remain unresolved.
Dates and next decision
No next project hearing verified.
No next hearing or vote verified.
Evidence date and verification
2026-10-07. Retained research. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Read the specific denial, current county ordinance, incorporated boundary and water-service conditions.
TucsonArizona · City
Tucson / southern Arizona
Zoning conditions

Retained city research records August 2026 large-scale data-center rules and the earlier rejection of Project Blue as proposed.

2026-10-07 · Retained research

No next hearing or vote verified.

A project-specific hearing and the exact current standards still need verification.

Authority, zoning, utilities and sources
Jurisdiction scope
City limits; Pima County and other incorporated areas require separate checks.
Approval authority
City Planning and Development Services and Mayor and Council for zoning decisions.
Zoning and approval route
The retained rules require planned-development zoning, residential separation and evidence of adequate water and power. A prior project denial is not a ban on every site.
Utility and water context
Obtain the electric-provider determination and water supply confirmation for the parcel. No Tucson provider is assigned in this directory.
No regional utility entry linked; provider and terms remain unresolved.
Dates and next decision
A project-specific hearing and the exact current standards still need verification.
No next hearing or vote verified.
Evidence date and verification
2026-10-07. Retained research. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Reopen the adopted city code and obtain the proposed site's zoning and resource-capacity evidence.
Clayton CountyGeorgia · County
Atlanta south
Moratorium reported

Retained reporting describes a county moratorium through 2026 and an exception for Lovejoy's separate jurisdiction.

2026-10-07 · Retained research

No next hearing or vote verified.

Through 2026 in the retained report; exact endpoint and later amendments remain unverified.

Authority, zoning, utilities and sources
Jurisdiction scope
Retained county pause excludes Lovejoy; verify the exact jurisdiction of the parcel.
Approval authority
County planning staff and governing board for county-controlled applications.
Zoning and approval route
Use the county resolution and city boundary together. The county exception does not establish permission under Lovejoy's own rules.
Utility and water context
Obtain the serving provider and a written service schedule; tax relief and local permission cannot establish power.
Regional tariff research: Georgia Power. These entries do not assign the provider.
Dates and next decision
Through 2026 in the retained report; exact endpoint and later amendments remain unverified.
No next hearing or vote verified.
Evidence date and verification
2026-10-07. Retained research. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Check the county-city boundary, moratorium text and local replacement rules.
Cobb CountyGeorgia · County
Atlanta northwest
Moratorium reported

Retained August reporting records a 180-day extension covering new data-center applications or permitting.

2026-10-07 · Retained research

No next hearing or vote verified.

The retained report describes an endpoint in early February 2027; the exact day and subsequent amendments are unverified.

Authority, zoning, utilities and sources
Jurisdiction scope
County-controlled applications; incorporated city limits require separate confirmation.
Approval authority
County Board of Commissioners and land-use staff; exact moratorium jurisdiction needs the resolution.
Zoning and approval route
Do not submit on the assumption that industrial zoning overrides the pause. Obtain the operative resolution and exceptions.
Utility and water context
Compare regional utility requirements only after establishing the provider and facility demand at the address.
Regional tariff research: Georgia Power; GreyStone Power. These entries do not assign the provider.
Dates and next decision
The retained report describes an endpoint in early February 2027; the exact day and subsequent amendments are unverified.
No next hearing or vote verified.
Evidence date and verification
2026-10-07. Retained research. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Reopen the county resolution, scope, vested-application exceptions and extension calendar.
Coweta CountyGeorgia · County
Atlanta southwest
Approval with litigation reported

Retained reporting describes a 3-to-2 campus rezoning approval and a residents' lawsuit seeking to void it.

2026-10-07 · Retained research

No next hearing or vote verified.

No court deadline or next hearing verified.

Authority, zoning, utilities and sources
Jurisdiction scope
The retained county campus rezoning case; separate jurisdictions must be checked.
Approval authority
County governing board for rezoning; court proceedings are a separate approval risk.
Zoning and approval route
An adopted rezoning and unresolved litigation can coexist. Obtain the current court status before treating entitlement as final.
Utility and water context
Confirm the electric provider, water availability and upgrade obligations for the approved design.
Regional tariff research: Georgia Power. These entries do not assign the provider.
Dates and next decision
No court deadline or next hearing verified.
No next hearing or vote verified.
Evidence date and verification
2026-10-07. Retained research. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Check the final order, litigation docket, stays and remaining site-plan approvals.
DeKalb CountyGeorgia · County
Atlanta east
Moratorium reported

Retained reporting records an extension of the data-center moratorium through March 30, 2027.

2026-10-07 · Retained research

No next hearing or vote verified.

March 30, 2027 is the reported endpoint, not a promised construction or utility service date.

Authority, zoning, utilities and sources
Jurisdiction scope
County-controlled land-use applications; municipal boundaries require a separate check.
Approval authority
County governing board and planning staff; verify application and permit scope in the adopted resolution.
Zoning and approval route
Obtain the ordinance before deciding which filings, expansions or existing approvals remain eligible.
Utility and water context
Serving territory and capacity are unconfirmed. Georgia tariff references are background, not a county-wide provider designation.
Regional tariff research: Georgia Power. These entries do not assign the provider.
Dates and next decision
March 30, 2027 is the reported endpoint, not a promised construction or utility service date.
No next hearing or vote verified.
Evidence date and verification
2026-10-07. Retained research. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Check adopted scope, exceptions, later extensions and the applicable city or county authority.
Douglas CountyGeorgia · County
Atlanta west
Project decision

Retained July reporting describes denial of a data-center rezoning involving more than 700 acres.

2026-10-07 · Retained research

No next hearing or vote verified.

No next project hearing verified.

Authority, zoning, utilities and sources
Jurisdiction scope
The retained county rezoning case; other parcels and incorporated cities need separate review.
Approval authority
County land-use staff and governing board for the rezoning application.
Zoning and approval route
Review the vote, staff findings and parcel conditions. That case is not proof of a countywide ban.
Utility and water context
Identify the actual provider and study obligations. Georgia Power and GreyStone are regional tariff references, not an assignment.
Regional tariff research: Georgia Power; GreyStone Power. These entries do not assign the provider.
Dates and next decision
No next project hearing verified.
No next hearing or vote verified.
Evidence date and verification
2026-10-07. Retained research. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Obtain the adopted case decision and compare the proposed site's zoning, resources and access.
LovejoyGeorgia · City
Atlanta south / Clayton County
Ban reported

Retained October reporting describes a city data-center ban adopted September 21, 2026.

2026-10-07 · Retained research

No next hearing or vote verified.

No expiration or scheduled reconsideration verified.

Authority, zoning, utilities and sources
Jurisdiction scope
City of Lovejoy; separate from Clayton County's moratorium scope.
Approval authority
City governing body and zoning staff; obtain the adopted prohibition text.
Zoning and approval route
Do not read Clayton County's Lovejoy exclusion as approval. Confirm the city's prohibited-use definition and any existing-project treatment.
Utility and water context
A utility service inquiry does not overcome a prohibited local use. Provider and available capacity are unconfirmed.
Regional tariff research: Georgia Power. These entries do not assign the provider.
Dates and next decision
No expiration or scheduled reconsideration verified.
No next hearing or vote verified.
Evidence date and verification
2026-10-07. Retained research. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Get the enacted ordinance, effective date, exceptions and city boundary.
Paulding CountyGeorgia · County
Atlanta west
Moratorium reported

Retained reporting describes a pause on new data-center proposals to January 1, 2027.

2026-10-07 · Retained research

No next hearing or vote verified.

January 1, 2027 is the retained reported endpoint. Recheck before assuming applications reopen.

Authority, zoning, utilities and sources
Jurisdiction scope
County land-use jurisdiction; cities within the county need their own checks.
Approval authority
County governing board and planning staff; obtain the adopted pause language.
Zoning and approval route
Confirm whether a new application or expansion falls inside the pause and whether any prior rights apply.
Utility and water context
Verify electric and water providers, load thresholds and connection studies for the site.
Regional tariff research: Georgia Power; GreyStone Power. These entries do not assign the provider.
Dates and next decision
January 1, 2027 is the retained reported endpoint. Recheck before assuming applications reopen.
No next hearing or vote verified.
Evidence date and verification
2026-10-07. Retained research. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Confirm the current resolution, exceptions and any replacement zoning standards.
Champaign CountyIllinois · County
Champaign-Urbana region
Moratorium reported

Retained April reporting describes a one-year data-center moratorium.

2026-10-07 · Retained research

No next hearing or vote verified.

One year in the retained report; exact effective and end dates and next hearing remain unverified.

Authority, zoning, utilities and sources
Jurisdiction scope
Unincorporated county areas in the retained research; cities have separate ordinances.
Approval authority
County Board and county zoning staff; exact ordinance scope must be confirmed.
Zoning and approval route
Read the adopted county ordinance before deciding whether a new site or expansion is affected. Do not apply the county pause to Champaign or Urbana city limits automatically.
Utility and water context
The provider and current large-load terms are not established for a specific parcel. No regional utility entry is assigned here.
No regional utility entry linked; provider and terms remain unresolved.
Dates and next decision
One year in the retained report; exact effective and end dates and next hearing remain unverified.
No next hearing or vote verified.
Evidence date and verification
2026-10-07. Retained research. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Obtain the signed ordinance, exception language, boundary and any subsequent extension.
ChicagoIllinois · City
Chicago metro
Proposed restriction

Retained September reporting describes a mayor-proposed 12-month data-center pause sent to the council rules committee.

2026-10-07 · Retained research

No next hearing or vote verified.

No committee hearing, final vote or fixed effective date verified.

Authority, zoning, utilities and sources
Jurisdiction scope
City of Chicago; suburban municipal and county rules are separate.
Approval authority
City Council for the proposed moratorium; city land-use and building departments for applicable approvals.
Zoning and approval route
Do not treat the introduced proposal as an effective ban. Confirm any later Council action and the current zoning classification.
Utility and water context
ComEd terms are a regional tariff reference. Obtain the actual service agreement, load threshold and collateral requirements.
Regional tariff research: ComEd. These entries do not assign the provider.
Dates and next decision
No committee hearing, final vote or fixed effective date verified.
No next hearing or vote verified.
Evidence date and verification
2026-10-07. Retained research. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Check the current Council docket and signed ordinance before changing the site's approval assumptions.
Lake CountyIllinois · County
Chicago north suburbs
Moratorium adopted

Ordinance 26-1018, adopted September 8, prohibits data centers in unincorporated Lake County until May 11, 2027, or earlier County Board adoption of the resulting regulations. The reviewed October 13 agenda contains no titled data-center moratorium amendment or extension item.

2026-10-10 · Primary source reviewed

No next hearing or vote verified.

Adopted September 8, 2026, effective immediately. Section 151.011(D)(2) sets May 11, 2027, or earlier adoption of resulting regulations as the end condition. The final October 13 County Board agenda was reviewed and contains no titled data-center moratorium change item; no next data-center ordinance hearing or extension is established by that agenda.

Authority, zoning, utilities and sources
Jurisdiction scope
Unincorporated Lake County only. Incorporated municipalities have their own rules.
Approval authority
County Board; county zoning bodies participate in ordinance review.
Zoning and approval route
Adopted Exhibit B adds a data-center definition and UDO section 151.011(D). It prohibits data centers in unincorporated areas and says those proposed after the effective date will not be considered until the moratorium expires. The definition includes a facility or part of a facility housing data equipment and associated power, generation and cooling infrastructure. Section (D) states no internal-use carveout or MW threshold. It does not establish that every earlier proposal is exempt; obtain a determination for the actual application's timing and approvals. Incorporated municipalities apply their own rules.
Utility and water context
Confirm the address and utility territory. ComEd is a regional reference and does not establish the parcel's capacity or agreement.
Regional tariff research: ComEd. These entries do not assign the provider.
Dates and next decision
Adopted September 8, 2026, effective immediately. Section 151.011(D)(2) sets May 11, 2027, or earlier adoption of resulting regulations as the end condition. The final October 13 County Board agenda was reviewed and contains no titled data-center moratorium change item; no next data-center ordinance hearing or extension is established by that agenda.
No next hearing or vote verified.
Evidence date and verification
2026-10-10. Primary source reviewed. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Confirm whether the parcel is unincorporated, whether the proposed use falls within the adopted definition, and the treatment of any pre-effective-date proposal or approval. The reviewed agenda does not establish an extension or a future regulatory adoption date.
New OrleansLouisiana · City
New Orleans / southeast Louisiana
Ban reported

Retained city planning research records a restriction on new data centers and a proposal to permanently prohibit large and hyperscale facilities.

2026-10-07 · Retained research

2026-10-13: Reported hearing. Planning Commission hearing in retained research; proposed permanent standards are not an adopted outcome.

Retained city materials list an October 13 hearing; current agenda and outcome need confirmation.

Authority, zoning, utilities and sources
Jurisdiction scope
City of New Orleans; other parishes have their own land-use authority.
Approval authority
City Planning Commission for the reviewed proposal and City Council for applicable ordinance adoption.
Zoning and approval route
Existing restrictions and a proposed permanent code change are separate actions. Confirm the adopted use definition and any grandfathering.
Utility and water context
Electric provider and available capacity are unconfirmed for the parcel. State incentive invitation and local zoning are separate approvals.
No regional utility entry linked; provider and terms remain unresolved.
Dates and next decision
Retained city materials list an October 13 hearing; current agenda and outcome need confirmation.
2026-10-13: Reported hearing. Planning Commission hearing in retained research; proposed permanent standards are not an adopted outcome.
Evidence date and verification
2026-10-07. Retained research. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Reopen the October 13 agenda and the operative ordinance. The previously saved primary page could not be reopened in this pass.
CharlotteNorth Carolina · City
Charlotte metro
Moratorium adopted

The June 8 ordinance pauses new telecommunications and data storage facilities until November 5 or earlier adoption of new regulations or policies. Internal-use and statutory exceptions apply. The October 12 agenda sets an extension hearing; October 26 is the stated consideration target, with no adopted extension established.

2026-10-10 · Primary source reviewed

2026-10-12: Extension hearing. Agenda item 11: extension hearing, 5 p.m., Council Chamber. October 26 is the stated ordinance-consideration target; no extension has been established as adopted.

Adopted and effective June 8, 2026; section 1 ends the pause no later than November 5 or upon earlier adoption of new regulations or policies. October 12 Council agenda item 11, file 15-26825, schedules the extension hearing at 5 p.m. in the Council Chamber and identifies October 26 for Council consideration of an extension ordinance. Neither agenda notice adopts an extension or establishes a new endpoint. G.S. 160D-107(e) requires findings about reasonable progress and new facts or conditions for an extension.

Authority, zoning, utilities and sources
Jurisdiction scope
City and its extraterritorial jurisdiction under section 1 of the adopted ordinance; other Mecklenburg municipalities are separate.
Approval authority
City Council for the moratorium and extension; city development staff for applications.
Zoning and approval route
Section 1 pauses acceptance, processing and approval of new telecommunications and data storage facilities in the city and ETJ. It exempts facilities primarily supporting internal operations of an institution, government agency, healthcare facility, telecommunications provider or other permitted principal use, provided data processing is not primarily a service to off-site users. Section 2 incorporates N.C. G.S. 160D-107(c). Absent an imminent public-health or safety threat, statutory exceptions cover valid outstanding building permits, complete special-use applications, approved site-specific vesting plans, substantial good-faith expenditures relying on a prior valid development approval, and subdivision plats accepted for review before the hearing was called. A pending application alone does not establish exemption; complete applications before the effective date have separate statutory treatment when processing resumes. Obtain written eligibility confirmation for the actual use and approvals.
Utility and water context
Obtain provider territory, water/sewer approvals and an actual capacity study. Duke Energy is a regional reference, not an address assignment.
Regional tariff research: Duke Energy. These entries do not assign the provider.
Dates and next decision
Adopted and effective June 8, 2026; section 1 ends the pause no later than November 5 or upon earlier adoption of new regulations or policies. October 12 Council agenda item 11, file 15-26825, schedules the extension hearing at 5 p.m. in the Council Chamber and identifies October 26 for Council consideration of an extension ordinance. Neither agenda notice adopts an extension or establishes a new endpoint. G.S. 160D-107(e) requires findings about reasonable progress and new facts or conditions for an extension.
2026-10-12: Extension hearing. Agenda item 11: extension hearing, 5 p.m., Council Chamber. October 26 is the stated ordinance-consideration target; no extension has been established as adopted.
Evidence date and verification
2026-10-10. Primary source reviewed. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Confirm parcel jurisdiction, internal-use facts and any statutory exception in writing. Recheck the October 12 hearing record and October 26 adoption record before assuming a new expiration date or setting a filing date.
ColumbusOhio · City
Central Ohio
Review needed

The official search excerpt identifies ongoing Phase 2 zoning modernization. The detailed current data-center use rules were not readable in this review.

2026-10-10 · Primary search excerpt

No next hearing or vote verified.

No data-center-specific hearing or adoption date verified.

Authority, zoning, utilities and sources
Jurisdiction scope
City of Columbus; New Albany and other suburbs have separate zoning authority.
Approval authority
City building and zoning staff and the applicable city legislative process; precise project route unresolved.
Zoning and approval route
Compare existing adopted zoning with proposed Zone In text. A draft map must not be treated as current entitlement.
Utility and water context
Determine the parcel's provider and large-load eligibility. AEP Ohio is a regional reference; other service territories and agreements may apply.
Regional tariff research: AEP Ohio (Ohio Power). These entries do not assign the provider.
Dates and next decision
No data-center-specific hearing or adoption date verified.
No next hearing or vote verified.
Evidence date and verification
2026-10-10. Primary search excerpt. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
The full primary page returned 403. Obtain current code, draft status and the official project calendar.
New AlbanyOhio · City
Central Ohio / New Albany business park
Zoning conditions

The city FAQ identifies data centers as permitted in General Employment and Technology Manufacturing districts, with design, buffering and noise standards.

2026-10-10 · Primary source reviewed

2026-10-19: General meeting. Planning Commission meeting listed. No site-specific data-center hearing is confirmed.

The Commission calendar lists October 19; a data-center item for your site is not established.

Authority, zoning, utilities and sources
Jurisdiction scope
City of New Albany; a Columbus metro location is not Columbus zoning jurisdiction.
Approval authority
City planning staff, Planning Commission and City Council for zoning matters; qualifying generation uses the separate Ohio Power Siting Board process.
Zoning and approval route
Read the parcel's district and limited-overlay text. Local land-use review is separate from state review of qualifying onsite generation.
Utility and water context
The city names AEP and The Energy Cooperative as primary business-park electric providers, and Columbus for contracted water/sewer. Confirm the parcel and provider before applying AEP DCT.
Regional tariff research: AEP Ohio (Ohio Power). These entries do not assign the provider.
Dates and next decision
The Commission calendar lists October 19; a data-center item for your site is not established.
2026-10-19: General meeting. Planning Commission meeting listed. No site-specific data-center hearing is confirmed.
Evidence date and verification
2026-10-10. Primary source reviewed. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Obtain district/overlay compliance, site-plan decisions and the provider's written capacity and delivery commitments.
HillsboroOregon · City
Portland west / Silicon Forest
Moratorium reported

The official July 27 announcement's search excerpt reports a 120-day land-use pause for new or expanded data centers and BESS facilities proposed as a primary use.

2026-10-10 · Primary search excerpt

No next hearing or vote verified.

120 days from the July action in the official excerpt. No exact ending day, extension or next hearing verified.

Authority, zoning, utilities and sources
Jurisdiction scope
City of Hillsboro; Washington County and nearby cities are separate authorities.
Approval authority
City Council for the moratorium and code changes; city land-use staff for applications.
Zoning and approval route
The local land-use pause is separate from Oregon's data-center Enterprise Zone agreement pause. Verify exceptions and any later extension.
Utility and water context
Serving utility, current large-load obligations and available capacity are not established for a parcel in this directory.
No regional utility entry linked; provider and terms remain unresolved.
Dates and next decision
120 days from the July action in the official excerpt. No exact ending day, extension or next hearing verified.
No next hearing or vote verified.
Evidence date and verification
2026-10-10. Primary search excerpt. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Full announcement returned 403. Obtain the adopted resolution and current city land-use calendar.
Source record
State policy not assessed on this page.
MemphisTennessee · City
Memphis / western Tennessee
Proposed restriction

Retained October reporting says the Council postponed a moratorium vote to October 20. No adopted pause is established by that report.

2026-10-07 · Retained research

2026-10-20: Reported vote. Moratorium vote reported as postponed to this date. Current official agenda not reverified.

October 20 is the retained reported vote date; verify the current agenda and any rescheduling.

Authority, zoning, utilities and sources
Jurisdiction scope
City of Memphis; Shelby County and other municipalities need separate checks.
Approval authority
City Council for the proposed moratorium; local development authorities for site approvals.
Zoning and approval route
Check the final vote and exact zoning/permit scope. A postponement does not establish either approval or a moratorium.
Utility and water context
MLGW and TVA research covers separate retail and wholesale roles. Confirm MLGW territory and the actual retail and upstream commitments for the project.
Regional tariff research: Memphis Light, Gas and Water; TVA wholesale network. These entries do not assign the provider.
Dates and next decision
October 20 is the retained reported vote date; verify the current agenda and any rescheduling.
2026-10-20: Reported vote. Moratorium vote reported as postponed to this date. Current official agenda not reverified.
Evidence date and verification
2026-10-07. Retained research. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Reopen the Council agenda and final decision, then check zoning and MLGW requirements separately.
DallasTexas · City
Dallas-Fort Worth / DFW
Application path

The city publishes a zoning-change pathway and DallasNow case records. This process page does not establish data-center eligibility or absence of restrictions.

2026-10-10 · Primary source reviewed

No next hearing or vote verified.

Search the specific case in DallasNow and the CPC docket; no project hearing date is assigned here.

Authority, zoning, utilities and sources
Jurisdiction scope
City of Dallas; not all sites in Dallas County or the DFW metro.
Approval authority
Planning and Development staff, City Plan Commission recommendation, then City Council for zoning changes.
Zoning and approval route
Confirm Chapter 51A use classification and district permissions. Zoning changes proceed through staff review and two public-hearing stages.
Utility and water context
Oncor terms are a regional reference; the parcel's provider, connection and state approval requirements still need confirmation.
Regional tariff research: Oncor. These entries do not assign the provider.
Dates and next decision
Search the specific case in DallasNow and the CPC docket; no project hearing date is assigned here.
No next hearing or vote verified.
Evidence date and verification
2026-10-10. Primary source reviewed. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Obtain a written use determination and parcel case record. A permit filing is not an approval or available-power commitment.
Fort WorthTexas · City
Dallas-Fort Worth / DFW
Application path

The city's zoning page describes case hearings and Council decisions. Data-center-specific eligibility and any later restrictions remain unresolved.

2026-10-10 · Primary source reviewed

No next hearing or vote verified.

Project-specific meeting and permit outcomes are not verified by this directory.

Authority, zoning, utilities and sources
Jurisdiction scope
City of Fort Worth; adjacent municipalities and county areas have separate authority.
Approval authority
Development Services, Zoning Commission recommendation and City Council for zoning changes.
Zoning and approval route
Use the parcel zoning, current use table and case record. A recorded planning or building application does not establish permission to energize.
Utility and water context
Confirm the distribution provider and the full service request. Regional Oncor research does not establish capacity or a service date.
Regional tariff research: Oncor. These entries do not assign the provider.
Dates and next decision
Project-specific meeting and permit outcomes are not verified by this directory.
No next hearing or vote verified.
Evidence date and verification
2026-10-10. Primary source reviewed. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Read the current data-center classification, zoning case disposition and any adopted code amendment.
Hill CountyTexas · County
Central Texas / south of DFW
Moratorium rescinded

Reopened reporting records a May 2026 moratorium rescinded in June after a developer lawsuit.

2026-10-10 · Secondary source reviewed

No next hearing or vote verified.

No later county action or court outcome verified.

Authority, zoning, utilities and sources
Jurisdiction scope
County action; incorporated cities and state requirements remain separate.
Approval authority
Commissioners Court for the reported moratorium action; confirm its actual permitting powers for the site.
Zoning and approval route
Rescission removes that reported pause only. It does not create a zoning approval, legal entitlement or grid clearance.
Utility and water context
Provider and capacity unconfirmed. Request territory verification and study requirements instead of assuming the local change clears ERCOT or TCEQ.
No regional utility entry linked; provider and terms remain unresolved.
Dates and next decision
No later county action or court outcome verified.
No next hearing or vote verified.
Evidence date and verification
2026-10-10. Secondary source reviewed. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Obtain the rescission and current county permitting requirements, plus the state and utility approval record.
Hood CountyTexas · County
DFW southwest / Granbury area
Proposal rejected

Reopened reporting says the county rejected two attempts to enact a countywide moratorium. These were rejected moratorium proposals, not two denied data-center projects.

2026-10-10 · Secondary source reviewed

No next hearing or vote verified.

No next proposal vote or project hearing verified.

Authority, zoning, utilities and sources
Jurisdiction scope
County action; cities and other authorities require separate checks.
Approval authority
Commissioners Court for the moratorium proposals; the scope of county legal authority was contested in the report.
Zoning and approval route
Do not treat the failed moratorium as project approval. Identify the actual permit, municipal zoning and state requirements for the parcel.
Utility and water context
No provider or capacity assignment. Texas utility territory and statewide permit/grid processes remain independent.
No regional utility entry linked; provider and terms remain unresolved.
Dates and next decision
No next proposal vote or project hearing verified.
No next hearing or vote verified.
Evidence date and verification
2026-10-10. Secondary source reviewed. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Read current minutes and the legal authority for each required local approval.
San MarcosTexas · City
Central Texas / Austin-San Antonio corridor
Ban reported

Reopened Texas Tribune reporting identifies San Marcos's June 2026 action to restrict data-center development within the city.

2026-10-10 · Secondary source reviewed

No next hearing or vote verified.

No expiration or reconsideration date established.

Authority, zoning, utilities and sources
Jurisdiction scope
City limits; projects outside them need their own authority review.
Approval authority
City Council and city zoning staff. County and state powers are separate.
Zoning and approval route
Read the adopted prohibited-use language, exceptions and existing approvals. Do not extend the city action to all of Hays County.
Utility and water context
Identify the serving provider and water supplier for the parcel. Local prohibition and the separate Texas state holds must both be checked.
No regional utility entry linked; provider and terms remain unresolved.
Dates and next decision
No expiration or reconsideration date established.
No next hearing or vote verified.
Evidence date and verification
2026-10-10. Secondary source reviewed. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Obtain the enacted city ordinance and current boundary; secondary reporting does not replace a use determination.
WilmerTexas · City
Dallas-Fort Worth / DFW south
Review needed

The official January 2026 meeting search excerpt discusses parcel-specific industrial and data-center zoning ordinances. The final disposition was not verified.

2026-10-10 · Primary search excerpt

No next hearing or vote verified.

No current case hearing or vote outcome established.

Authority, zoning, utilities and sources
Jurisdiction scope
City of Wilmer; a Dallas County address alone does not establish this jurisdiction.
Approval authority
City Council and planning staff for parcel-specific zoning ordinances.
Zoning and approval route
Obtain the signed planned-district ordinance and current zoning map for the site. An advertised data-center zoning description is not a city determination.
Utility and water context
Establish the electric provider and state approval path at the parcel. Regional Oncor terms do not assign the site.
Regional tariff research: Oncor. These entries do not assign the provider.
Dates and next decision
No current case hearing or vote outcome established.
No next hearing or vote verified.
Evidence date and verification
2026-10-10. Primary search excerpt. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Full meeting page could not be read. Obtain adopted ordinances and minutes; do not infer approval from discussion.
Fairfax CountyVirginia · County
Northern Virginia / Chantilly
Zoning conditions

The September 2024 amendment adds setbacks, screening and noise studies. Larger developments require special exceptions, with I-5 and I-6 district exceptions.

2026-10-10 · Primary source reviewed

No next hearing or vote verified.

No project-specific hearing or later amendment outcome was verified in this pass.

Authority, zoning, utilities and sources
Jurisdiction scope
County zoning jurisdiction; Fairfax City is a separate government.
Approval authority
County planning staff and Board of Supervisors for special exceptions.
Zoning and approval route
Published standards include a 200-foot building setback from residential property, a 300-foot equipment separation or building shielding, and pre/post-construction noise studies. Lesser distances may require special exceptions.
Utility and water context
Verify the serving utility and service agreement before modeling the site. Northern Virginia tariff references do not prove this parcel's provider.
Regional tariff research: Dominion Energy Virginia; NOVEC HV-1. These entries do not assign the provider.
Dates and next decision
No project-specific hearing or later amendment outcome was verified in this pass.
No next hearing or vote verified.
Evidence date and verification
2026-10-10. Primary source reviewed. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Check current district permissions, Metro-station distance, site plan and any later code changes.
Loudoun CountyVirginia · County
Northern Virginia / Ashburn
Zoning conditions

The current use table requires Special Exception approval in OP, IP, GI and MR-HI districts, subject to its footnotes and grandfathering. The October 6 action report records no repeal of grandfathering; a separate pause on final Board votes remains proposed.

2026-10-10 · Primary source reviewed

2026-10-20: Proposed-policy vote. County notice schedules pause consideration; calendar confirms the meeting. Detailed agenda and adopted terms not yet established.

October 6, item 10.a: the Board tabled an independent-audit motion indefinitely, 7-2; no grandfathering repeal is recorded. Proposed audit report dates in January/April 2027 were not adopted deadlines. The county notice schedules pause consideration for October 20; the calendar confirms that business meeting, but its detailed agenda was not published in the reviewed listing. The proposed pause excludes administrative processing and may allow grid-reliability/statutory-deadline exceptions; final terms remain unadopted.

Authority, zoning, utilities and sources
Jurisdiction scope
County zoning jurisdiction; incorporated towns need a separate authority check.
Approval authority
County Planning and Zoning, Planning Commission and Board of Supervisors for legislative approvals.
Zoning and approval route
Table 3.02.05-1, effective March 18, 2025, lists data centers as Special Exception uses. Footnote 3 allows qualifying minor changes to approved site plans without a new SPEX. Footnote 4 deems certain ZMAP/ZCPA/ZRTD approvals on or before March 18, 2025 to include a SPEX only where specific proffers/CDP detail and limit the approval to the data-center use. Separately, the signed grandfathering resolution covers eligible applications officially accepted on or before February 12, 2025. Administrative applications require prior by-right permission and proposed structures/external mechanical equipment more than 500 feet from residential structures existing on that date; qualifying revisions to meet that distance are allowed. Both administrative and legislative protection require diligent pursuit and no defined substantial modifications. For administrative applications, required compliant materials must be submitted within three years of February 12, 2025; six-month response rules also apply. Protection covers the use table, not all other ordinances. Obtain a written determination for the actual application.
Utility and water context
Confirm the address, delivery voltage and study with the actual provider. Dominion and NOVEC terms are regional references, not a parcel assignment.
Regional tariff research: Dominion Energy Virginia; NOVEC HV-1; NOVEC HV-2. These entries do not assign the provider.
Dates and next decision
October 6, item 10.a: the Board tabled an independent-audit motion indefinitely, 7-2; no grandfathering repeal is recorded. Proposed audit report dates in January/April 2027 were not adopted deadlines. The county notice schedules pause consideration for October 20; the calendar confirms that business meeting, but its detailed agenda was not published in the reviewed listing. The proposed pause excludes administrative processing and may allow grid-reliability/statutory-deadline exceptions; final terms remain unadopted.
2026-10-20: Proposed-policy vote. County notice schedules pause consideration; calendar confirms the meeting. Detailed agenda and adopted terms not yet established.
Evidence date and verification
2026-10-10. Primary source reviewed. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Obtain the application's acceptance record, zoning regime, approved proffers/CDP, distance evidence and written grandfathering/vesting determination. Recheck the October 20 packet and any adopted pause; the audit was tabled and does not validate individual projects.
Prince William CountyVirginia · County
Northern Virginia / Manassas area
Zoning conditions

The county's current page distinguishes eligible parcels inside the revised overlay from new proposals outside it. Some eligible overlay parcels retain by-right permissions.

2026-10-10 · Primary source reviewed

No next hearing or vote verified.

Effective dates, transition provisions and a project-specific hearing are not established by this summary page.

Authority, zoning, utilities and sources
Jurisdiction scope
County zoning jurisdiction; independent cities such as Manassas are separate.
Approval authority
County Planning Office and Board of County Supervisors; confirm the specific SUP or overlay pathway.
Zoning and approval route
Outside the overlay, the listed commercial and industrial districts use a Special Use Permit path. Do not apply a blanket claim that all by-right rights ended.
Utility and water context
Establish Dominion or NOVEC territory from the parcel and service request. A local SUP does not establish grid capacity or the utility contract.
Regional tariff research: Dominion Energy Virginia; NOVEC HV-1; NOVEC HV-2. These entries do not assign the provider.
Dates and next decision
Effective dates, transition provisions and a project-specific hearing are not established by this summary page.
No next hearing or vote verified.
Evidence date and verification
2026-10-10. Primary source reviewed. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Get the adopted overlay map, eligibility determination and transition language for the exact parcel.
Kittitas CountyWashington · County
Central Washington / upper Kittitas Valley
Review needed

Existing county notes record an August emergency pause. The reopened official notice confirms a September 15 hearing on a six-month extension, but not its outcome.

2026-10-10 · Primary source reviewed

2026-09-15: Past hearing (past; verify outcome). Six-month extension hearing notice. Decision and current moratorium end date unresolved.

September 15 is a past hearing, not a future event or confirmed extension endpoint.

Authority, zoning, utilities and sources
Jurisdiction scope
Unincorporated county areas in retained notes; Cle Elum and Ellensburg have separate city authority.
Approval authority
Board of County Commissioners and Community Development Services.
Zoning and approval route
Do not assume either expiration or extension from the notice alone. Read the original resolution and subsequent minutes for unincorporated land.
Utility and water context
Existing notes identify multiple county providers; exact electric and water territories and available capacity remain unconfirmed.
No regional utility entry linked; provider and terms remain unresolved.
Dates and next decision
September 15 is a past hearing, not a future event or confirmed extension endpoint.
2026-09-15: Past hearing (past; verify outcome). Six-month extension hearing notice. Decision and current moratorium end date unresolved.
Evidence date and verification
2026-10-10. Primary source reviewed. Reopening an old announcement is not proof that no later rule changed.
What remains unresolved
Obtain the September 15 adopted decision and any separate city development agreement or exemption.
Source record
State policy not assessed on this page.
Near-term meetings and votes recorded in the research
  • 2026-10-12 · Charlotte: Extension hearing. Agenda item 11: extension hearing, 5 p.m., Council Chamber. October 26 is the stated ordinance-consideration target; no extension has been established as adopted. Local record and source.
  • 2026-10-13 · New Orleans: Reported hearing. Planning Commission hearing in retained research; proposed permanent standards are not an adopted outcome. Local record and source.
  • 2026-10-19 · New Albany: General meeting. Planning Commission meeting listed. No site-specific data-center hearing is confirmed. Local record and source.
  • 2026-10-20 · Memphis: Reported vote. Moratorium vote reported as postponed to this date. Current official agenda not reverified. Local record and source.
  • 2026-10-20 · Loudoun County: Proposed-policy vote. County notice schedules pause consideration; calendar confirms the meeting. Detailed agenda and adopted terms not yet established. Local record and source.

Snapshot: October 10, 2026. Event listings distinguish primary notices, retained news reports and general meetings. Confirm the latest agenda before relying on any date. Dates are maintained manually.

Download the local evidence records (JSON). For a shortlist, obtain the adopted ordinance, parcel zoning, hearing/case number, provider confirmation and written capacity schedule. Use the site approval checklist.

Put the difference in dollars

Power benchmarks for all 50 states

Compare the same annual load across states, with the previous year's benchmark beside it.

50-state power coverage; 20-state policy coverage. Prices are preliminary industrial-sector averages for January to July 2026, released September 24, 2026. The other 30 states have no incentive, utility-access or local-policy assessment on this page. DC appears separately below.

Default illustration: 20 MW installed IT capacity, PUE 1.30, 90% average IT utilization. All 50 states shown.

Average facility demand
23.4 MW
Annual facility energy
204,984 MWh
Annual impact of 1¢/kWh
$2,049,840
US benchmark illustration
$18,510,055

Calculation: installed IT MW × utilization × PUE × 1,000 × 8,760 = annual facility kWh. Utilization here means average IT electrical demand as a share of installed IT power capacity, not CPU or GPU busy time. Multiply by the industrial average in dollars/kWh. PUE is held constant for this screen; partial-load efficiency, fixed idle loads, monthly demand, a phased ramp and onsite generation are not modeled. These inputs do not change the separate facility-utility-demand policy screen.

Illustrative spend, not a utility bill. EIA reports electricity revenue divided by sales, so the average is not an energy-only charge. Do not add a generic demand charge to this result. Use the site operating cost estimator for actual energy, demand, rider and tax inputs. This screen applies no new tax, exemption, upgrade, rent or financing adjustment.

EIA Electric Power Monthly, Table 5.6.B, January to July 2026 versus January to July 2025. Negative dollar differences are below the US benchmark, not guaranteed savings. EIA source; reviewed October 9, 2026. Sorting by price is not a ranking of site suitability.
State2026 ¢/kWh2025 ¢/kWhChangeIllustrative annual spendDifference from USPolicy coverage
Alabama7.937.76+2.2%$16,255,231-$2,254,824Policy profile
Alaska24.0219.99+20.2%$49,237,157$30,727,102Power benchmark only
Arizona7.668.22-6.8%$15,701,774-$2,808,281Policy profile
Arkansas6.826.63+2.9%$13,979,909-$4,530,146Policy profile
California20.7420.76-0.1%$42,513,682$24,003,626Power benchmark only
Colorado9.608.96+7.1%$19,678,464$1,168,409Power benchmark only
Connecticut18.5019.15-3.4%$37,922,040$19,411,985Power benchmark only
Delaware11.739.68+21.2%$24,044,623$5,534,568Power benchmark only
Florida9.218.77+5.0%$18,879,026$368,971Power benchmark only
Georgia7.998.16-2.1%$16,378,222-$2,131,834Policy profile
Hawaii37.5931.63+18.8%$77,053,486$58,543,430Power benchmark only
Idaho8.148.07+0.9%$16,685,698-$1,824,358Power benchmark only
Illinois10.249.96+2.8%$20,990,362$2,480,306Policy profile
Indiana9.158.77+4.3%$18,756,036$245,981Policy profile
Iowa7.387.06+4.5%$15,127,819-$3,382,236Power benchmark only
Kansas8.307.94+4.5%$17,013,672-$1,496,383Power benchmark only
Kentucky7.507.00+7.1%$15,373,800-$3,136,255Policy profile
Louisiana6.656.38+4.2%$13,631,436-$4,878,619Policy profile
Maine15.6115.12+3.2%$31,998,002$13,487,947Power benchmark only
Maryland15.2812.26+24.6%$31,321,555$12,811,500Power benchmark only
Massachusetts19.9919.53+2.4%$40,976,302$22,466,246Power benchmark only
Michigan9.338.65+7.9%$19,125,007$614,952Power benchmark only
Minnesota9.759.25+5.4%$19,985,940$1,475,885Power benchmark only
Mississippi7.667.33+4.5%$15,701,774-$2,808,281Policy profile
Missouri8.628.29+4.0%$17,669,621-$840,434Power benchmark only
Montana6.837.04-3.0%$14,000,407-$4,509,648Power benchmark only
Nebraska8.658.15+6.1%$17,731,116-$778,939Power benchmark only
Nevada8.437.77+8.5%$17,280,151-$1,229,904Policy profile
New Hampshire18.2116.89+7.8%$37,327,586$18,817,531Power benchmark only
New Jersey15.1813.70+10.8%$31,116,571$12,606,516Power benchmark only
New Mexico5.216.02-13.5%$10,679,666-$7,830,389Power benchmark only
New York10.249.57+7.0%$20,990,362$2,480,306Power benchmark only
North Carolina7.917.80+1.4%$16,214,234-$2,295,821Policy profile
North Dakota8.187.48+9.4%$16,767,691-$1,742,364Power benchmark only
Ohio10.328.16+26.5%$21,154,349$2,644,294Policy profile
Oklahoma6.696.01+11.3%$13,713,430-$4,796,626Policy profile
Oregon8.338.26+0.8%$17,075,167-$1,434,888Power benchmark only
Pennsylvania10.939.04+20.9%$22,404,751$3,894,696Policy profile
Rhode Island21.8622.00-0.6%$44,809,502$26,299,447Power benchmark only
South Carolina7.857.13+10.1%$16,091,244-$2,418,811Policy profile
South Dakota9.468.67+9.1%$19,391,486$881,431Power benchmark only
Tennessee6.826.86-0.6%$13,979,909-$4,530,146Policy profile
Texas6.726.47+3.9%$13,774,925-$4,735,130Policy profile
Utah8.588.23+4.3%$17,587,627-$922,428Policy profile
Vermont12.9312.26+5.5%$26,504,431$7,994,376Power benchmark only
Virginia10.089.26+8.9%$20,662,387$2,152,332Policy profile
Washington7.156.83+4.7%$14,656,356-$3,853,699Power benchmark only
West Virginia8.558.08+5.8%$17,526,132-$983,923Power benchmark only
Wisconsin9.398.89+5.6%$19,247,998$737,942Policy profile
Wyoming8.788.67+1.3%$17,997,595-$512,460Power benchmark only

US: 9.03¢/kWh, up from 8.53¢ (+5.9%). District of Columbia: 20.98¢/kWh, up from 14.74¢; illustrative annual spend $43,005,643. DC is not included in the 50-state count or CSV. Price changes can reflect customer mix and classification, not just tariff increases.

Download the source-backed power benchmarks (JSON). EIA lists its next release for October 23, 2026; this retained table will not update automatically.

Who controls the decision?

Political climates: state leadership and local pressure

Compare who governs with what officials are doing about data centers. Governor and legislative party control describe the route for state policy changes. The actual incentive, utility and land-use decisions determine what a project can do.

20 reviewed states. Government-control facts checked October 9, 2026 against the NCSL table updated October 6 and NGA governor directory. Data-center signals reuse the October 7 policy research, plus the targeted October 9 Texas check. This is a dated comparison, not a public-opinion poll or forecast.

Control means the same party holds the governorship and majorities in both legislative chambers. Divided government includes a different-party governor or split chambers. Majorities follow NCSL membership counts, not governing coalitions; no veto-proof majority is inferred. Local control and opposition are project-specific.
StateGovernorLegislatureState controlData-center policy and local pressure
AlabamaKay Ivey
Republican
House: Republican
Senate: Republican
Republican control

Open incentive path with new cost-protection laws and 2027 abatement limits.

Local: Local pauses include Baldwin County; state access does not settle rezoning.

Decision to watch and sources
ArizonaKatie Hobbs
Democratic
House: Republican
Senate: Republican
Divided government

New incentive certifications are paused through June 2029. That law is an incentive restriction, not a statewide development ban.

Local: Tucson, Phoenix, Chandler and Pinal County have different approval records.

Decision to watch and sources
ArkansasSarah Huckabee Sanders
Republican
House: Republican
Senate: Republican
Republican control

Incentives expanded in 2025. The retained moratorium resolution was proposed and non-binding.

Local: Local moratoriums, board approvals and a Clarksville bond election remain separate questions.

Decision to watch and sources
GeorgiaBrian Kemp
Republican
House: Republican
Senate: Republican
Republican control

Equipment relief remains in the retained review; a 2026 repeal bill passed the Senate but stalled in the House.

Local: County moratoriums, divided rezoning votes and litigation show site-specific opposition.

Decision to watch and sources
IllinoisJB Pritzker
Democratic
House: Democratic
Senate: Democratic
Democratic control

New incentive applications stopped July 1. The retained POWER Act proposal is separate from the effective application pause.

Local: Moratoriums and approved campuses coexist in different jurisdictions.

Decision to watch and sources
IndianaMike Braun
Republican
House: Republican
Senate: Republican
Republican control

The equipment and utility incentive path remains open in the retained review, with project cost guarantees and local benefit-sharing conditions.

Local: County and city moratoriums can prevent a site advancing despite state incentives.

Decision to watch and sources
KentuckyAndy Beshear
Democratic
House: Republican
Senate: Republican
Divided government

Statewide incentives coexist with a governor energy-plan requirement intended to protect other ratepayers.

Local: Louisville, Scott County and Lexington have separate pause and extension records.

Decision to watch and sources
LouisianaJeff Landry
Republican
House: Republican
Senate: Republican
Republican control

LED describes an invitation-only transition and an agency-supported commitment process.

Local: New Orleans restrictions and parish-level siting rules differ.

Decision to watch and sources
MississippiTate Reeves
Republican
House: Republican
Senate: Republican
Republican control

State incentives remain open in the retained review, subject to investment and jobs tests.

Local: Jackson has a moratorium; other project disputes have their own local and court records.

Decision to watch and sources
NevadaJoe Lombardo
Republican
House: Democratic
Senate: Democratic
Divided government

New abatements need a binding Community Support Commitment before GOED board consideration. Proposed 2027 changes are separate.

Local: Reno and several counties have pauses or restrictions; water standards are location-specific.

Decision to watch and sources
North CarolinaJosh Stein
Democratic
House: Republican
Senate: Republican
Divided government

Electricity relief was repealed; equipment relief remains in the retained review. A proposed end to new applications is a different action.

Local: County and municipal moratoriums are independent; an existing project can present a vested-rights dispute.

Decision to watch and sources
OhioMike DeWine
Republican
House: Republican
Senate: Republican
Republican control

The governor paused new exemption proposals while a legislative committee reviews data-center growth. No fixed end is stated.

Local: The retained local review reports numerous moratoriums and effective bans.

Decision to watch and sources
OklahomaKevin Stitt
Republican
House: Republican
Senate: Republican
Republican control

Equipment incentives remain open while large-load cost rules and a future cooling-water restriction add conditions.

Local: Municipal and tribal governments have distinct moratoriums and bans.

Decision to watch and sources
PennsylvaniaJosh Shapiro
Democratic
House: Democratic
Senate: Republican
Divided government

Equipment relief requires a GRID consent order. The retained executive order ties certain DEP permits to local approvals.

Local: Municipal decisions and zoning challenges can control whether state permitting advances.

Decision to watch and sources
South CarolinaHenry McMaster
Republican
House: Republican
Senate: Republican
Republican control

Incentive certification remains available before 2032, with investment and employment conditions. Large-load obligations remain separate.

Local: Several county moratoriums and project-size rules appear in the retained research.

Decision to watch and sources
TennesseeBill Lee
Republican
House: Republican
Senate: Republican
Republican control

Equipment relief remains open; a suggested three-year incentive pause is a planned 2027 bill, not an enacted pause.

Local: Nashville restrictions, Knoxville's moratorium and a pending Memphis vote differ.

Decision to watch and sources
TexasGreg Abbott
Republican
House: Republican
Senate: Republican
Republican control

The targeted October 9 review confirms reported ERCOT and TCEQ holds and the effective interconnection funding rule. Incentive repeal remains a proposal.

Local: Hill County rescinded its moratorium after a developer lawsuit; that local change is separate from the state holds.

Decision to watch and sources
UtahSpencer Cox
Republican
House: Republican
Senate: Republican
Republican control

Equipment relief remains available in the retained review; limits on some local incentives start in May 2027.

Local: Tooele County and Box Elder project litigation show different local approval risks.

Decision to watch and sources
VirginiaAbigail Spanberger
Democratic
House: Democratic
Senate: Democratic
Democratic control

Equipment relief remains available, while the retained executive order restricts state site-readiness and fast-track assistance for large projects.

Local: Loudoun and Prince William are changing by-right and discretionary approval paths.

Decision to watch and sources
WisconsinTony Evers
Democratic
House: Republican
Senate: Republican
Divided government

Qualified incentives remain open in the retained statute. A candidate pledge to repeal them is a campaign position, not enacted law.

Local: County moratoriums and pending city proposals need individual checks.

Decision to watch and sources

Read actions alongside party control

The retained evidence records restrictions under both parties: Texas has reported grid and environmental-permit holds, Ohio paused new exemption proposals, and Illinois stopped new incentive applications. Texas and Ohio have Republican state control; Illinois has Democratic state control. These actions affect different approvals and cannot be treated as equivalent construction bans.

Pennsylvania has a Democratic governor and House, with a Republican Senate. Its executive and agency requirements still affect permitting and tax certification. Legislative division alone does not predict a project's approval date.

Five political checks before committing to a site

  1. Identify every decision maker. Distinguish the state incentive agency, utility commission, environmental agency and municipal or county zoning authority. Establish tribal jurisdiction where relevant.
  2. Read the actual local approval route. A permitted use can differ from a rezoning or special-use application requiring a public vote. Obtain the ordinance, moratorium scope, exceptions and next hearing date.
  3. Address the documented concerns. Show who funds grid upgrades, the water source and annual demand, noise limits and backup-generator operation. Compare enforceable conditions and local benefits with the actual project design.
  4. Use the public record. Read staff reports, meeting minutes, recorded votes and filed litigation for the proposed site. A crowded hearing or one denied project does not establish statewide opposition or an approval probability.
  5. Track changes through adoption. Separate candidate pledges, introduced bills, chamber votes, signed laws and effective dates. Record which obligations cover existing awards, expansions and new applications.

The 2026 general election is November 3. Recheck government composition after certified results and office transitions; this page does not predict election outcomes. Download the political-context records (JSON). Government composition is kept separate from the incentive-access score.

2026 governors-elect

See where the 2026 governors-elect in 26 key states stand on construction pauses, incentives, electricity costs and local control. Sourced quotes and documented official actions appear separately.

See where the new governors stand on data centers
Compare the serving utility

Large-load utility comparison

Compare project requirements and contract obligations before requesting a site-specific quote.

35 selected utility, tariff and wholesale-network entries across 20 states. Initial research: 2026-10-07; individual review dates appear in each entry. Includes major utilities, co-ops and municipal providers; coverage within each state is incomplete. Your address determines the serving utility, subject to applicable customer-choice rules. A wholesale network also needs a retail member agreement.

Tariffs set rates and service rules. An electric service agreement (ESA) sets project commitments; a power purchase agreement (PPA) covers supply. None confirms available capacity or a delivery date. Unknown terms remain unverified. This comparison does not change the state's incentive access score.

How to read these terms

Published tariffs and approved frameworks are separate evidence categories: a framework may still need a project contract or final rate sheet. Proposed terms and approved future rates are labeled and are not today's requirements. A project example describes one customer's agreement.

MW means total facility utility demand, not just IT equipment. MVA also depends on power factor. Load factor is average demand divided by peak demand over the stated period. A minimum-demand percentage applies to its specified billing component, not necessarily the whole bill. Firm service is not a guarantee against outages; interruptible service allows contractual curtailment.

The state scenario's MW input does not filter this directory. Read each utility's voltage, load-factor, aggregation and contract conditions before assessing eligibility. State permitting and grid holds still apply: review the state evidence.

35 utility records, ordered by provider name.

Ohio · Investor-owned utility

AEP Ohio (Ohio Power)

Published tariff

DCT

Minimum-demand table starts at 25,001 kW; affiliate aggregation. Studies start at 25,000 kW.

Terms, limits and source
State coverage
Ohio
Provider role
Investor-owned utility
Evidence status
Published tariff
Tariff or agreement
DCT
Project size and conditions
Minimum-demand table starts at 25,001 kW; affiliate aggregation. Studies start at 25,000 kW.
Firm or interruptible
Not verified in saved research.
Upfront costs
Not verified in saved research.
Recurring obligations
Tiered contract-capacity formula plus prior-demand ratchet; not a flat 85% bill.
Contract length
8 years plus ramp up to 4 years.
Security and exit exposure
Conditional collateral: 50% of full-term minimum charges; exit provisions apply.
What still needs checking
Effective July 23, 2025. Confirm aggregation and applicable demand tier.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Alabama · Investor-owned utility

Alabama Power

Published tariff

LPL

General industrial; billing floor 1,200 kVA. Negotiated terms possible above 30,000 kVA.

Terms, limits and source
State coverage
Alabama
Provider role
Investor-owned utility
Evidence status
Published tariff
Tariff or agreement
LPL
Project size and conditions
General industrial; billing floor 1,200 kVA. Negotiated terms possible above 30,000 kVA.
Firm or interruptible
Not verified in saved research.
Upfront costs
Not verified in saved research.
Recurring obligations
Greatest of actual, seasonal ratchet, 75% contract capacity or 1,200 kVA.
Contract length
At least 5 years for new customers.
Security and exit exposure
Not verified in saved research.
What still needs checking
January 2025 price components are not a current all-in quote.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Texas · Municipal utility

Austin Energy

Published tariff

High Load Factor schedules

Primary: 3 to below 20 MW or at least 20 MW; annual average monthly load factor at least 85%. Transmission: at least 20 MW and 69 kV.

Terms, limits and source
State coverage
Texas
Provider role
Municipal utility
Evidence status
Published tariff
Tariff or agreement
High Load Factor schedules
Project size and conditions
Primary: 3 to below 20 MW or at least 20 MW; annual average monthly load factor at least 85%. Transmission: at least 20 MW and 69 kV.
Firm or interruptible
Not verified in saved research.
Upfront costs
Not verified in saved research.
Recurring obligations
Primary 3-to-below-20 MW class: preceding 12-month highest billed kW times demand charge, plus power supply adjustment.
Contract length
Multi-year sole-supplier contract; base rates fixed, not every bill component.
Security and exit exposure
Not verified in saved research.
What still needs checking
Effective October 1, 2026. General industrial schedules; other class-specific minimums and exact term need review.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Texas · Retail co-op

Bluebonnet Electric Cooperative

Published tariff

Key Account schedules

Eligibility text says at least 1 MW; headings say above 1 MW. Distribution, substation and transmission versions.

Terms, limits and source
State coverage
Texas
Provider role
Retail co-op
Evidence status
Published tariff
Tariff or agreement
Key Account schedules
Project size and conditions
Eligibility text says at least 1 MW; headings say above 1 MW. Distribution, substation and transmission versions.
Firm or interruptible
Not verified in saved research.
Upfront costs
Not verified in saved research.
Recurring obligations
Greatest of 30-minute peak, 1 MW or contract demand. Wholesale supply and applicable adjustments add costs.
Contract length
Not verified in saved research.
Security and exit exposure
Not verified in saved research.
What still needs checking
Currently linked compilation retains 2017-2019 sheet dates. Confirm exact 1 MW boundary, supplier conditions and project contract.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Illinois · Investor-owned utility

ComEd

Verification gap

Large-demand retail proceeding / accepted Equinix TSA

June 2025 filing proposed at least 50 MW within 10 years; final retail threshold remains unverified.

Terms, limits and source
State coverage
Illinois
Provider role
Investor-owned utility
Evidence status
Verification gap
Tariff or agreement
Large-demand retail proceeding / accepted Equinix TSA
Project size and conditions
June 2025 filing proposed at least 50 MW within 10 years; final retail threshold remains unverified.
Firm or interruptible
Not verified in saved research.
Upfront costs
Not verified in saved research.
Recurring obligations
Not verified in saved research.
Contract length
Not verified in saved research.
Security and exit exposure
FERC accepted the customer-specific Equinix TSA on March 10, 2026. Ramped transmission payments continue for delayed/cancelled projects, or a termination fee applies; not a universal retail price.
What still needs checking
ICC docket lists March 19 final order, March 30 compliance filing and June appeal. Final retail sheets, deposits, TSA scope and current appeal outcome remain unverified. Do not use proposed terms as final requirements.
Research date
2026-10-09. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Texas · Municipal utility

CPS Energy

Interconnection process

Large-load studies

FAQ: aggregate at least 40 MW across common-development delivery points.

Terms, limits and source
State coverage
Texas
Provider role
Municipal utility
Evidence status
Interconnection process
Tariff or agreement
Large-load studies
Project size and conditions
FAQ: aggregate at least 40 MW across common-development delivery points.
Firm or interruptible
Not verified in saved research.
Upfront costs
Table: $75,000 study at 40 to below 75 MW; at least 75 MW: $75,000 screening and $150,000 LLIS per connection point. ERCOT fees extra.
Recurring obligations
Not verified in saved research.
Contract length
Not verified in saved research.
Security and exit exposure
Not verified in saved research.
What still needs checking
Study fees are not construction or energy prices. Prose/table differ at boundaries; confirm exactly 75 MW. Capacity/timing require studies.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Texas · Municipal utility

Denton Municipal Electric

Project example

Core Scientific amended agreement

Approximately 394 MW potential utility load in named project, not an eligibility threshold.

Terms, limits and source
State coverage
Texas
Provider role
Municipal utility
Evidence status
Project example
Tariff or agreement
Core Scientific amended agreement
Project size and conditions
Approximately 394 MW potential utility load in named project, not an eligibility threshold.
Firm or interruptible
Not verified in saved research.
Upfront costs
Not verified in saved research.
Recurring obligations
Not verified in saved research.
Contract length
Named agreement: 14 years plus two 7-year extensions.
Security and exit exposure
Not verified in saved research.
What still needs checking
Retained SEC agreement evidence, not freshly fetched. Not an offer to other customers or a claim of available capacity.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Virginia · Investor-owned utility

Dominion Energy Virginia

Approved future

GS-5

At least 25 MW and 75% load factor.

Terms, limits and source
State coverage
Virginia
Provider role
Investor-owned utility
Evidence status
Approved future
Tariff or agreement
GS-5
Project size and conditions
At least 25 MW and 75% load factor.
Firm or interruptible
Not verified in saved research.
Upfront costs
Not verified in saved research.
Recurring obligations
Qualifying new ESAs: 85% transmission/distribution and 60% generation minimums.
Contract length
14 years including optional ramp up to 4 years for qualifying new ESAs.
Security and exit exposure
Collateral conditions apply; existing contracts differ.
What still needs checking
Approved for January 1, 2027. Not effective at the October 7, 2026 evidence date.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

North Carolina · Investor-owned utility

Duke Energy

Proposed

High Load Factor settlement

Proposed: at least 50 MW and 80% load factor; ESAs after June 1, 2026.

Terms, limits and source
State coverage
North Carolina
Provider role
Investor-owned utility
Evidence status
Proposed
Tariff or agreement
High Load Factor settlement
Project size and conditions
Proposed: at least 50 MW and 80% load factor; ESAs after June 1, 2026.
Firm or interruptible
Not verified in saved research.
Upfront costs
Proposed nonrefundable dedicated facilities costs.
Recurring obligations
Not verified in saved research.
Contract length
Not verified in saved research.
Security and exit exposure
Proposed deposits/security for shared upgrades.
What still needs checking
October 7, 2026 announcement pending NCUC approval; exact filed settlement terms need confirmation.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Kentucky · Wholesale network

East Kentucky Power Cooperative

Approved framework

DCP / retail member agreements

At least 15 MW maximum capacity and operation at 60% or more of capacity.

Terms, limits and source
State coverage
Kentucky
Provider role
Wholesale network
Evidence status
Approved framework
Tariff or agreement
DCP / retail member agreements
Project size and conditions
At least 15 MW maximum capacity and operation at 60% or more of capacity.
Firm or interruptible
Not verified in saved research.
Upfront costs
Capital upfront; study fee up to $250,000 plus excess study cost. Dedicated resource at 250 MW or more.
Recurring obligations
Operating costs prepaid on a rolling basis.
Contract length
Three-party contract requires PSC approval; years not verified.
Security and exit exposure
Prepaid operating account; other security needs contract review.
What still needs checking
Utility explanation of approved tariff. Full filed DCP and retail delivery terms remain gaps.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Arkansas · Investor-owned utility

Entergy Arkansas

Contract policy

Industrial tariffs and project agreements

Project-specific; general LPS and PST schedules exist.

Terms, limits and source
State coverage
Arkansas
Provider role
Investor-owned utility
Evidence status
Contract policy
Tariff or agreement
Industrial tariffs and project agreements
Project size and conditions
Project-specific; general LPS and PST schedules exist.
Firm or interruptible
Not verified in saved research.
Upfront costs
Not verified in saved research.
Recurring obligations
Not verified in saved research.
Contract length
Not verified in saved research.
Security and exit exposure
Not verified in saved research.
What still needs checking
Cryptocurrency/mobile-load interruptible LPHLDS is not a generic hyperscale tariff. Proposed project deals are not statewide terms.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Louisiana · Investor-owned utility

Entergy Louisiana

Published tariff

LLHLFPS-L

At least 70 MW firm load; at least 80% average monthly load factor; at least 69 kV; one delivery point.

Terms, limits and source
State coverage
Louisiana
Provider role
Investor-owned utility
Evidence status
Published tariff
Tariff or agreement
LLHLFPS-L
Project size and conditions
At least 70 MW firm load; at least 80% average monthly load factor; at least 69 kV; one delivery point.
Firm or interruptible
Firm
Upfront costs
Not verified in saved research.
Recurring obligations
Block-based demand charges and minimum bill; riders add costs.
Contract length
Not verified in saved research.
Security and exit exposure
Not verified in saved research.
What still needs checking
Confirm service-area eligibility and ESA terms; no all-in quote established.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Mississippi · Investor-owned utility

Entergy Mississippi

Contract policy

Data-center service agreements

Project-specific; universal threshold not established.

Terms, limits and source
State coverage
Mississippi
Provider role
Investor-owned utility
Evidence status
Contract policy
Tariff or agreement
Data-center service agreements
Project size and conditions
Project-specific; universal threshold not established.
Firm or interruptible
Not verified in saved research.
Upfront costs
Customer pays direct service costs under reviewed agreements.
Recurring obligations
Not verified in saved research.
Contract length
Not verified in saved research.
Security and exit exposure
Not verified in saved research.
What still needs checking
Company-wide explanation requires Mississippi project confirmation. Mississippi Power and TVA service are separate.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Georgia · Investor-owned utility

Georgia Power

Approved framework

PSC large-load contract rule

New customers above 100 MW.

Terms, limits and source
State coverage
Georgia
Provider role
Investor-owned utility
Evidence status
Approved framework
Tariff or agreement
PSC large-load contract rule
Project size and conditions
New customers above 100 MW.
Firm or interruptible
Not verified in saved research.
Upfront costs
Generation, transmission and distribution cost recovery.
Recurring obligations
Minimum billing permitted; no universal percentage established.
Contract length
Terms up to 15 years permitted, not a universal minimum.
Security and exit exposure
Not verified in saved research.
What still needs checking
January 23, 2025 enabling rule. Obtain PSC-reviewed project contract.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Georgia · Retail co-op

GreyStone Power

Contract policy

Data-center agreements

Project-specific; universal threshold not verified.

Terms, limits and source
State coverage
Georgia
Provider role
Retail co-op
Evidence status
Contract policy
Tariff or agreement
Data-center agreements
Project size and conditions
Project-specific; universal threshold not verified.
Firm or interruptible
Not verified in saved research.
Upfront costs
Dedicated substations paid in full before construction; milestone deposits.
Recurring obligations
Market supply agreement can require fixed minimum payments even if facility is not online at start.
Contract length
Negotiated; universal term not verified.
Security and exit exposure
Performance assurance and termination payments for supply commitments.
What still needs checking
January 2026 executive interview, not a published rate sheet. Delivery and supply agreements both matter.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Indiana / Illinois · Wholesale network

Hoosier Energy member network

Contract policy

Consumer Directed Resource Policy

Loads above 50 MW; identify serving retail member.

Terms, limits and source
State coverage
Indiana, Illinois
Provider role
Wholesale network
Evidence status
Contract policy
Tariff or agreement
Consumer Directed Resource Policy
Project size and conditions
Loads above 50 MW; identify serving retail member.
Firm or interruptible
Not verified in saved research.
Upfront costs
Customer pays studies, transmission and capacity costs, and prepays obligations.
Recurring obligations
Energy invoiced every 7 days with prepayments.
Contract length
Not verified in saved research.
Security and exit exposure
Customer procures capacity; robust prepayments, exact security unverified.
What still needs checking
May 2026 policy explanation. Outside traditional Hoosier tariffs; member delivery prices require separate review.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Indiana · Investor-owned utility

Indiana Michigan Power

Approved framework

Large-load framework

70 MW individually or 150 MW aggregate.

Terms, limits and source
State coverage
Indiana
Provider role
Investor-owned utility
Evidence status
Approved framework
Tariff or agreement
Large-load framework
Project size and conditions
70 MW individually or 150 MW aggregate.
Firm or interruptible
Not verified in saved research.
Upfront costs
Not verified in saved research.
Recurring obligations
Take-or-pay; exact demand percentage not verified.
Contract length
At least 12 years; tariff index indicates ramp up to 5 years before initial term.
Security and exit exposure
Financial guarantees; amount needs verification.
What still needs checking
Utility confirms approved framework. Full tariff book could not be reopened.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Kentucky · Investor-owned utility

Kentucky Utilities

Published tariff

EHLF

New customers above 50 MVA AND above 85% expected average monthly load factor.

Terms, limits and source
State coverage
Kentucky
Provider role
Investor-owned utility
Evidence status
Published tariff
Tariff or agreement
EHLF
Project size and conditions
New customers above 50 MVA AND above 85% expected average monthly load factor.
Firm or interruptible
Not verified in saved research.
Upfront costs
Not verified in saved research.
Recurring obligations
Greatest of current peak, prior 11-month peak or 80% contract capacity.
Contract length
At least 15 years.
Security and exit exposure
Starts at 24 months of minimum bills, with credit/cash exceptions.
What still needs checking
Effective February 16, 2026. MVA is not MW. Do not apply KU prices to LG&E.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Tennessee · Municipal utility

Memphis Light, Gas and Water

Published tariff

TDC / TVA supply

Classes above 1 through 5 MW, above 5 through 15, above 15 through 25, and above 25 MW; qualifying use required.

Terms, limits and source
State coverage
Tennessee
Provider role
Municipal utility
Evidence status
Published tariff
Tariff or agreement
TDC / TVA supply
Project size and conditions
Classes above 1 through 5 MW, above 5 through 15, above 15 through 25, and above 25 MW; qualifying use required.
Firm or interruptible
Firm
Upfront costs
Not verified in saved research.
Recurring obligations
Tiered demand floors and minimum energy provisions; fuel/other adjustments and voltage charges apply.
Contract length
At least 1 year for TDCA; at least 5 years for TDCB/C/D.
Security and exit exposure
Not verified in saved research.
What still needs checking
Effective October 1, 2026. Separate TVA wholesale capacity-charge question unresolved; other distributors may differ.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Virginia · Retail co-op

NOVEC HV-1

Published tariff

HV-1

At least 5 MW new/separately metered additional load; annual load factor at least 70%; voltage conditions apply.

Terms, limits and source
State coverage
Virginia
Provider role
Retail co-op
Evidence status
Published tariff
Tariff or agreement
HV-1
Project size and conditions
At least 5 MW new/separately metered additional load; annual load factor at least 70%; voltage conditions apply.
Firm or interruptible
Not verified in saved research.
Upfront costs
Primary distribution investment and excess facilities can require contributions.
Recurring obligations
Greatest of monthly 30-minute peak, 5 MW or contract minimum.
Contract length
Negotiated to recover investment; ESA normally effective 12 months before service.
Security and exit exposure
Not verified in saved research.
What still needs checking
HV-1 effective April 1, 2023. Standard, market or qualifying third-party supply. See separate NOVEC HV-2 entry for dedicated-facilities contract service; exact ESA and capacity remain site-specific.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Virginia · Retail co-op

NOVEC HV-2

Published tariff

HV-2, effective April 1, 2023

Minimum contract billing demand 65 MW; alternatively at least 45 MW with delivery at least 34.5 kV through specified dedicated facilities sourced from 230 kV. Average annual load factor at least 85%. No backup/standby service.

Terms, limits and source
State coverage
Virginia
Provider role
Retail co-op
Evidence status
Published tariff
Tariff or agreement
HV-2, effective April 1, 2023
Project size and conditions
Minimum contract billing demand 65 MW; alternatively at least 45 MW with delivery at least 34.5 kV through specified dedicated facilities sourced from 230 kV. Average annual load factor at least 85%. No backup/standby service.
Firm or interruptible
Not verified in saved research.
Upfront costs
Excess facilities require a one-time construction contribution plus monthly charges on contributed investment: 0.442% high-voltage line, 0.644% substation, 0.893% primary distribution.
Recurring obligations
Distribution billing demand: greater of 30-minute monthly peak or contract minimum times ramp percentage. Distribution billing energy: greater of actual kWh or billing kW x month hours x 85%. Distribution minimum is contract amount plus excess-facilities charge.
Contract length
Negotiated to recover investment, maintenance and operations. ESA normally effective at least 12 months before desired service.
Security and exit exposure
Not verified in saved research.
What still needs checking
All supply purchased from NOVEC at a case-specific market rate. Published distribution charges: $1,420.23/month, $0.793/kW, $0.16/rKVA and $0.000337/kWh. These exclude supply and do not establish an all-in price. Confirm ESA ramp, collateral, service type and available capacity.
Research date
2026-10-09. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Nevada · Investor-owned utility

NV Energy

Proposed

LLESA framework

Typically above 25 MW with new generation/transmission needs; proposed scope.

Terms, limits and source
State coverage
Nevada
Provider role
Investor-owned utility
Evidence status
Proposed
Tariff or agreement
LLESA framework
Project size and conditions
Typically above 25 MW with new generation/transmission needs; proposed scope.
Firm or interruptible
Not verified in saved research.
Upfront costs
Proposed upfront infrastructure recovery.
Recurring obligations
Proposed minimum payments; formula not established.
Contract length
Proposed long-term commitment; years not verified.
Security and exit exposure
Proposed guarantees and termination protection.
What still needs checking
June 2026 proposal; each agreement requires PUCN approval. Do not treat as effective terms.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Oklahoma · Investor-owned utility

OG&E

Proposed

Large-load tariff

Threshold not established in reopened evidence.

Terms, limits and source
State coverage
Oklahoma
Provider role
Investor-owned utility
Evidence status
Proposed
Tariff or agreement
Large-load tariff
Project size and conditions
Threshold not established in reopened evidence.
Firm or interruptible
Not verified in saved research.
Upfront costs
Not verified in saved research.
Recurring obligations
Not verified in saved research.
Contract length
Indexed proposal: 15 years plus ramp up to 5 years; full terms need verification.
Security and exit exposure
Not verified in saved research.
What still needs checking
September 30 status says proposed. Conflicting hearing dates remain unresolved; no approved minimum percentage.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Oklahoma · Retail co-op

Oklahoma Electric Cooperative

Contract policy

Interruptible data-center service / WFEC supply

Public rate page directs accounts at 1,000 kVA and above to a key-account specialist. This is a contact threshold, not a verified data-center eligibility rule.

Terms, limits and source
State coverage
Oklahoma
Provider role
Retail co-op
Evidence status
Contract policy
Tariff or agreement
Interruptible data-center service / WFEC supply
Project size and conditions
Public rate page directs accounts at 1,000 kVA and above to a key-account specialist. This is a contact threshold, not a verified data-center eligibility rule.
Firm or interruptible
Interruptible
Upfront costs
Not verified in saved research.
Recurring obligations
Must reduce operations during monthly system peak; substantial penalties if not reduced.
Contract length
Not verified in saved research.
Security and exit exposure
Not verified in saved research.
What still needs checking
No public large-account contract verified. Curtailment duration, notice, penalty formula, backup requirements, term, security and price require the actual contract. Smaller commercial schedules are not a substitute.
Research date
2026-10-09. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Texas · Investor-owned utility

Oncor

Published tariff

Transmission-voltage delivery

Delivery-voltage class; retail energy supply contracted separately.

Terms, limits and source
State coverage
Texas
Provider role
Investor-owned utility
Evidence status
Published tariff
Tariff or agreement
Transmission-voltage delivery
Project size and conditions
Delivery-voltage class; retail energy supply contracted separately.
Firm or interruptible
Not verified in saved research.
Upfront costs
Not verified in saved research.
Recurring obligations
4CP transmission billing and 80% prior-11-month actual-demand ratchet for distribution component.
Contract length
Not verified in saved research.
Security and exit exposure
Not verified in saved research.
What still needs checking
Delivery tariff only. Retail supply, ERCOT requirements and site capacity are separate.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Texas · Retail co-op

Pedernales Electric Cooperative

Published tariff

Large Power / Transmission Level

Large power: 50 kW rolling average demand. Transmission service: at least 60 kV.

Terms, limits and source
State coverage
Texas
Provider role
Retail co-op
Evidence status
Published tariff
Tariff or agreement
Large Power / Transmission Level
Project size and conditions
Large power: 50 kW rolling average demand. Transmission service: at least 60 kV.
Firm or interruptible
Not verified in saved research.
Upfront costs
Not verified in saved research.
Recurring obligations
Transmission class: $1,000 monthly service charge, 4CP transmission and wholesale supply pass-through; not an all-in price.
Contract length
Not verified in saved research.
Security and exit exposure
Not verified in saved research.
What still needs checking
October 1, 2026 tariff. Industrial Power section 500.5 is closed to new applicants. Exact project agreement and upgrades unverified.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Pennsylvania · Investor-owned utility

PPL Electric

Published tariff

LP-6, effective July 1, 2026

Service began on/after October 1, 2025; at least 69 kV; 50 MW at one facility or 75 MW aggregated within 10 miles. A 50-75 MW facility without network upgrade costs may qualify for LP-5 only with PUC approval.

Terms, limits and source
State coverage
Pennsylvania
Provider role
Investor-owned utility
Evidence status
Published tariff
Tariff or agreement
LP-6, effective July 1, 2026
Project size and conditions
Service began on/after October 1, 2025; at least 69 kV; 50 MW at one facility or 75 MW aggregated within 10 miles. A 50-75 MW facility without network upgrade costs may qualify for LP-5 only with PUC approval.
Firm or interruptible
Firm
Upfront costs
Directly assigned transmission/distribution upgrades funded through construction contributions paid before work milestones.
Recurring obligations
Monthly distribution minimum $999.11; supply, transmission and riders additional. ESA uses greater of actual peak or 80% of ramp load until the Rate Base Security Obligation is satisfied. After satisfaction: 80% in first five years, 50% in second five years.
Contract length
ESA at least 10 years, with a load ramp schedule. Initial ramp provisions reference five years but permit a schedule up to the ESA initial term.
Security and exit exposure
Security covers attributable upgrades recovered through transmission rates. Exit fee is greater of remaining minimum-load guarantee or remaining Rate Base Security Obligation.
What still needs checking
Voluntary interruptible option reduces minimum-load guarantees to 60%/30% for the first/second five years; confirm its interaction with security in the ESA. Supply, TSC, riders, actual upgrade costs and load-shedding arrangements require site review. September 2026 transmission rider proposal is separate from this final LP-6.
Research date
2026-10-09. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Virginia · Retail co-op

Rappahannock Electric Cooperative

Published tariff

LP-DF

Above 25 MW; annual load factor at least 75%; dedicated facilities, at least 34.5 kV delivery from qualifying 115 kV source.

Terms, limits and source
State coverage
Virginia
Provider role
Retail co-op
Evidence status
Published tariff
Tariff or agreement
LP-DF
Project size and conditions
Above 25 MW; annual load factor at least 75%; dedicated facilities, at least 34.5 kV delivery from qualifying 115 kV source.
Firm or interruptible
Not verified in saved research.
Upfront costs
Additional facilities may require upfront contribution plus recurring charges.
Recurring obligations
Agreement-specific distribution minimum; supply obligations are separate.
Contract length
Negotiated; ESA normally effective 12 months before service.
Security and exit exposure
Distribution and supply collateral set by agreement; attributable supply costs can survive exit.
What still needs checking
Effective April 15, 2026. Excludes standby, supplemental, self-generation, net-metering and resale service.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Utah · Investor-owned utility

Rocky Mountain Power

Verification gap

Large-load special contracts

Indexed statute: requests reaching 100 MW within 5 years; confirm applicable definition.

Terms, limits and source
State coverage
Utah
Provider role
Investor-owned utility
Evidence status
Verification gap
Tariff or agreement
Large-load special contracts
Project size and conditions
Indexed statute: requests reaching 100 MW within 5 years; confirm applicable definition.
Firm or interruptible
Not verified in saved research.
Upfront costs
Not verified in saved research.
Recurring obligations
Not verified in saved research.
Contract length
Not verified in saved research.
Security and exit exposure
Not verified in saved research.
What still needs checking
Utility confirms special-contract path. Docket/statute direct retrieval failed; universal price and term not established.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Arizona · Public power

Salt River Project (SRP)

Approved framework

E-67 / large customer integration

New accounts with at least 20 MW forecast load.

Terms, limits and source
State coverage
Arizona
Provider role
Public power
Evidence status
Approved framework
Tariff or agreement
E-67 / large customer integration
Project size and conditions
New accounts with at least 20 MW forecast load.
Firm or interruptible
Not verified in saved research.
Upfront costs
Customer-specific upgrades paid upfront.
Recurring obligations
Greater of actual demand or 80% forecast.
Contract length
Not verified in saved research.
Security and exit exposure
Not verified in saved research.
What still needs checking
Utility explanation of approved 2025 plan. Confirm account eligibility and executed agreement.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

South Carolina · Public power

Santee Cooper

Approved framework

L-25-LL

Index says data centers above 50 MW or mobile loads above 1 MW; exact boundary needs confirmation.

Terms, limits and source
State coverage
South Carolina
Provider role
Public power
Evidence status
Approved framework
Tariff or agreement
L-25-LL
Project size and conditions
Index says data centers above 50 MW or mobile loads above 1 MW; exact boundary needs confirmation.
Firm or interruptible
Not verified in saved research.
Upfront costs
Not verified in saved research.
Recurring obligations
Special minimum demand and incremental demand charges.
Contract length
Not verified in saved research.
Security and exit exposure
Collateral required; details need verification.
What still needs checking
Approved April 2025; presentation lists April 24, 2029 expiration. Exact contract years not reconfirmed.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Arizona · Retail co-op

Trico Electric Cooperative

Contract policy

Large data-center framework

Universal MW threshold not verified.

Terms, limits and source
State coverage
Arizona
Provider role
Retail co-op
Evidence status
Contract policy
Tariff or agreement
Large data-center framework
Project size and conditions
Universal MW threshold not verified.
Firm or interruptible
Not verified in saved research.
Upfront costs
100% upfront distribution/transmission costs and studies; generation costs directly assigned.
Recurring obligations
Not verified in saved research.
Contract length
Not verified in saved research.
Security and exit exposure
Not verified in saved research.
What still needs checking
January 2026 utility explanation, not a filed price schedule. Term, minimum bill and collateral remain unverified.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Tennessee · Wholesale network

TVA wholesale network

Approved framework

August 20, 2026 approved rate resolution

Qualifying data-center load above 5 MW enters Schedule DC; optional DCA covers above 1 through 5 MW. Identify local retail distributor.

Terms, limits and source
State coverage
Tennessee
Provider role
Wholesale network
Evidence status
Approved framework
Tariff or agreement
August 20, 2026 approved rate resolution
Project size and conditions
Qualifying data-center load above 5 MW enters Schedule DC; optional DCA covers above 1 through 5 MW. Identify local retail distributor.
Firm or interruptible
Not verified in saved research.
Upfront costs
First FY2027 cohort, up to 2,000 MW: $1.521 million/MW, nonrefundable. For new requests, charge applies above first 5 MW. Existing/inflight rules and expansion waivers affect applicability; TVA sets payment terms.
Recurring obligations
Separate retail schedule and riders apply; the capacity commitment payment is additional.
Contract length
Not verified in saved research.
Security and exit exposure
Not verified in saved research.
What still needs checking
Resolution verified, but final CCC rider exhibits and site agreement still needed. Cohort-specific interruption requirements and Firm Generation Date are set by TVA. Confirm eligibility, exemptions, cohort availability and payment schedule. MLGW is one retail implementation.
Research date
2026-10-09. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Georgia · Retail co-op

Walton EMC

Contract policy

Case-by-case data-center service

Project-specific; universal threshold not verified.

Terms, limits and source
State coverage
Georgia
Provider role
Retail co-op
Evidence status
Contract policy
Tariff or agreement
Case-by-case data-center service
Project size and conditions
Project-specific; universal threshold not verified.
Firm or interruptible
Not verified in saved research.
Upfront costs
Required transmission/substation upgrades and other service costs assigned to customer.
Recurring obligations
Not verified in saved research.
Contract length
Not verified in saved research.
Security and exit exposure
Not verified in saved research.
What still needs checking
Utility explanation confirms project selection case by case. Public price, term, security and minimum bill not established.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Wisconsin · Investor-owned utility

We Energies

Approved framework

Very Large Customer / Bespoke Resources

100 MW threshold in PSC decision summary.

Terms, limits and source
State coverage
Wisconsin
Provider role
Investor-owned utility
Evidence status
Approved framework
Tariff or agreement
Very Large Customer / Bespoke Resources
Project size and conditions
100 MW threshold in PSC decision summary.
Firm or interruptible
Not verified in saved research.
Upfront costs
Full-benefits resource model requires 100% of associated costs.
Recurring obligations
Not verified in saved research.
Contract length
At least 15 years.
Security and exit exposure
Not verified in saved research.
What still needs checking
April 24, 2026 approval with modifications. Final prices and detailed collateral require filed rate sheets.
Research date
2026-10-07. Saved evidence, not a live rate feed. Unresolved terms are listed separately.

Download utility comparison data (JSON) · Estimate a site's operating costs · Request a location-specific shortlist

Key takeaways

  • Texas is open for data center loads under 75 MW. Those go through the local utility's approval process. Our October 9 source check confirms ERCOT's energization pause applies at 75 MW or more (ERCOT, pages 2 and 7) and the separate governor directive pausing TCEQ permit issuance (September 21 letter). The adopted interconnection funding rule took effect October 8. Audit, meeting and reporting dates do not automatically end either hold. See scope, funding obligations and the October 12 RFI deadline.
  • Seven states paused, narrowed or ended incentives or state help for new projects in 2026: Arizona, Illinois, Nevada, North Carolina, Ohio, Pennsylvania and Virginia. Twelve, including Texas, remain open but added new utility, cost, water or permit conditions. Alabama and Utah will also trim incentives from 2027. Within this 20-state review, only Arkansas received the Open label. Its local restrictions still matter.
  • Across these 20 states, average industrial power ran from 6.65¢/kWh in Louisiana to 10.93¢/kWh in Pennsylvania from January to July 2026 (EIA). That is an average, not the rate a large load pays.
  • Local moratoriums are the fastest-moving risk. Ohio has at least 138 local moratoriums (Ohio Capital Journal). North Carolina has at least 34 (North State Journal). Trackers list 32 Indiana counties (Indiana University ERI) and 21 Wisconsin counties (UW-Madison Extension) with moratoriums. We log new local actions, with the source document, in our moratorium tracker, and individual projects by state in the project tracker.

Start with the workload and delivery date

The state screen answers different questions for a tenant, a new campus and a landowner. Write the required IT load, facility load, first delivery date, growth phases and network endpoints before choosing a state. Otherwise a cheap average or generous equipment exemption can hide the constraint that actually stops the project.

Practical screening priorities. These are project-selection questions, not state rankings.
ProjectFirst comparisonEvidence that advances the shortlist
Lease an existing 1 MW+ hallCommissioned IT capacity, density, network endpoints and the lease commencement date.Operator delivery commitment, commissioning scope, actual bill pass-through and tenant incentive treatment. A new-development pause does not automatically determine an existing lease.
Build a phased campusFirm utility capacity by phase, the expansion path and what becomes payable before load arrives.Utility study and service agreement, upgrade allocation, ramp milestones, land-use approval and a tested construction schedule.
AI training or batch computeCluster size, usable rack density, liquid-cooling capability and sustained power cost.Delivered cooling capacity, coolant and heat-rejection design, onsite network fabric and tested data-transfer time to the required storage and cloud endpoints.
Inference or interactive applicationsMeasured latency to users and application dependencies, then power and lease cost.Round-trip measurements on proposed routes, cloud on-ramp details, capacity commitments and failover tests. A state boundary does not define a latency budget.
Offer land or an industrial buildingAllowed use, serving utility, usable expansion area and the owner's infrastructure exposure.Parcel-level zoning record, a utility response naming the site and phased MW, route and easement evidence, and a written division of development costs.

A listed facility is not a block of wholesale capacity. A marketed MW figure may mean ultimate campus plans, utility reservation or delivered IT load. Ask which one it represents. Use our wholesale leasing guide, powered land guide and site selection guide for the next level of detail.

What it takes to qualify for the incentive

An open application path does not mean every project qualifies. Compare investment, permanent employment or payroll, eligible purchases and the clock that starts the obligation. A $75 million construction budget does not satisfy a $75 million eligible-investment test if excluded costs make up part of the spend.

These are selected conditions for the 20 reviewed states. Paused programs retain their legacy criteria for evaluating existing certificates. The October 9 qualification supplement does not refresh every policy rule or change the October 7 access scores. Each profile links the source and review date; fields not established by that source remain unresolved.

Compare investment, employment and timing in all 20 programs
Selected qualification conditions. Follow each state link for benefit scope, source dates and budget implications.
StateInvestmentEmployment or payrollClock and duration
AlabamaExisting Chapter 9B tiers: up to $200 million supports a 10-year term; more than $200 million but less than $400 million supports 20 years. A 30-year term requires more than $200 million within ten years and more than $400 million within twenty years. The 2027 grant rules need a separate review.No universal data-center job minimum established in this comparison. Other Alabama incentive programs have separate requirements.Existing terms run 10, 20 or 30 years; the 30-year tier has both ten-year and twenty-year investment tests. New abatement limits apply to grants on or after January 1, 2027.
ArizonaLegacy certification: $50 million in Maricopa or Pima County; $25 million elsewhere.No job threshold established from the legacy program page reviewed here.Legacy investment window: five years after the certification letter. New-center incentive pause: July 1, 2026 through June 30, 2029 in the policy snapshot.
ArkansasQualified data center: $100 million. Separate qualified large-data-center definition: $2 billion across the qualifying facilities.Annualized compensation of at least $1 million for the standard category; $3 million for the large category. Qualifying contractor compensation can count.Standard investment: within five years after construction starts. Large category: ten years. Compensation test covers the two calendar years after operations begin.
GeorgiaInvestment and quality-job thresholds vary by county population and certificate date. Obtain the applicable county schedule before comparing incentives.The application requires planned and maintained New Quality Jobs, with wage and work-hour records. Do not substitute temporary construction headcount.Meet the applicable investment-period tests and maintain the certificate. The retained policy review places the equipment exemption sunset at December 31, 2031.
IllinoisAt least $250 million collectively by the data center and tenants over 60 months under published program criteria.At least 20 new full-time or equivalent operating/maintenance jobs; compensation at least 120% of the county median full-time wage.60-month investment period. DCEO's page says new applications are not processed from July 1, 2026.
IndianaIEDC describes terms up to 25 years below $750 million and up to 50 years above $750 million. The separate local property-tax program uses a $25 million investment test.The reviewed IEDC overview does not establish a universal job minimum. Confirm the state's project agreement and county-specific criteria.Duration is an awarded term, not an automatic entitlement. The $750 million boundary needs statutory review because the overview does not resolve equality.
KentuckyRetained 2025 review: $25 million to $450 million, depending on county population and applicant category.No universal operating-job threshold established in the retained summary. Obtain the applicable KEDFA approval requirements.The approval agreement controls eligible spend and timing. County population and project-organizer treatment require separate confirmation.
LouisianaRetained program review: at least $200 million invested between July 2024 and July 2029.Commitment to at least 50 new direct jobs in the retained program review.The investment window is tied to calendar dates, not a new five-year period whenever a buyer acquires land.
MississippiAt least $20 million for the standard data-center incentive program.At least 20 jobs paying 125% of the state average wage.Retained program research describes ten-year relief. State approval and the project's award determine its commencement and covered purchases.
Nevada10-year abatement: $25 million within five years. 20-year abatement: $100 million within five years, aggregating the applicant and tenants.10 or 50 full-time Nevada-resident jobs, respectively, within five years; wages at least the statewide average.Business-maintenance, insurance and construction-residency obligations apply. New applications require an executed Community Support Commitment before board consideration.
North CarolinaAt least $75 million in qualifying private investment within five years for the qualifying-datacenter category, with a Commerce determination.County-tier wage standards and employee health-insurance requirements. This is not a flat statewide minimum job count.Investment clock starts with the first qualifying investment. Electricity exemption repeal applies to billing periods beginning on or after August 6, 2026.
OhioStatutory investment minimum: $100 million over three consecutive calendar years for projects beginning in or after 2015.At least $1.5 million in qualifying annual compensation, beginning with the agreement's specified post-month-24 period.Tax Credit Authority agreement controls the percentage and term. New requests remain paused in the retained October 7 policy snapshot.
OklahomaThe reviewed Commerce guide uses activity and revenue tests for equipment relief; it does not provide one universal capital-investment threshold.No common job minimum across these exemptions. The Quality Jobs cash incentive is a separate program.Property-tax relief and sales-tax relief have separate applications, property classes and terms.
PennsylvaniaRetained GRID guideline review: at least $250 million and payment of the full cost of new power capacity.At least 50 jobs paying 125% of the state average wage in the retained GRID review.Since August 2026, the equipment-exemption pathway requires a GRID consent order. Approval and compliance milestones are project-specific.
South CarolinaRetained statute review: at least $50 million for the qualifying data-center exemption.At least 25 full-time jobs in the retained qualification review.Certification must occur before 2032 under the reviewed program. Eligible investment and job periods need project-level confirmation.
TennesseeDepartment of Revenue notice: required capital investment in excess of $100 million.DOR's 2016 notice: at least 15 new permanent full-time jobs paying at least 150% of the state average occupational wage, with minimum health care.DOR's 2016 notice uses a three-year investment period. Verify current certification and later ownership/reorganization provisions; reopening the historical notice is not a full current-law review.
TexasStandard category: $200 million within five years; $250 million supports the longer term. Separate large-project category: $500 million within five years.20 qualifying jobs for the standard category; 40 for the large-project category. Job-location and compensation tests also apply.Standard exemption: ten years, or fifteen with the higher investment. Large-project exemption: twenty years. Investment clock starts at certification.
UtahThe retained equipment-exemption review does not establish a universal dollar threshold. Facility definition and ownership tests must be checked separately.No universal operating-job minimum established for this equipment exemption. Negotiated post-performance credits are separate awards.Certain locally funded incentive limitations begin May 6, 2027; statutory exceptions require a separate review.
VirginiaOrdinary category: $150 million. Qualifying distressed locality: $70 million with the reduced-job criteria.50 new operating/maintenance jobs, or 10 in a qualifying distressed locality; jobs pay at least 150% of the locality's prevailing average wage.VEDP memorandum sets investment, jobs, compliance timing and repayment. Ordinary exemption ends June 30, 2035; special extension categories require separate review.
WisconsinRetained statute review: $50 million to $150 million within five years, depending on county population.No universal job minimum established from the retained qualification summary. WEDC certification and other statutory conditions apply.Five-year investment test. No program sunset is recorded in the retained sales-tax statute review.

Compare the benefit on the same tax base

  • Equipment versus electricity: North Carolina's reviewed equipment exemption remains separate from its repealed electricity exemption. Oklahoma's Commerce guide distinguishes hosting/data processing from web-search activities.
  • State versus local: Texas's standard category exempts the 6.25% state sales/use tax; applicable local sales/use tax remains due. Indiana's local personal-property exemption is separate from the IEDC equipment and energy award.
  • Owner versus tenant: establish who buys the equipment, owns the meter and holds the certificate. A developer's award is not automatically a tenant's exemption.
  • Award duration versus program sunset: a program with no sunset can still issue an award of limited duration. A sunset date is not necessarily the end date on an existing certificate.
  • Compliance versus headline savings: preserve eligible invoices, payroll evidence and annual filings. Identify repayment provisions before treating an exemption as unconditional savings.

Examples: Texas Comptroller, Indiana IEDC, North Carolina sources and Oklahoma sources.

The commitments that can outweigh a cheap rate

Compare four amounts separately: money spent upfront, electricity bills as the load ramps, security that ties up cash or credit, and the liability if the project shrinks or stops. Adding them into one cents/kWh figure hides when the cash is needed and which amounts are recoverable.

Use the actual tariff and service agreement to determine which obligations apply to a site.
ObligationBudget effectWhat to request
Minimum billing demandCharges can follow contracted capacity while actual demand is lower. Energy charges and delivery minimums may use different billing bases.A monthly bill at each ramp phase, the exact minimum-demand formula, ratchets, power-factor adjustments and the right to reduce contract capacity.
Contribution to constructionLine, substation and network work can require payment long before commissioning. A quoted contribution may cover only part of the connection.Utility scope, owner-paid share, estimate validity, payment milestones, refund terms and treatment of cost overruns.
Collateral or guaranteeCash deposits and letters of credit use liquidity or credit capacity. Their face value is not the same as an annual operating expense.Credit-rating trigger, security amount, allowable forms, guarantee scope and release schedule. Model fees and capital tied up separately.
Early terminationRemaining minimum bills, dedicated facilities or unrecovered system costs can survive a site exit.Exit formula at years 1, 3, 5 and 10; replacement-customer credits; assignment rights; and liability if the utility misses delivery.
Interruptible or curtailable serviceA lower service cost can come with an operating constraint. Backup systems do not automatically allow unrestricted operation during a curtailment.Notice, duration, frequency, restoration priority, penalties, generator permit limits and whether load above the reservation can be curtailed.

Three examples with the units kept separate

  • TVA capacity charge: for an eligible new 50 MW request in the first FY2027 cohort, the illustration is (50 − 5) × $1.521 million = $68.445 million. This is the nonrefundable capacity commitment charge, not a yearly energy bill. Cohort limits, existing and inflight treatment, expansion waivers and payment terms can change applicability. Start with the TVA entry and primary source.
  • Dominion security: the approved future GS-5 framework permits collateral up to $1.5 million per MW. At a 50 MW contract reservation, that ceiling illustrates $75 million of security exposure. The same record describes delivery minimums on 85% of contracted demand, or 42.5 MW in this example. These are different obligations; neither is a $75 million annual power bill. GS-5 starts January 1, 2027 and has additional eligibility conditions. See the Virginia rule and SCC order.
  • Ohio Power demand floor: use the published DCT formula and contract size, not actual IT demand alone. A delayed rack deployment does not automatically reduce reserved demand or erase the eight-year commitment following the permitted ramp. Price the low-load years and the exit case alongside steady operation. See Ohio Power's utility entry.

For a wholesale tenant, obtain the lease's treatment of each obligation. The operator may pay the utility directly while recovering selected costs through rent, power pass-throughs, deposits or termination provisions. The retail service agreement and the tenant lease need to reconcile.

Compare cooling, water and permits together

A cooling label alone does not establish water use. A liquid-cooled IT loop can reject heat through dry coolers, evaporative equipment or a combination. The relevant questions are where heat leaves the site, how much makeup water the design needs and whether that source can meet peak demand.

Cooling performance
Request annual and peak facility load for the same IT load. Compare PUE assumptions at the proposed site's summer design conditions and during partial occupancy. A single annual PUE does not prove the electrical or cooling capacity needed on the hottest design day.
Makeup water
Ask for annual volume and peak-day flow, the water source, treatment needs and drought restrictions. State whether a WUE number is makeup water or evaporated water, and whether its denominator is IT energy or total facility energy.
Water and sewer bills
Obtain the industrial meter rate, capacity or connection fees, minimums, included volume and sewer-billed share. Evaporated water is not automatically exempt from sewer charges; get any credit in writing.
Generator operation
Distinguish backup testing, emergency operation, demand response and continuous onsite generation. Obtain the applicable air-permit operating limits and fuel-storage approvals for the intended use.

Energy sensitivity: at 20 MW installed IT and 90% average IT utilization, reducing a constant PUE assumption from 1.30 to 1.20 reduces this simple annual screen by 15,768 MWh. At the retained US industrial benchmark of 9.03¢/kWh, that is about $1.424 million of benchmark spend. It is an arithmetic sensitivity, not a promised cooling upgrade result or a tariff savings estimate. Cooling capital, water, maintenance and actual efficiency still need pricing.

The state-specific water rules matter before equipment selection. The retained Oklahoma profile records a groundwater restriction for open-air evaporative cooling from November 1, 2026. Nevada's new commitment includes location-specific water standards. The South Carolina review records reporting tied to qualifying large loads, contract dates and monthly consumption. Follow those sources for their exact scope.

Use the operating cost estimator's cooling options to compare entered power, makeup water and sewer assumptions on the same property. State averages do not provide a local industrial water quote.

What a state shortlist must prove at the site

Move each candidate through the following evidence checks before a nonrefundable land or capacity commitment. Several can run together, but utility studies, local approval and equipment delivery must converge on the same in-service schedule.

  1. Allowed use and local process. Identify the parcel, incorporated or unincorporated jurisdiction, zoning category and any current moratorium. Obtain the actual ordinance and expiration or extension action. Record whether approval is by right, conditional, special-use or a rezoning vote. A local pause count is not an answer for a parcel.
  2. Firm power by phase. Ask the serving utility to name the delivery point, voltage, initial MW, expansion MW and study assumptions. Distinguish a feasibility response from a completed study and an executed service commitment. Record conditions that can delay the date.
  3. Connection scope and land rights. Locate the planned route, substations and crossings. Price line and transformer work, easements, road or rail crossings and permitting. A nearby substation does not establish spare capacity, a usable connection or a short construction schedule.
  4. Two usable network paths. Obtain carrier route drawings, entrances, splice points and upstream endpoints. Two carrier names can share a duct, bridge or upstream route. Verify the physical separation required by the application's resilience plan. See the site selection guide.
  5. Cooling and water permission. Match peak heat rejection and makeup-water demand to a supplier commitment. Confirm water rights or allocations, industrial connection capacity, discharge conditions and drought treatment. Include onsite generation's cooling needs when relevant.
  6. Physical and environmental constraints. Review floodplain, drainage, geotechnical conditions, wetlands, contamination, access and emergency fuel delivery at the parcel. Regional weather or seismic screening must be followed by site engineering and insurance review.
  7. Incentive certificate and ongoing compliance. Name the applicant, participating tenants, covered purchases, investment and payroll clocks, filing requirements and repayment triggers. Allocate savings to the party that actually receives them.
  8. One reconciled commercial schedule. Put land control, local hearings, utility studies, upgrade payments, long-lead equipment, commissioning, rent commencement and the IT ramp on one dated plan. Record which party bears delay costs and which commitments can be terminated.

The minimum useful shortlist packet

For each finalist, keep the parcel and jurisdiction, serving utility, written MW and date status, upgrade scope and owner share, tariff and service terms, water approach, network routes, incentive basis and unresolved approvals. Name a responsible party and next evidence milestone for each unknown. This is more useful than a state friendliness score because it makes the missing decision visible.

Keep four statuses distinct: announced campus plans; under construction capacity; energized facility capacity; and available to your project capacity supported by a commercial delivery commitment. A tax certificate, air permit or generation proposal cannot substitute for the others.

How we label each state

These labels summarize state incentives and recent restrictions in the 20 states reviewed. They do not measure overall friendliness, available power or the likelihood of a site approval. A state with new rules can still offer a workable project path. Read the utility and local evidence separately.

Open
State tax incentives remain open, and this review identified no new statewide conditions in 2025 or 2026 beyond ordinary utility contracts. Local moratoriums and project-specific obligations can still apply.
Open with new conditions
Tax breaks are still open, but the state, its regulators or its main utilities added cost, contract, water, siting or eligibility conditions in 2025 or 2026.
Tightening
The main tax break is closed, paused or cut for new projects, the state added a data-center-specific tax, or it withholds state help from large new projects.
Paused
A state-level approval, grid-connection or permitting pause affects new projects. Read the profile for the responsible agency, project scope and load threshold. Existing energized capacity needs a separate check.

Read status literally: a proposal is not an effective rule; an approved future tariff is not today's tariff. A local rejection or lawsuit is not a statewide ban. Local counts use different reporting coverage and cannot support a fair ranking.

Before you shortlist: identify the local jurisdiction, confirm the serving utility and your total facility load, then get written confirmation of eligibility, capacity and timing. A state average cannot answer those questions.

Full reference tables

Show all 20 states, power benchmarks and policy summaries
StateLabelData centersPower, ¢/kWhTax break for new projects
AlabamaOpen with new conditions457.93Abatements open; 20-year cap from 2027 (30 with local deal), trimmed for 100 MW+
ArizonaTightening1607.66Equipment sales and use tax exemption paused for new centers through June 2029
ArkansasOpen126.82Tax exemption open; Act 548 (2025) cut threshold to $100M, kept electricity exemption
GeorgiaOpen with new conditions2767.99Equipment sales tax exemption open to new projects through 2031; 2026 repeal bills failed
IllinoisTightening24210.24Exemption law unchanged; governor directive paused new applications July 1, 2026, no end date
IndianaOpen with new conditions1259.15Sales tax exemption open; 2026 law allows local payment, max 1% of electricity exemption
KentuckyOpen with new conditions567.50Sales and use tax exemption open statewide since 2025 law; $25M to $450M minimums
LouisianaOpen with new conditions236.65Sales tax exemption open but moving to invitation-only; June 2026 order requires eight-commitment attestation
MississippiOpen with new conditions257.66Sales, income and franchise tax exemptions open, no sunset; $20M and 20 jobs minimum
NevadaTightening768.43New abatements require a binding Community Support Commitment and full school-support tax payment before GOED board consideration
North CarolinaTightening977.91Equipment sales tax exemption open; electricity exemption repealed from August 6, 2026 billing periods
OhioTightening24010.32New exemption requests paused after the June 1, 2026 Tax Credit Authority meeting; no fixed end date stated
OklahomaOpen with new conditions486.69Equipment sales tax and five-year property tax breaks open; electricity usually not exempt
PennsylvaniaTightening17410.93Exemption needs GRID consent order since August 2026; fast-track permitting ended; repeal bills pending
South CarolinaOpen with new conditions487.85Equipment and electricity sales tax exemption open to centers certified before 2032
TennesseeOpen with new conditions656.82Sales tax exemption and 1.5% electricity tax rate still open; three-year pause only proposed
TexasOpen with new conditions5376.72Sales tax exemption open; governor seeks repeal, but no bill filed yet
UtahOpen with new conditions488.58Exemption open; optional county energy tax up to 6%; local incentives curbed 2027
VirginiaTightening67410.08Sales tax exemption open to new projects through June 2035; temporary $0.011/kWh power tax
WisconsinOpen with new conditions539.39Sales and use tax exemption, electricity included, open to new projects; no sunset date
Data centers listed: facilities of all sizes on Data Center Map, read October 7, 2026 (US total 4,767). Power: average price to industrial customers, January to July 2026, from EIA Electric Power Monthly, Table 5.6.B (US average 9.03¢). Tax break status as of October 7, 2026, sourced in each state profile below.
StateLarge-load power termsLocal moratoriums and pushback
AlabamaPSC cost test for 150 MW+ data center contracts; TVA first FY2027 cohort charge: $1.521M/MW, subject to exemptionsFoley, Tarrant, Baldwin County and at least eight other localities adopted or weighed moratoriums
ArizonaSRP minimum bill: 80% of forecast load, 20 MW+; APS proposes 45%+ data center rate riseTucson, Chandler and Pinal County rejected projects; Phoenix and Tucson added zoning rules
ArkansasEntergy's AVAIO contract pending at PSC: 15-year term, minimum bills, security; AVAIO to fund transmission upgradesFour counties and Russellville have moratoriums; Little Rock, Fayetteville and Fort Smith added rules
GeorgiaGeorgia Power loads over 100 MW: PSC-reviewed contracts, minimum bills, 15-year termsAt least four county moratoriums (Cobb, DeKalb, Paulding, Clayton); Lovejoy ban; Douglas rezoning denied
IllinoisComEd 50 MW+: take-or-pay agreements, 10 years' transmission revenue collateral, ICC-approved cancellation depositsMoratoriums include unincorporated Lake and Champaign counties, Lee County, Ottawa, Bourbonnais; Chicago pause proposed
Indiana2025 law: large loads guarantee 80%+ of utility project costs; I&M requires 12-year minimum contractsIU tracker: 32 county moratoriums, three bans; Indianapolis, Gary and Evansville adopted city pauses
KentuckyLG&E/KU over 50 MVA: 15-year-plus contracts, 80% minimum billing demand, up to 24 months' collateralMore than a dozen local moratoriums, including Louisville, Lexington and Scott County
LouisianaPSC fast track: 15-year contracts, large load pays at least half of new infrastructureOne citywide pause (New Orleans); St. Charles moratorium failed; Ascension siting rules pending
MississippiEntergy and Mississippi Power use custom contracts; TVA first FY2027 cohort charge: $1.521M/MW above a new request's first 5 MWJackson moratorium into 2027; Southaven xAI suits pending; Walls planners voted to deny rezoning
NevadaNV Energy proposed 25 MW+ contracts: minimum payments, guarantees, early-termination cost recovery; each needs PUCN approvalMoratoriums in Reno, Humboldt, White Pine, Wells; Nye's Pahrump-area ban faces lawsuit
North CarolinaDuke proposed 10- or 15-year contracts, 75% minimum bill; October 6 settlement awaits state regulatorsAt least 34 local moratoriums by September 4, 2026; Raleigh adopted one October 6
OhioOhio Power (formerly AEP Ohio) over 25 MW: minimum demand, ramp plus eight-year term, collateral, exit feesAt least 138 local moratoriums and 23 effective bans, per September 2026 news tally
OklahomaHB 2992: new 75 MW+ loads get separate tariffs, 10-year minimum terms; OG&E, PSO tariffs pendingMoratoriums in Oklahoma City (75 MW+), Norman, Seminole Nation; Cherokee, Cheyenne-Arapaho bans
PennsylvaniaPPL large loads (50 MW+): 10-year minimum contracts, load guarantees, exit fees, upgrade-cost collateralAt least four denials or withdrawals since November 2025; Hazle 180-day zoning-challenge pause
South CarolinaSantee Cooper 50 MW+ rate: 15-year contract, exit payment; Duke minimum terms 10 to 15+ yearsAt least seven counties enacted 2026 moratoriums, including Spartanburg, Greenwood, Anderson and Laurens
TennesseeTVA data center rate above 5 MW; first FY2027 cohort capacity charge subject to eligibilityAt least seven local moratoriums in 2026, Nashville and Knoxville included; Memphis vote pending
TexasERCOT energization pause at 75 MW+; adopted PUCT interconnection rule effective October 8. Intermediate security: $50,000/MW; later security may be higher.San Marcos ban; Hill County moratorium rescinded after $100M suit; Hood County rejected two moratorium proposals
UtahSB 132: new 100 MW+ loads pay incremental costs, post security, face curtailment above contractTooele County paused data center applications; three lawsuits pending over Box Elder's Stratos project
VirginiaDominion GS-5 (2027; 25 MW+, 75%+ load factor): 14-year terms, $1.5M/MW max collateral, 85% delivery minimumsPrince William overlay and special-use requirements vary by parcel; Loudoun special-exception rules and a proposed pause need a site-specific check
WisconsinWe Energies: 100 MW+ customers pay full generation costs, 15-year minimum term, collateral below A- rating21 counties adopted moratoriums by September 2026; Janesville enacted one; Milwaukee's is pending
Utility terms apply to the utility named, not the whole state. Local counts come from the trackers and news reports linked in each profile.

What the power price column does and does not tell you

The EIA figure is total industrial revenue divided by industrial sales in each state (EIA glossary). It blends industrial customers and their electricity bills. It is not a base energy rate to which you can simply add demand charges. Model energy, demand charges, minimum bills, riders and taxes from the actual tariff to estimate a data center bill. The effective rate can sit well above or below the state average.

The averages also miss new data-center-only charges. Virginia's temporary tax of $0.011 per kWh on data center electricity started July 1, 2026 (Virginia budget Item 3-5.24). TVA's data center rates started October 1, 2026 at manufacturing-rate levels, then rise in fiscal 2028 and 2029 to an expected bill impact of about 10 percent (TVA, August 2026). For TVA's first FY2027 cohort of up to 2,000 MW, the nonrefundable capacity commitment charge is $1.521 million per MW above a new request's first 5 MW. Existing and inflight rules, expansion waivers and TVA payment terms affect applicability (TVA, August 2026). Use the averages to compare states. Then price the actual tariff.

Pricing a specific site? Our landowner operating cost estimator models a large-load power bill with demand charges, riders and cooling water. Its worked example is a real Ohio property priced on AEP Ohio's published data center tariff. Alabama Power's Rate LPL is also included.

Leasing wholesale data center space rather than building? Power is usually billed on top of rent, so the local rate flows straight into your cost. See how power is billed in a wholesale lease.

State by state

Each profile opens with a planning watchpoint drawn from the evidence below it. Use the source links to check the exact scope, status and dates. Site-level power availability and approval remain unconfirmed.

Alabama

Confirm whether Alabama Power or a TVA distributor serves the site. Their obligations differ, and new incentive limits may affect the project schedule.

Open with new conditions 45 data centers listed Industrial power 7.93¢/kWh

Political climate and approval direction

Governor
Kay Ivey (Republican)
Legislative majority
House: Republican. Senate: Republican. Republican control.
State policy signal
Open incentive path with new cost-protection laws and 2027 abatement limits.
Local approval pressure
Local pauses include Baldwin County; state access does not settle rezoning.

Decision to watch: Separate the grant date, local land-use vote and PSC contract review. Confirm each before counting state support as a schedule advantage.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
Existing Chapter 9B tiers: up to $200 million supports a 10-year term; more than $200 million but less than $400 million supports 20 years. A 30-year term requires more than $200 million within ten years and more than $400 million within twenty years. The 2027 grant rules need a separate review.
Employment or payroll
No universal data-center job minimum established in this comparison. Other Alabama incentive programs have separate requirements.
Timing and duration
Existing terms run 10, 20 or 30 years; the 30-year tier has both ten-year and twenty-year investment tests. New abatement limits apply to grants on or after January 1, 2027.
What the benefit covers
Selected noneducational property and sales/use taxes. The retained 2027 law review caps terms at 20 years, or 30 with the required local agreement.

Budget implication: Separate the abatement grant date from the in-service date. A 100 MW+ project needs the new tax limitations reviewed before budgeting the same relief as a smaller project.

Alabama Legislature, April 2026 (primary; retained October 7 review); Alabama DOR, Chapter 9B program and 2027 notice (primary; reviewed 2026-10-09). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    Applications remain open; investment and program requirements still apply.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Alabama Legislature, April 2026 (primary)

  • Effective Alabama PSC jurisdiction

    Large data center contracts face a cost-recovery and customer-benefit test.

    Load: at least 150 MW. Effective from: 2026-10-01. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Alabama Legislature, April 2026 (primary)

  • Future effective date State incentive policy

    Grants from 2027 have 20-year caps, or 30 years with a qualifying local investment agreement.

    Load: No numerical threshold used in this screen. Effective from: 2027-01-01. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Alabama Legislature, April 2026 (primary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

Alabama's data center abatements stay open, but grants from 2027 are capped at 20 years, or 30 with a local investment deal (Alabama Legislature, April 2026). Since October 1, 2026, 150 MW-plus data center power contracts face a PSC test on cost recovery and benefits to other customers (Alabama Legislature, April 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Tax break: For grants from 2027 to 100 MW-plus sites, state property tax breaks end at in-service, as do state sales tax breaks on buildings and power systems (Alabama Legislature, April 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Alabama Power: Its large-load contracts include minimum bills and terms, upfront payments and collateral (Alabama Power, August 2026). It says PSC procedures under the new law are not final (Alabama Power, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

TVA: Data center rates equal manufacturing rates through September 2027, rising to about a 10% bill impact by fiscal 2029 (Tennessee Valley Authority, August 2026). TVA's first FY2027 cohort, up to 2,000 MW, has a nonrefundable $1.521 million per MW charge above a new request's first 5 MW, subject to existing/inflight treatment and payment terms (Tennessee Valley Authority, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Local rules: At least eight cities had adopted or weighed moratoria by September 2026 (Government Technology, September 2026). Baldwin County paused rezonings and new data center projects in county-zoned areas for 180 days on October 6 (Gulf Coast Media, October 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Model a bill on Alabama Power's published large-customer rate (Rate LPL) with our estimator.

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

Arizona

For a new project, check incentive eligibility and the specific utility commitment before pricing land. Local siting decisions remain a separate hurdle.

Tightening 160 data centers listed Industrial power 7.66¢/kWh

Political climate and approval direction

Governor
Katie Hobbs (Democratic)
Legislative majority
House: Republican. Senate: Republican. Divided government.
State policy signal
New incentive certifications are paused through June 2029. That law is an incentive restriction, not a statewide development ban.
Local approval pressure
Tucson, Phoenix, Chandler and Pinal County have different approval records.

Decision to watch: Track the incentive certificate separately from municipal zoning and utility capacity. A statement opposing a statewide ban does not approve a specific site.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
Legacy certification: $50 million in Maricopa or Pima County; $25 million elsewhere.
Employment or payroll
No job threshold established from the legacy program page reviewed here.
Timing and duration
Legacy investment window: five years after the certification letter. New-center incentive pause: July 1, 2026 through June 30, 2029 in the policy snapshot.
What the benefit covers
Qualifying equipment transaction privilege and use tax relief under an existing certification. Legacy thresholds do not establish a current new application path.

Budget implication: An existing building and an existing incentive certificate are different assets. Establish whether the certificate covers this operator, tenant and expansion before assigning it value.

Arizona House: 2026 enacted-law summary, Chapter 140, page 6 (primary; retained October 7 review); Arizona Commerce Authority, legacy CDC criteria (primary; reviewed 2026-10-09). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    New data centers cannot qualify for the program during the July 1, 2026 through June 30, 2029 pause. The enacted-law summary identifies Chapter 140 and lists September 12, 2026 as the general effective date; the data center restriction covers the earlier July 1 start.

    Load: No numerical threshold used in this screen. Effective from: 2026-07-01. Ends: 2029-06-30.

    Last source review: . Source reopened in this update. Review due: 2026-11-07.

    Arizona House: 2026 enacted-law summary, Chapter 140, page 6 (primary)

  • Effective SRP

    New large accounts face minimum billing based on actual demand or 80% of forecast load, whichever is greater.

    Load: at least 20 MW. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Source reopened in this update. Review due: 2026-11-07.

    Salt River Project (primary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

No new data centers qualify for Arizona's data center tax relief from July 2026 through June 2029 (Arizona Legislature, 2026 enacted-law summary). Governor Hobbs rejected calls for a statewide moratorium but said data centers must pay for themselves (KJZZ, September 2026).

Review recorded 2026-10-07. Retained from the initial source review.

A 2026 law lets regulators set minimum bills, collateral and exit terms for round-the-clock loads (Arizona Legislature, June 2026).

Review recorded 2026-10-07. Retained from the initial source review.

SRP bills new 20 MW+ accounts at least 80% of forecast load. Large loads pay upgrades upfront (Salt River Project).

Review recorded 2026-10-07. Retained from the initial source review.

APS proposed raising data center rates by over 45% (APS, July 2026). A regulator vote is due by December 31, 2026 (Corporation Commission, July 2026).

Review recorded 2026-10-07. Retained from the initial source review.

APS said grid constraints kept it from new data center commitments for 2.5 years (Arizona's Family, September 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Tucson declined Project Blue as proposed in August 2025 (City of Tucson, August 2025). Its 2026 rules require planned-development zoning, home setbacks and adequate water and power (City of Tucson, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Phoenix requires special permits for data centers (City of Phoenix, July 2025). Chandler (City of Chandler, December 2025) and Pinal County (Pinal County, August 2026) denied data center rezonings.

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

Arkansas

Open state incentives do not establish local permission. Check the county or city moratorium and obtain utility terms for this project.

Open 12 data centers listed Industrial power 6.82¢/kWh

Political climate and approval direction

Governor
Sarah Huckabee Sanders (Republican)
Legislative majority
House: Republican. Senate: Republican. Republican control.
State policy signal
Incentives expanded in 2025. The retained moratorium resolution was proposed and non-binding.
Local approval pressure
Local moratoriums, board approvals and a Clarksville bond election remain separate questions.

Decision to watch: Determine whether the project needs a discretionary board vote or public financing vote. Neither follows automatically from the state incentive program.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
Qualified data center: $100 million. Separate qualified large-data-center definition: $2 billion across the qualifying facilities.
Employment or payroll
Annualized compensation of at least $1 million for the standard category; $3 million for the large category. Qualifying contractor compensation can count.
Timing and duration
Standard investment: within five years after construction starts. Large category: ten years. Compensation test covers the two calendar years after operations begin.
What the benefit covers
Qualifying equipment, eligible costs, covered services and electricity. Positive state cost-benefit review is also required.

Budget implication: Use the correct category and clock in the construction budget. A multi-site project is not automatically a qualifying large data center; the statutory connectivity and investment tests still apply.

Arkansas Legislature, Act 548 of 2025 (primary; reviewed 2026-10-09). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    The reported equipment and electricity exemption remains open, with a $100 million investment threshold.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Kutak Rock, April 2025 (secondary)

  • Proposed Entergy Arkansas, AVAIO project only

    The proposed AVAIO agreement includes a 15-year term, minimum bills and security. It is not a statewide approved tariff.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Arkansas Democrat-Gazette, September 2026 (secondary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

The data center sales tax exemption widened in 2025 (Kutak Rock, April 2025). A non-binding resolution urging a statewide moratorium was proposed in August 2026 and referred to legislative committees (Arkansas Advocate, August 2026). Plan around utility contract terms and local siting votes.

Review recorded 2026-10-07. Retained from the initial source review.

Act 548 cut the investment threshold from $500 million to $100 million within five years and kept the electricity exemption (Kutak Rock, April 2025).

Review recorded 2026-10-07. Retained from the initial source review.

Entergy Arkansas's pending AVAIO application uses its standard Large Power Service rate and a contract with an initial 15-year term, minimum bills (charges owed even at low use) and security obligations (Arkansas Democrat-Gazette, September 2026). AVAIO would pay about $19 million in transmission upgrades in full (Arkansas Democrat-Gazette, September 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Talk Business reports Act 851 of 2023 bars local bans but allows rules that delay or significantly restrict projects (Talk Business & Politics, October 2026). The Advocate's map, updated October 5, 2026, shows moratoriums in Carroll, Union, Independence and Madison counties and in Russellville (Arkansas Advocate, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Fort Smith's ordinance, approved October 5, requires board approval, 500-foot setbacks and utility capacity and load letters (Talk Business & Politics, October 2026). Clarksville called a December special election on bonds for Serverfarm's $6.6 billion data center (KNWA FOX24, September 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

Georgia

Confirm local zoning and the utility delivery commitment first. An open incentive program does not establish that new power capacity is available.

Open with new conditions 276 data centers listed Industrial power 7.99¢/kWh

Political climate and approval direction

Governor
Brian Kemp (Republican)
Legislative majority
House: Republican. Senate: Republican. Republican control.
State policy signal
Equipment relief remains in the retained review; a 2026 repeal bill passed the Senate but stalled in the House.
Local approval pressure
County moratoriums, divided rezoning votes and litigation show site-specific opposition.

Decision to watch: Confirm the final legislative disposition and the parcel-level approval record. A vote in one chamber cannot be budgeted as enacted repeal.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
Investment and quality-job thresholds vary by county population and certificate date. Obtain the applicable county schedule before comparing incentives.
Employment or payroll
The application requires planned and maintained New Quality Jobs, with wage and work-hour records. Do not substitute temporary construction headcount.
Timing and duration
Meet the applicable investment-period tests and maintain the certificate. The retained policy review places the equipment exemption sunset at December 31, 2031.
What the benefit covers
High-technology data-center equipment exemption. Owner and customer applications are distinct; an owner bond can be required.

Budget implication: A tenant's equipment exemption needs its own documentation. Model any owner bond and the large-load contract separately from tax savings.

Alston & Bird, February 2026 (secondary; retained October 7 review); Georgia DOR, high-technology data-center application requirements (primary; reviewed 2026-10-09). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    The reported equipment exemption remains open through 2031, subject to certification.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: 2031-12-31.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Alston & Bird, February 2026 (secondary)

  • Effective Georgia Power

    Regulator-reviewed contracts can include 15-year terms and minimum bills.

    Load: over 100 MW. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Georgia Public Service Commission, January 2025 (primary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

Georgia's data center equipment sales tax exemption runs to December 31, 2031 (Alston & Bird, February 2026). A 2026 bill ending it for new projects passed the Senate but stalled in the House (Inside Climate News, April 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Power: Georgia Power can put loads over 100 MW on 15-year, regulator-reviewed contracts with minimum bills (Georgia Public Service Commission, January 2025). Early exit means owing minimum bills for the remaining term (Georgia Public Service Commission, April 2025). All 9,985 MW of generation approved in December 2025 is contracted (Georgia Public Service Commission, September 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Local: Paulding paused new proposals to January 1, 2027 (Spectrum News, August 2026), Cobb to early February 2027 (WSB-TV, August 2026) and DeKalb to March 30, 2027 (Decaturish, July 2026). Clayton County's moratorium, through 2026, excludes Lovejoy (Atlanta News First, August 2026), which banned data centers on September 21, 2026 (Atlanta Journal-Constitution, October 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Rezoning: Douglas County denied a 700-plus-acre rezoning (FOX 5 Atlanta, July 2026). Coweta approved 800-plus acres, 3 to 2 (Atlanta Journal-Constitution, April 2026), and residents sued to void it (The Citizen, May 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

Illinois

Check whether an incentive agreement already exists. New applications and large-load utility obligations need separate review.

Tightening 242 data centers listed Industrial power 10.24¢/kWh

Political climate and approval direction

Governor
JB Pritzker (Democratic)
Legislative majority
House: Democratic. Senate: Democratic. Democratic control.
State policy signal
New incentive applications stopped July 1. The retained POWER Act proposal is separate from the effective application pause.
Local approval pressure
Moratoriums and approved campuses coexist in different jurisdictions.

Decision to watch: Check existing-award coverage and the local application window. Separate proposed statewide conditions from the rules currently controlling the site.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
At least $250 million collectively by the data center and tenants over 60 months under published program criteria.
Employment or payroll
At least 20 new full-time or equivalent operating/maintenance jobs; compensation at least 120% of the county median full-time wage.
Timing and duration
60-month investment period. DCEO's page says new applications are not processed from July 1, 2026.
What the benefit covers
Covered state and local tax exemptions. A separate construction-wage credit applies to qualifying underserved-area projects.

Budget implication: A project can meet the published thresholds while new applications remain paused. For an existing agreement, verify tenant participation and whether planned phases fall within its terms.

Illinois DCEO, program criteria and application pause (primary; reviewed 2026-10-09). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    DCEO stopped processing new data center incentive applications on July 1, 2026. Existing agreements are a separate question.

    Load: No numerical threshold used in this screen. Effective from: 2026-07-01. Ends: no fixed end recorded.

    Last source review: . Source reopened in this update. Review due: 2026-11-07.

    Illinois DCEO (primary)

  • Effective ComEd

    Large projects face take-or-pay agreements and transmission-revenue collateral. Confirm the approved deposit terms.

    Load: at least 50 MW. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    ComEd, January 2026 (primary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

Illinois DCEO stopped processing data center tax incentive applications on July 1, 2026, per Illinois DCEO. The June 5 governor directive names no end date and honors existing agreements, per Office of the Governor, June 2026.

Review recorded 2026-10-07. Retained from the initial source review.

ComEd makes projects of 50 MW or more sign take-or-pay deals with collateral covering 10 years of transmission revenue, per ComEd, January 2026. Regulators approved ComEd deposit rules that protect existing customers if a large project is canceled, per Illinois Commerce Commission, March 2026.

Review recorded 2026-10-07. Retained from the initial source review.

House Bill 5513, the POWER Act (Prairie Rivers Network, February 2026), would require impact studies, water permits and annual fees for hyperscale sites, but has sat in the House Rules Committee since March 27, 2026, per Illinois General Assembly. Pritzker wants data center rules passed in the veto session starting November 17, 2026, per WAND TV, September 2026.

Review recorded 2026-10-07. Retained from the initial source review.

Active moratoriums cover unincorporated Lake (Shaw Local, September 2026) and Champaign (NPR Illinois, April 2026) counties, Lee County (Shaw Local, August 2026), Ottawa (Shaw Local, August 2026) and Bourbonnais (Shaw Local, June 2026). Chicago's mayor proposed a 12-month pause, which was sent to the council's rules committee, per Block Club Chicago, September 2026. Joliet (Shaw Local, March 2026) and Sangamon County (NPR Illinois, April 2026) still approved large campuses.

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

Indiana

Check the exact county and city rules, then the serving utility contract. The state incentive program does not override local pauses.

Open with new conditions 125 data centers listed Industrial power 9.15¢/kWh

Political climate and approval direction

Governor
Mike Braun (Republican)
Legislative majority
House: Republican. Senate: Republican. Republican control.
State policy signal
The equipment and utility incentive path remains open in the retained review, with project cost guarantees and local benefit-sharing conditions.
Local approval pressure
County and city moratoriums can prevent a site advancing despite state incentives.

Decision to watch: Obtain the local application status and required approvals before pricing the award. State and local political decisions can move in different directions.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
IEDC describes terms up to 25 years below $750 million and up to 50 years above $750 million. The separate local property-tax program uses a $25 million investment test.
Employment or payroll
The reviewed IEDC overview does not establish a universal job minimum. Confirm the state's project agreement and county-specific criteria.
Timing and duration
Duration is an awarded term, not an automatic entitlement. The $750 million boundary needs statutory review because the overview does not resolve equality.
What the benefit covers
State sales/use tax relief on qualifying equipment and energy. Local personal-property tax relief is a separate decision.

Budget implication: Do not use the local $25 million threshold as the state-program threshold. Compare local electricity-exemption payments and utility cost guarantees alongside the award.

Indiana Capital Chronicle, March 2026 (secondary; retained October 7 review); Indiana IEDC, state exemption and separate local property-tax program (primary; reviewed 2026-10-09). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    Prior research reports that equipment and utility exemptions remain open to qualifying projects.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Indiana Capital Chronicle, March 2026 (secondary)

  • Effective Indiana regulated utility project

    The retained law review describes an 80% utility-project cost guarantee. Confirm the statutory large-load definition with the utility.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Indiana General Assembly, May 2025 (primary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

Indiana still exempts data centers from its 7% sales tax on equipment and utilities (Indiana Capital Chronicle, March 2026). Check utility terms and local moratoriums before choosing a site.

Review recorded 2026-10-07. Retained from the initial source review.

House Bill 1210, signed in March 2026, lets local governments receive up to 1% of the electricity sales tax exemption for projects approved locally after June 30, 2026 (Indiana Capital Chronicle, March 2026).

Review recorded 2026-10-07. Retained from the initial source review.

A 2025 law (Indiana General Assembly, May 2025) makes large new loads guarantee at least 80% of the cost of utility projects built to serve them (Indiana Capital Chronicle, April 2025).

Review recorded 2026-10-07. Retained from the initial source review.

Indiana Michigan Power's approved terms for loads of at least 70 MW at one site or 150 MW in total require 12-year minimum contracts and bills based on at least 80% of contracted capacity (Indiana Capital Chronicle, November 2024; Indiana Michigan Power, February 2025).

Review recorded 2026-10-07. Retained from the initial source review.

An Indiana University tracker lists 32 counties with moratoriums and 3 that bar data centers (Indiana University ERI, October 2026). Indianapolis paused new projects through 2027 (Mirror Indy, August 2026). Gary's mayor ordered a one-year pause on new approvals (Capital B Gary, September 2026), and Evansville's council approved a 180-day moratorium (WNIN, October 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

Kentucky

Check the local moratorium and the serving utility's load threshold. Contract length and collateral can materially affect the commitment.

Open with new conditions 56 data centers listed Industrial power 7.50¢/kWh

Political climate and approval direction

Governor
Andy Beshear (Democratic)
Legislative majority
House: Republican. Senate: Republican. Divided government.
State policy signal
Statewide incentives coexist with a governor energy-plan requirement intended to protect other ratepayers.
Local approval pressure
Louisville, Scott County and Lexington have separate pause and extension records.

Decision to watch: Align the energy plan and utility contract with the local vote calendar. Divided state government does not remove executive or local approval requirements.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
Retained 2025 review: $25 million to $450 million, depending on county population and applicant category.
Employment or payroll
No universal operating-job threshold established in the retained summary. Obtain the applicable KEDFA approval requirements.
Timing and duration
The approval agreement controls eligible spend and timing. County population and project-organizer treatment require separate confirmation.
What the benefit covers
Sales/use tax exemption expanded statewide by the 2025 law. It does not waive the serving utility's collateral or minimum bills.

Budget implication: A lower county investment threshold does not reduce the LG&E/KU load threshold. Its rule is above 50 MVA, so an MW-only requirement needs a power-factor conversion.

Stites & Harbison, April 2025 (secondary; retained October 7 review); Kentucky PSC, February 2026 (primary; retained October 7 review). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    Prior research reports an open state tax incentive, subject to project qualification.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Stites & Harbison, April 2025 (secondary)

  • Effective LG&E / Kentucky Utilities

    Large-load terms include at least 15 years, an 80% minimum billing demand and up to 24 months of collateral. MW alone does not determine MVA eligibility.

    Load: over 50 MVA. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Kentucky PSC, February 2026 (primary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

The state tax break is open (Stites & Harbison, April 2025). Expect collateral-backed utility contracts (Kentucky PSC, February 2026) and local moratoria (Louisville Public Media, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

A 2025 law extended the sales and use tax exemption statewide, with $25 million to $450 million minimums by county population (Stites & Harbison, April 2025).

Review recorded 2026-10-07. Retained from the initial source review.

New LG&E and KU loads above 50 MVA need 15-year-plus contracts, minimum billing at 80% of contracted capacity and up to 24 months of minimum bills as collateral (Kentucky PSC, February 2026). East Kentucky Power Cooperative requires data centers of 15 MW or more to prepay at least six months of expected maximum bills (Kentucky PSC, October 2025).

Review recorded 2026-10-07. Retained from the initial source review.

A governor's executive order, not a law, requires an energy plan showing other ratepayers will not carry project costs (Kentucky Governor's Office, August 2026). Regulators approved a 482 MW Hawesville contract, noting consistency with it (Kentucky PSC, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Louisville Metro paused approvals until February 2027 or new rules (Louisville Public Media, September 2026). Scott County's pause runs to March 13, 2027 (Georgetown News-Graphic, September 2026). A Lexington extension to October 2027 is pending (WEKU, October 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

Louisiana

Confirm the current incentive application path and local siting rules before relying on state support. Request project-specific infrastructure terms.

Open with new conditions 23 data centers listed Industrial power 6.65¢/kWh

Political climate and approval direction

Governor
Jeff Landry (Republican)
Legislative majority
House: Republican. Senate: Republican. Republican control.
State policy signal
LED describes an invitation-only transition and an agency-supported commitment process.
Local approval pressure
New Orleans restrictions and parish-level siting rules differ.

Decision to watch: Establish who can issue the state invitation and which parish approvals remain. A favorable infrastructure process is separate from land-use permission.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
Retained program review: at least $200 million invested between July 2024 and July 2029.
Employment or payroll
Commitment to at least 50 new direct jobs in the retained program review.
Timing and duration
The investment window is tied to calendar dates, not a new five-year period whenever a buyer acquires land.
What the benefit covers
Qualifying equipment and construction, including covered substations and generators. The incentive pathway and required attestation remain separate conditions.

Budget implication: Reconcile remaining qualifying spend with the July 2029 deadline. Invitation or attestation requirements and utility-funded infrastructure terms cannot be replaced by meeting the dollar threshold.

Louisiana Economic Development, read October 2026 (primary; retained October 7 review); Louisiana Legislature, December 2024 (primary; retained October 7 review). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    LED describes an invitation-only transition and requires an attestation supported by environmental, energy and utility agencies.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Source reopened in this update. Review due: 2026-11-07.

    Louisiana Economic Development, read October 2026 (primary)

  • Effective Louisiana PSC fast-track process

    The retained process review describes 15-year agreements and at least half of new infrastructure costs paid by the large load. Confirm eligibility.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    WWNO, December 2025 (secondary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

The state is making its data center sales tax exemption invitation-only. Applicants must show how new grid costs get funded without shifting to existing customers (Louisiana Economic Development, read October 2026).

Review recorded 2026-10-07. Retained from the initial source review.

The exemption covers equipment and construction, including substations and generators. Projects must commit to 50 new jobs and $200 million invested from July 2024 to July 2029 (Louisiana Legislature, December 2024).

Review recorded 2026-10-07. Retained from the initial source review.

A June 2026 executive order ties it to eight commitments, including fully funding the incremental generation, transmission and infrastructure a project needs (Louisiana Governor's Office, June 2026).

Review recorded 2026-10-07. Retained from the initial source review.

A 3-2 regulator directive lets utilities skip the market test for large loads on 15-year contracts paying at least half of new infrastructure costs (WWNO, December 2025). Non-binding guidelines ask utilities for safeguards against stranded generation, such as corporate guarantees (Louisiana Public Service Commission, read October 2026).

Review recorded 2026-10-07. Retained from the initial source review.

New Orleans has barred new data centers citywide since January 2026. Planning staff propose permanently banning large and hyperscale sites, with a hearing October 13 (New Orleans City Planning Commission, October 2026). St. Charles Parish rejected a moratorium (St. Charles Herald Guide, April 2026), then limited data centers to industrial districts (St. Charles Herald Guide, June 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

Mississippi

Identify the serving utility before comparing costs. Check local permitting status and the requirements of the incentive program.

Open with new conditions 25 data centers listed Industrial power 7.66¢/kWh

Political climate and approval direction

Governor
Tate Reeves (Republican)
Legislative majority
House: Republican. Senate: Republican. Republican control.
State policy signal
State incentives remain open in the retained review, subject to investment and jobs tests.
Local approval pressure
Jackson has a moratorium; other project disputes have their own local and court records.

Decision to watch: Identify the decision-making municipality, county and utility. Treat state incentive eligibility and a contested local rezoning as separate milestones.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
At least $20 million for the standard data-center incentive program.
Employment or payroll
At least 20 jobs paying 125% of the state average wage.
Timing and duration
Retained program research describes ten-year relief. State approval and the project's award determine its commencement and covered purchases.
What the benefit covers
Certain construction-material and equipment sales/use tax relief, plus income and franchise tax relief. Electricity treatment has a separate statutory basis.

Budget implication: Keep the ten-year award separate from the state's lack of a program sunset. For a TVA-served property, the capacity commitment charge is an additional capital obligation.

NCSL, April 2026 (secondary; retained October 7 review); Mississippi Today, July 2026 (secondary; retained October 7 review); Mississippi Power, state data-center incentive thresholds (primary; reviewed 2026-10-09). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    Prior research reports an open data center incentive program; qualifying investment and employment are required.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    NCSL, April 2026 (secondary)

  • Effective TVA service area

    First FY2027 cohort, up to 2,000 MW: $1.521 million/MW above a new request's first 5 MW. Existing/inflight treatment, expansion waivers and TVA payment terms affect applicability.

    Load: over 5 MW. Effective from: 2026-10-01. Ends: 2027-09-30.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Tennessee Valley Authority, August 2026 (primary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

Mississippi's data center tax exemption stays open, with no sunset (NCSL, April 2026). Qualifying data centers pay no sales tax on electricity for industrial purposes (FindLaw, Miss. Code 27-65-107). In TVA areas, the first FY2027 cohort, up to 2,000 MW, has a nonrefundable $1.521 million per MW charge above a new request's first 5 MW, subject to existing/inflight treatment and payment terms (TVA Board, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

State-approved projects investing at least $20 million, with 20 jobs at 125% of average state wage, get 10-year sales tax breaks on certain construction materials and equipment, plus income and franchise tax breaks (Mississippi Today, July 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Entergy Mississippi says its Amazon contracts include a minimum bill, a contract term and termination provisions (Mississippi Today, July 2026).

Review recorded 2026-10-07. Retained from the initial source review.

TVA data center rates equal manufacturing rates through fiscal 2027, then rise to an expected 10% bill impact by fiscal 2029 (TVA Board, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Jackson passed a six-month moratorium on data center zoning and permits on July 14, 2026 (Mississippi Free Press, July 2026). WLBT says it ends January 13, 2027 (WLBT, October 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Walls planners voted September 22 to deny rezoning about 1,200 acres for a possible data center; aldermen will decide (DeSoto Times-Tribune, September 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

Nevada

Establish which incentive terms apply to the application and whether the local jurisdiction is accepting projects. Utility proposals still need approval.

Tightening 76 data centers listed Industrial power 8.43¢/kWh

Political climate and approval direction

Governor
Joe Lombardo (Republican)
Legislative majority
House: Democratic. Senate: Democratic. Divided government.
State policy signal
New abatements need a binding Community Support Commitment before GOED board consideration. Proposed 2027 changes are separate.
Local approval pressure
Reno and several counties have pauses or restrictions; water standards are location-specific.

Decision to watch: Confirm the commitment process and local water conditions. Track the legislative proposal through enactment rather than assuming it has already closed the current path.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
10-year abatement: $25 million within five years. 20-year abatement: $100 million within five years, aggregating the applicant and tenants.
Employment or payroll
10 or 50 full-time Nevada-resident jobs, respectively, within five years; wages at least the statewide average.
Timing and duration
Business-maintenance, insurance and construction-residency obligations apply. New applications require an executed Community Support Commitment before board consideration.
What the benefit covers
Partial equipment sales/use and personal-property abatements. General 2% sales-tax wording must be reconciled with the new school-support-tax requirement.

Budget implication: Compare the two award categories using permanent Nevada jobs, not contractor totals. Budget incremental electrical-service costs and location-specific water commitments outside the tax abatement.

Nevada Governor: Executive Order 2026-005 announcement, September 18, 2026 (primary; retained October 7 review); Nevada GOED, award tiers and Community Support Commitment (primary; reviewed 2026-10-09). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    GOED requires a binding Community Support Commitment before a new abatement application can reach its board. Requirements include full school-support tax payment, local water standards, incremental electricity costs and emergency load reduction. Confirm the commitment form and review timing with GOED.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Source reopened in this update. Review due: 2026-11-06.

    Nevada GOED: Data Center Abatements, checked October 7, 2026 (primary); Nevada Governor: Executive Order 2026-005 announcement, September 18, 2026 (primary)

  • Proposed NV Energy

    Proposed agreements include minimum payments, guarantees and termination-cost recovery; commission approval is required.

    Load: at least 25 MW. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    NV Energy, June 2026 (primary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

New data center abatements require a Community Support Commitment covering school-support taxes, water standards, electrical-service costs and grid reliability (Nevada GOED, checked October 2026). Applications cannot reach the GOED board before the commitment is executed (Office of the Governor, September 18, 2026). Confirm the applicable tax rate and commitment process for the specific application.

Review recorded 2026-10-07. Source reopened in this update.

An interim legislative committee voted to send the 2027 Legislature a bill to end the abatement and pause new and expanded data centers statewide (The Nevada Independent, September 2026). Democratic governor nominee Aaron Ford pledges to pause new tax breaks (The Nevada Independent, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

NV Energy proposed contracts for loads typically over 25 MW with minimum payments, guarantees and early-termination cost recovery, each needing regulator approval (NV Energy, June 2026). Regulators approved, subject to permits, two private gas plants totaling over 360 MW that a developer expects to run for Storey County projects until NV Energy can serve them (Nevada Current, September 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Reno paused approvals until August 2027, Humboldt and White Pine counties and Wells adopted moratoria, and Nye County banned data centers in a Pahrump-area groundwater basin (The Nevada Independent, August 2026), a ban two landowners have sued over (KTNV Channel 13, September 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

North Carolina

Budget electricity separately from the equipment exemption. Check local pauses and the status of the proposed Duke large-load terms.

Tightening 97 data centers listed Industrial power 7.91¢/kWh

Political climate and approval direction

Governor
Josh Stein (Democratic)
Legislative majority
House: Republican. Senate: Republican. Divided government.
State policy signal
Electricity relief was repealed; equipment relief remains in the retained review. A proposed end to new applications is a different action.
Local approval pressure
County and municipal moratoriums are independent; an existing project can present a vested-rights dispute.

Decision to watch: Separate the enacted electricity change, the equipment certificate and any proposed repeal. Obtain the local ruling on the project rather than assuming grandfathering.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
At least $75 million in qualifying private investment within five years for the qualifying-datacenter category, with a Commerce determination.
Employment or payroll
County-tier wage standards and employee health-insurance requirements. This is not a flat statewide minimum job count.
Timing and duration
Investment clock starts with the first qualifying investment. Electricity exemption repeal applies to billing periods beginning on or after August 6, 2026.
What the benefit covers
Qualifying support equipment relief remains distinct from the repealed electricity exemption.

Budget implication: A retained equipment certificate does not preserve tax-free electricity. Use billing-period dates when modeling the transition, then price the applicable Duke or other utility agreement.

NC Department of Revenue, July 2026 (primary; retained October 7 review); NCDOR, qualifying-datacenter definition (primary; reviewed 2026-10-09). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    Equipment exemption remains in the retained research; electricity relief has been repealed. Confirm the equipment certification path.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    NC Department of Revenue, July 2026 (primary)

  • Proposed Duke Energy

    The proposed large-load settlement describes 10- or 15-year terms and 75% minimum bills. Approval and the MW/load-factor test need confirmation.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Latitude Media, July 2026 (secondary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

North Carolina still exempts data center equipment from sales tax, but not their electricity in billing periods starting on or after August 6, 2026 (NC Department of Revenue, July 2026). At least 14 counties and 20 municipalities had moratoriums by September 4, 2026 (North State Journal, September 2026), and Raleigh adopted a six-month one on October 6, 2026 (News and Observer via Yahoo, October 2026).

Review recorded 2026-10-07. Retained from the initial source review.

The equipment exemption needs at least $75 million invested over five years, and Governor Stein proposed ending new applications after 2026 (WUNC, June 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Duke proposed 10 or 15 year contracts and a minimum bill of 75 percent of contracted demand for loads from 100 MW, or from 50 MW at an 80 percent load factor (Latitude Media, July 2026). A large load tariff settlement filed October 6, 2026, which Duke supports, awaits a commission ruling (NC Utilities Commission, October 2026).

Review recorded 2026-10-07. Retained from the initial source review.

House Bill 1189 would pause data center siting permits statewide (UNC School of Government, May 2026) but has sat in committee since May 5, 2026 (NC General Assembly).

Review recorded 2026-10-07. Retained from the initial source review.

A judge let a Chatham County data center proceed despite the county's February 2026 moratorium, after the developer argued it was already under way (Carolina Journal, September 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

Ohio

Verify the local moratorium and whether a prior incentive agreement covers the project. Confirm contract and exit obligations with the serving utility.

Tightening 240 data centers listed Industrial power 10.32¢/kWh

Political climate and approval direction

Governor
Mike DeWine (Republican)
Legislative majority
House: Republican. Senate: Republican. Republican control.
State policy signal
The governor paused new exemption proposals while a legislative committee reviews data-center growth. No fixed end is stated.
Local approval pressure
The retained local review reports numerous moratoriums and effective bans.

Decision to watch: Check the Tax Credit Authority application path and the specific city or township. Incentive reopening would not automatically reopen a local zoning process.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
Statutory investment minimum: $100 million over three consecutive calendar years for projects beginning in or after 2015.
Employment or payroll
At least $1.5 million in qualifying annual compensation, beginning with the agreement's specified post-month-24 period.
Timing and duration
Tax Credit Authority agreement controls the percentage and term. New requests remain paused in the retained October 7 policy snapshot.
What the benefit covers
A negotiated complete or partial equipment exemption, including covered related charges. A threshold is not a promise of a 100% award.

Budget implication: For an expansion, confirm that the existing agreement includes the project site and participating tenants. Ohio Power's minimum-demand, ramp and exit terms are separate from that agreement.

Governor DeWine Communications: May 27, 2026 official bulletin (primary; retained October 7 review); Ohio Revised Code, section 122.175 (primary; reviewed 2026-10-09). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    The governor directed the Tax Credit Authority to stop accepting new data center exemption proposals after its June 1, 2026 meeting while the legislative review proceeds. No fixed end date is stated. The directive pauses incentive requests; it is not a development ban.

    Load: No numerical threshold used in this screen. Effective from: 2026-06-02. Ends: no fixed end recorded.

    Last source review: . Source reopened in this update. Review due: 2026-11-07.

    Governor DeWine Communications: May 27, 2026 official bulletin (primary)

  • Effective Ohio Power (AEP Ohio)

    Term is ramp period plus eight years; minimum demand follows a tiered formula, with conditional collateral and exit fees. Affiliated loads can aggregate.

    Load: over 25 MW. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Source reopened in this update. Review due: 2026-11-07.

    Ohio Power Company, July 2025 (primary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

A governor's directive paused new requests for Ohio's data center tax exemption while a legislative committee studies data center growth (Office of the Governor of Ohio, May 2026). State data center tax incentives were still on hiatus in September 2026 (Ohio Capital Journal, September 2026).

Review recorded 2026-10-07. Retained from the initial source review.

The exemption statute still stands (Ohio Legislative Service Commission, September 2025). A Senate version of House Bill 646 would cap it at 50 percent for new agreements (Ohio Legislative Service Commission, June 2026). It is a proposal, sent back to committee on June 10, 2026 (Ohio General Assembly, June 2026).

Review recorded 2026-10-07. Retained from the initial source review.

AEP Ohio began using its legal name, Ohio Power Company, on October 1, 2026 (Ohio Power Company, September 2026). Its contracts for data centers above 25 MW run up to four ramp-up years plus eight more, with minimum demand charges, exit fees and, for some buyers, collateral (Ohio Power Company, July 2025).

Review recorded 2026-10-07. Retained from the initial source review.

In August 2026, regulators ordered AEP Ohio data center customers returning to standard utility supply to give 180 days' notice and bear the full cost of separately bought energy (Public Utilities Commission of Ohio, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

At least 138 municipalities and townships had data center moratoriums as of September 17, 2026, and 23 communities had effectively banned them (Ohio Capital Journal, September 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

Oklahoma

Check the load threshold, local or tribal jurisdiction and cooling-water approach. Separate pending utility tariffs from rules already in force.

Open with new conditions 48 data centers listed Industrial power 6.69¢/kWh

Political climate and approval direction

Governor
Kevin Stitt (Republican)
Legislative majority
House: Republican. Senate: Republican. Republican control.
State policy signal
Equipment incentives remain open while large-load cost rules and a future cooling-water restriction add conditions.
Local approval pressure
Municipal and tribal governments have distinct moratoriums and bans.

Decision to watch: Confirm land status and the government with jurisdiction before reading the state label. A state incentive does not override a tribal land restriction.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
The reviewed Commerce guide uses activity and revenue tests for equipment relief; it does not provide one universal capital-investment threshold.
Employment or payroll
No common job minimum across these exemptions. The Quality Jobs cash incentive is a separate program.
Timing and duration
Property-tax relief and sales-tax relief have separate applications, property classes and terms.
What the benefit covers
NAICS 518210 hosting/data processing equipment relief requires at least 80% out-of-state revenue. The guide includes electric power for eligible 519130/519290 web-search categories, not every hosting business.

Budget implication: Classify the actual operating business before assigning an electricity exemption. Do not apply a web-search or digital-asset-mining exemption to a wholesale hosting tenant by analogy.

Oklahoma Commerce, industry-specific tax guide (primary; reviewed 2026-10-09). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    Equipment and property incentives remain in the retained research, subject to program requirements; electricity is usually not exempt.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Oklahoma Department of Commerce, October 2024 (primary)

  • Effective Oklahoma utility large-load tariffs

    New large loads require separate tariffs and at least 10-year contract terms. Confirm the serving utility tariff.

    Load: at least 75 MW. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Oklahoma Legislature, May 2026 (primary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

Bills to narrow the property tax break (Oklahoma Legislature, February 2026) and pause 100 MW-plus data centers (Oklahoma Legislature, April 2026) never left committee before the session ended (KGOU, May 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Cloud and hosting firms with 80%-plus out-of-state revenue skip sales tax on equipment, not electricity (Oklahoma Department of Commerce, October 2024). The state can cover their property taxes for five years (The Frontier, February 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Developers buying land for 75 MW-plus sites outside municipalities and industrial parks must notify regulators, the county and neighbors within 60 days (Oklahoma Corporation Commission, July 2026). Utilities must give them separate tariffs with 10-year minimum terms (Oklahoma Legislature, May 2026). OG&E proposes 15-year terms and full upfront connection payments (OG&E, June 2026). A judge-backed large-load tariff in PSO's rate case awaits a commission ruling (Tulsa Flyer, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

From November 1, 2026, data centers cannot use groundwater for open-air evaporative cooling (Oklahoma House of Representatives, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Oklahoma City paused 75 MW-plus data centers through 2026 (KGOU, May 2026). Norman (KGOU, June 2026) and the Seminole Nation (KGOU, September 2026) also enacted moratoriums. The Cherokee Nation banned hyperscale data centers on tribally owned and trust land (KGOU, August 2026). Cheyenne and Arapaho members approved a three-year tribal land ban (KGOU, October 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

Pennsylvania

Confirm local approvals and the state permit and incentive pathway. Review the serving utility's load guarantees and upgrade security.

Tightening 174 data centers listed Industrial power 10.93¢/kWh

Political climate and approval direction

Governor
Josh Shapiro (Democratic)
Legislative majority
House: Democratic. Senate: Republican. Divided government.
State policy signal
Equipment relief requires a GRID consent order. The retained executive order ties certain DEP permits to local approvals.
Local approval pressure
Municipal decisions and zoning challenges can control whether state permitting advances.

Decision to watch: Secure the local approval record and consent-order pathway. Split legislative control does not mean executive agency processes stand still.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
Retained GRID guideline review: at least $250 million and payment of the full cost of new power capacity.
Employment or payroll
At least 50 jobs paying 125% of the state average wage in the retained GRID review.
Timing and duration
Since August 2026, the equipment-exemption pathway requires a GRID consent order. Approval and compliance milestones are project-specific.
What the benefit covers
Covered computer-data-center equipment exemption after the required consent process. State permit and local zoning approvals remain separate.

Budget implication: Compare the consent-order obligations with the utility's upgrade security. Identify overlapping infrastructure costs before treating both documents as separate full payments.

Pennsylvania Department of Revenue, August 2026 (primary; retained October 7 review); Utility Dive, March 2026 (secondary; retained October 7 review). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    New applications must include an executed DEP consent order implementing the GRID standards.

    Load: No numerical threshold used in this screen. Effective from: 2026-08-18. Ends: no fixed end recorded.

    Last source review: . Source reopened in this update. Review due: 2026-11-07.

    Pennsylvania Department of Revenue, August 2026 (primary)

  • Effective PPL Electric

    Large-load terms include at least 10 years, load guarantees, exit charges and upgrade-cost collateral.

    Load: at least 50 MW. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Pennsylvania PUC, June 2026 (primary)

  • Effective Projects needing DEP permits and local approvals

    DEP permits for projects over 25 MW are held until local approvals are obtained. Confirm local approval before relying on state permitting.

    Load: over 25 MW. Effective from: 2026-08-18. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Pennsylvania Governor's Office, August 2026 (primary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

Since August 18, 2026, data center equipment sales tax exemption applicants need a GRID consent order with the state DEP (Pennsylvania Department of Revenue, August 2026). A same-day executive order ends data center fast-track permitting and holds DEP permits for projects over 25 MW until local approvals (Pennsylvania Governor's Office, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

GRID requires paying the full cost of new power capacity, at least $250 million invested and 50 jobs at 125% of the state average wage (Pennsylvania Governor's Office, May 2026).

Review recorded 2026-10-07. Retained from the initial source review.

PPL Electric's settlement proposed 10-year minimum contracts, load guarantees, exit fees and upgrade-cost security for 50 MW-plus loads (Utility Dive, March 2026). Regulators approved it with a farm biogas change (Pennsylvania PUC, June 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Exemption repeal bills passed the House 197-5 and the Senate 44-6 (Route Fifty, June 2026), but both sit in committee and neither is law (Pennsylvania General Assembly, June 2026; Pennsylvania General Assembly, October 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Hazle Township denied a data center in November 2025, then paused zoning challenges for 180 days (Times Leader, June 2026). Montour County (Inside Climate News, February 2026) and East Vincent Township (Philadelphia Inquirer, May 2026) also denied proposals.

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

South Carolina

Check the county, serving utility and project size together. Incentive eligibility does not remove utility commitments or local restrictions.

Open with new conditions 48 data centers listed Industrial power 7.85¢/kWh

Political climate and approval direction

Governor
Henry McMaster (Republican)
Legislative majority
House: Republican. Senate: Republican. Republican control.
State policy signal
Incentive certification remains available before 2032, with investment and employment conditions. Large-load obligations remain separate.
Local approval pressure
Several county moratoriums and project-size rules appear in the retained research.

Decision to watch: Obtain the county ordinance and its size definitions, then the utility contract. State certification cannot substitute for county acceptance.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
Retained statute review: at least $50 million for the qualifying data-center exemption.
Employment or payroll
At least 25 full-time jobs in the retained qualification review.
Timing and duration
Certification must occur before 2032 under the reviewed program. Eligible investment and job periods need project-level confirmation.
What the benefit covers
Qualifying equipment and electricity sales-tax exemption, subject to certification and ongoing requirements.

Budget implication: Match the tax certification schedule to the utility ramp. Santee Cooper's reviewed large-load rate requires full load within three years, which is a separate operating commitment.

South Carolina Legislature, October 2026 (primary; retained October 7 review); SC Daily Gazette, April 2025 (secondary; retained October 7 review). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    The exemption requires certification before 2032 and qualifying investment and employment.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    South Carolina Legislature, October 2026 (primary)

  • Effective Santee Cooper

    Retained reporting describes 15-year terms and an exit payment; confirm the current service agreement.

    Load: at least 50 MW. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    SC Daily Gazette, April 2025 (secondary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

The sales tax exemption on data center equipment and electricity covers centers certified before 2032 investing at least $50 million and creating 25 full-time jobs (South Carolina Legislature, October 2026). A one-year suspension failed in the Senate in April 2026 (SC Daily Gazette, April 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Power: Santee Cooper's experimental 50 MW-plus rate for new loads, effective April 2025, requires a 15-year contract, a set exit payment and full load within three years (SC Daily Gazette, April 2025).

Review recorded 2026-10-07. Retained from the initial source review.

Regulator: The Public Service Commission's open docket on 50 MW-plus loads has a workshop October 26 and 27 (SC Public Service Commission, August 2026). Duke said 50 to 100 MW loads get 10-year minimum terms; larger ones would get 15-plus years (SC Public Service Commission, Duke filing, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Water: The ratified 2026-27 budget makes 50 MW-plus centers signing power contracts after 2026 report monthly use of 3 million gallons or more (South Carolina Legislature, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Counties: Chesterfield and Newberry (SC Daily Gazette, June 2026), Chester (WBTV, July 2026), Greenwood (Fox Carolina, July 2026), Anderson (Fox Carolina, August 2026) and Laurens (Fox Carolina, September 2026) enacted moratoriums. Spartanburg's one-year freeze covers new centers over 65 MW, and smaller ones off industrial sites or self-generating beyond backup (Fox Carolina, September 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

Tennessee

Confirm local permission and whether TVA service applies. Account for the capacity charge separately from ongoing electricity bills.

Open with new conditions 65 data centers listed Industrial power 6.82¢/kWh

Political climate and approval direction

Governor
Bill Lee (Republican)
Legislative majority
House: Republican. Senate: Republican. Republican control.
State policy signal
Equipment relief remains open; a suggested three-year incentive pause is a planned 2027 bill, not an enacted pause.
Local approval pressure
Nashville restrictions, Knoxville's moratorium and a pending Memphis vote differ.

Decision to watch: Recheck the actual local vote and the next legislative filing. A suggested statewide pause and an adopted local pause have different practical effects.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
Department of Revenue notice: required capital investment in excess of $100 million.
Employment or payroll
DOR's 2016 notice: at least 15 new permanent full-time jobs paying at least 150% of the state average occupational wage, with minimum health care.
Timing and duration
DOR's 2016 notice uses a three-year investment period. Verify current certification and later ownership/reorganization provisions; reopening the historical notice is not a full current-law review.
What the benefit covers
Qualifying equipment sales-tax exemption and reduced electricity taxation. The retained state review lists a 1.5% electricity tax rate.

Budget implication: The incentive investment period and TVA service commitment are different clocks. Align the initial load ramp with both before calculating tax savings or the capital charge.

Local 3 News, September 2026 (secondary; retained October 7 review); Tennessee DOR, qualified-data-center requirements notice 16-06 (primary; reviewed 2026-10-09). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    Prior research reports open equipment relief and a reduced electricity tax rate; a suggested pause is not an enacted restriction.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Local 3 News, September 2026 (secondary)

  • Effective TVA service area

    First FY2027 cohort, up to 2,000 MW: $1.521 million/MW above a new request's first 5 MW. Existing/inflight treatment, expansion waivers and TVA payment terms affect applicability.

    Load: over 5 MW. Effective from: 2026-10-01. Ends: 2027-09-30.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Tennessee Valley Authority, August 2026 (primary)

  • Proposed State incentive policy

    A suggested three-year incentive pause is a planned 2027 bill, not an enacted pause.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    FOX 17, September 2026 (secondary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

Tennessee's data center tax breaks remain in effect (Local 3 News, September 2026). New costs are TVA's data center capacity charge (TVA, August 2026) and local moratoria like Knoxville's (Spectrum News, July 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Projects of $100 million or more with 15 full-time jobs get a sales tax exemption on certain equipment and a 1.5% electricity tax rate (Local 3 News, September 2026). A three-year pause is only a planned 2027 bill (FOX 17, September 2026).

Review recorded 2026-10-07. Retained from the initial source review.

A May 2026 law generally bars cities and utilities from funding grid infrastructure for data centers projected to peak at 50 MW or more (Tennessee General Assembly, May 2026).

Review recorded 2026-10-07. Retained from the initial source review.

TVA's data center rate, mandatory above 5 MW, matches manufacturing rates from October 1, 2026, with bills expected to rise about 10% by fiscal 2029 (TVA, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

The first FY2027 cohort, up to 2,000 MW, has a nonrefundable $1.521 million per MW charge above a new request's first 5 MW; existing/inflight treatment, expansion waivers and TVA payment terms affect applicability (TVA, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Nashville banned the largest data centers and paused new permits through December 1, 2026 (Nashville Banner, July 2026). Memphis postponed its moratorium vote to October 20, 2026 (Action News 5, October 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

Texas

Open for data center loads under 75 MW, which go through the local utility's approval process. ERCOT has paused energization of new loads of 75 MW or more. A separate directive holds TCEQ permits for data center projects of any size, so confirm which permits your site needs.

Open with new conditions 537 data centers listed Industrial power 6.72¢/kWh

Targeted policy check: 2026-10-09. ERCOT energization pause, TCEQ permit directive, adopted large-load interconnection rule and the October 12 State and Community Impact RFI deadline. This is a targeted source check, not a full Texas permitting or incentive audit. Other evidence retains its individual source dates.

Political climate and approval direction

Governor
Greg Abbott (Republican)
Legislative majority
House: Republican. Senate: Republican. Republican control.
State policy signal
The targeted October 9 review confirms reported ERCOT and TCEQ holds and the effective interconnection funding rule. Incentive repeal remains a proposal.
Local approval pressure
Hill County rescinded its moratorium after a developer lawsuit; that local change is separate from the state holds.

Decision to watch: Keep energization, environmental permitting and tax certification on separate schedules. Audit or reporting deadlines are not automatic reopening dates.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
Standard category: $200 million within five years; $250 million supports the longer term. Separate large-project category: $500 million within five years.
Employment or payroll
20 qualifying jobs for the standard category; 40 for the large-project category. Job-location and compensation tests also apply.
Timing and duration
Standard exemption: ten years, or fifteen with the higher investment. Large-project exemption: twenty years. Investment clock starts at certification.
What the benefit covers
State sales/use tax relief on specified operating purchases. Standard projects need at least 100,000 SF; large projects at least 250,000 SF. Single-occupant restrictions apply.

Budget implication: A multi-tenant wholesale campus is not automatically eligible for these single-occupant programs. Incentive certification also does not resolve the separately reported ERCOT or TCEQ holds.

Texas Comptroller, standard and large-project certification (primary; reviewed 2026-10-09). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    The Comptroller accepts applications for qualifying projects. Certification and investment, jobs and facility requirements apply.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Source reopened in this update. Review due: 2026-11-07.

    Texas Comptroller, accessed October 2026 (primary)

  • Effective ERCOT large-load interconnection: new requests and specified expansions; incremental addition for expansions; Batch Zero transition provisions apply

    Adopted 16 TAC 25.194 took effect October 8. At the intermediate agreement: $100,000 study fee and $50,000/MW security. At the standard large-load agreement: security is the greater of $50,000/MW of contracted peak demand or allocated system-upgrade costs. Separate direct interconnection costs and additional security may apply; funding does not lift the energization or permit holds.

    Load: at least 75 MW. Effective from: 2026-10-08. Ends: no fixed end recorded.

    Last source review: . Source reopened in this update. Review due: 2026-11-09.

    Texas Register, adopted 16 TAC 25.194, October 2, 2026 (primary)

  • Effective Projects requiring a TCEQ permit

    The September 21 directive pauses issuance of all TCEQ permits related to data center projects until ERCOT completes its review. October 19 is TCEQ's compliance-report deadline, not an expiration date. Confirm the permits required for your project; this directive does not establish a ban on leasing existing capacity.

    Load: No numerical threshold used in this screen. Effective from: 2026-09-21. Ends: no fixed end recorded.

    Last source review: . Source reopened in this update. Review due: 2026-10-19.

    Office of the Texas Governor, September 2026 (primary)

  • Effective ERCOT interconnection

    ERCOT reports paused energization approvals for data center and virtual-currency-mining loads of at least 75 MW until Batch Zero eligibility verification is complete. Medium loads (25 MW to below 75 MW) are outside this specific pause, but remain subject to other approvals and information requests. December 10 is the planned report date, not an automatic end date.

    Load: at least 75 MW. Effective from: 2026-08-03. Ends: no fixed end recorded.

    Last source review: . Source reopened in this update. Review due: 2026-10-12.

    ERCOT, August 2026 (primary)

  • Proposed State incentive policy

    The governor has called for repealing incentives; the retained review does not establish enacted repeal.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Office of the Texas Governor, July 2026 (primary)

  • Withdrawn / rescinded Hill County only

    Hill County rescinded its moratorium. This does not settle another jurisdiction or restore paused state approvals.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    The Texas Tribune, August 2026 (secondary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

A governor directive, not a law, holds new data center grid approvals until a state audit ends, and sets no end date (Office of the Texas Governor, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

ERCOT's presentation confirms an energization pause for data center and crypto loads of at least 75 MW. Medium loads of 25 MW to below 75 MW continue through their transmission/distribution provider's approval process outside this specific pause. The planned report date is December 10 and PUCT meeting date December 17; neither is an automatic reopening date (ERCOT, August 20 presentation, pages 2, 7 and 10; reopened October 9).

Review recorded 2026-10-09. Source reopened in this update.

The September 21 directive pauses TCEQ permit issuance until ERCOT completes its review. It requires a compliance update by October 19, not a permit reopening on that date (Governor's letter, pages 1-2; reopened October 9).

Review recorded 2026-10-09. Source reopened in this update.

The sales tax exemption on electricity, cooling and emergency generators remains in effect (Texas Comptroller, accessed October 2026). The governor's plan to repeal it is a proposal, not law (Office of the Texas Governor, July 2026).

Review recorded 2026-10-07. Retained from the initial source review.

The adopted interconnection rule took effect October 8. Intermediate security is $50,000/MW; the $100,000 study fee is separate. At the standard agreement, security is the greater of $50,000/MW or allocated upgrade costs. For expansions, confirm the incremental-load test; Batch Zero loads have transition provisions (Texas Register, 16 TAC 25.194(b), (d), (f) and (h); reviewed October 9).

Review recorded 2026-10-09. Source reopened in this update.

Hill County rescinded its moratorium after a developer sued for $100 million (The Texas Tribune, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

ERCOT's September 24 notice says previously identified substantiated medium-load data centers must complete their issued State and Community Impact RFI. Responses, including voluntary RFIs issued to newly substantiated medium loads, are due October 12 at 5 p.m. Central Prevailing Time. The October 5 cutoff for issuing new voluntary medium-load RFIs has passed; it was not the response deadline (ERCOT notice M-B091426-02; reviewed October 9).

Review recorded 2026-10-09. Source reopened in this update.

Back to state finder and comparison · Compare power costs

Utah

Check the serving utility's large-load rules, local jurisdiction and the timing of incentive changes. Confirm project-specific security and service terms.

Open with new conditions 48 data centers listed Industrial power 8.58¢/kWh

Political climate and approval direction

Governor
Spencer Cox (Republican)
Legislative majority
House: Republican. Senate: Republican. Republican control.
State policy signal
Equipment relief remains available in the retained review; limits on some local incentives start in May 2027.
Local approval pressure
Tooele County and Box Elder project litigation show different local approval risks.

Decision to watch: Read the statutory exception and local award terms before carrying an incentive into a later phase. Resolve the parcel-specific legal and approval record.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
The retained equipment-exemption review does not establish a universal dollar threshold. Facility definition and ownership tests must be checked separately.
Employment or payroll
No universal operating-job minimum established for this equipment exemption. Negotiated post-performance credits are separate awards.
Timing and duration
Certain locally funded incentive limitations begin May 6, 2027; statutory exceptions require a separate review.
What the benefit covers
Qualifying equipment sales-tax exemption. Optional county energy tax and negotiated local awards are separate items.

Budget implication: Keep a project-specific tax credit out of the default statewide savings assumption. A 100 MW+ utility contract's incremental costs and security still need their own budget.

Utah State Legislature, July 2026 (primary; retained October 7 review); Utah State Legislature, May 2026 (primary; retained October 7 review). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    Qualifying data center equipment remains exempt under the retained state-code research.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Utah State Legislature, July 2026 (primary)

  • Effective Large-scale electric utility under SB 132

    Large-load contracts recover incremental costs, require security and allow curtailment above the contracted amount.

    Load: at least 100 MW. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Utah State Legislature, May 2025 (primary)

  • Future effective date Qualifying local incentive programs

    Limits on certain locally funded incentives for large-load data centers begin May 6, 2027, with statutory exceptions.

    Load: No numerical threshold used in this screen. Effective from: 2027-05-06. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Utah State Legislature, May 2026 (primary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

Utah exempts qualifying data center equipment from sales tax (Utah State Legislature, July 2026). Under SB 132, new loads of 100 MW or more served by a large-scale electric utility must pay all just and reasonable incremental costs (Utah State Legislature, May 2025).

Review recorded 2026-10-07. Retained from the initial source review.

From May 6, 2027, local governments cannot give large-load data centers incentives funded by tax increment or personal property tax, with exceptions such as approved development zones (Utah State Legislature, May 2026). Counties may also tax electricity and gas delivered to large loads and qualifying data centers on unincorporated land, up to 6 percent (Utah State Legislature, May 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Large-load utility contracts must require financial security and allow service cuts above the contracted amount (Utah State Legislature, May 2025). Regulators approved one such Rocky Mountain Power contract (Utah Public Service Commission, April 2026).

Review recorded 2026-10-07. Retained from the initial source review.

In April 2026, the state awarded Creekstone's Delta data center a post-performance tax credit worth about $172 million over 20 years (Utah News Dispatch, September 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Tooele County paused data center applications pending an ordinance (Utah News Dispatch, September 2026). Three lawsuits over Box Elder County's Stratos project are pending (Deseret News, October 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

Virginia

Model the temporary electricity tax and applicable utility contract alongside incentives. Verify the county approval path for the particular site.

Tightening 674 data centers listed Industrial power 10.08¢/kWh

Political climate and approval direction

Governor
Abigail Spanberger (Democratic)
Legislative majority
House: Democratic. Senate: Democratic. Democratic control.
State policy signal
Equipment relief remains available, while the retained executive order restricts state site-readiness and fast-track assistance for large projects.
Local approval pressure
Loudoun and Prince William are changing by-right and discretionary approval paths.

Decision to watch: Establish whether the site needs a special approval and whether state assistance applies. Distinguish loss of state assistance from a blanket construction ban.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
Ordinary category: $150 million. Qualifying distressed locality: $70 million with the reduced-job criteria.
Employment or payroll
50 new operating/maintenance jobs, or 10 in a qualifying distressed locality; jobs pay at least 150% of the locality's prevailing average wage.
Timing and duration
VEDP memorandum sets investment, jobs, compliance timing and repayment. Ordinary exemption ends June 30, 2035; special extension categories require separate review.
What the benefit covers
Covered equipment and enabling software, including qualifying replacement and upgrade equipment. General building improvements are excluded from this provision.

Budget implication: A locality's distressed status is tested when the memorandum is executed. Model the temporary electricity tax and future Dominion GS-5 obligations independently of the equipment exemption.

Virginia Code, section 58.1-609.3(18) (primary; reviewed 2026-10-09). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    Qualifying equipment purchases and leases are exempt through June 30, 2035, with investment, job and agreement requirements.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: 2035-06-30.

    Last source review: . Source reopened in this update. Review due: 2026-11-07.

    Virginia General Assembly, Code § 58.1-609.3 (primary)

  • Future effective date Dominion Energy Virginia

    Approved GS-5 starts January 1, 2027. It also requires at least a 75% load factor. Terms include 14 years, 85% delivery minimums and collateral up to $1.5 million per MW.

    Load: at least 25 MW. Effective from: 2027-01-01. Ends: no fixed end recorded.

    Last source review: . Source reopened in this update. Review due: 2027-01-01.

    Virginia State Corporation Commission, November 2025 (primary)

  • Effective Qualifying Virginia data centers

    A temporary electricity consumption tax of $0.011/kWh applies to qualifying data centers of at least 1 MW, including onsite generation.

    Load: at least 1 MW. Effective from: 2026-07-01. Ends: 2028-06-30.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Virginia General Assembly, June 2026 (primary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

Virginia still exempts qualifying data center equipment from sales tax through June 30, 2035 (Virginia General Assembly, Code § 58.1-609.3). Budget for a power tax, long Dominion contracts and county votes.

Review recorded 2026-10-07. Retained from the initial source review.

Some legislators who favor repeal pledged to revisit the exemption as soon as 2027 (Hunton Andrews Kurth, July 2026).

Review recorded 2026-10-07. Retained from the initial source review.

An enacted $0.011 per kWh tax covers power at 1 MW+ data centers, onsite generation included, from July 2026 through June 2028 (Virginia General Assembly, June 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Dominion's approved GS-5 rate for 25 MW+ customers with 75%+ load factors starts January 1, 2027: 14-year contracts, collateral up to $1.5 million per MW and minimum delivery charges on 85% of contracted demand (Virginia State Corporation Commission, November 2025).

Review recorded 2026-10-07. Retained from the initial source review.

Since September 18, 2026, Executive Order 22 bars new 25 MW+ data center projects from state site-readiness and fast-track permitting help (Office of the Governor of Virginia, September 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Prince William voted to end new by-right approvals, which skip a board vote, after a 90-day grace period (Prince William Times, September 2026). Loudoun ended them for new applications in March 2025 and weighs a 12-month pause (Loudoun Now, October 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

Wisconsin

Confirm utility territory and the local moratorium before using state incentives in a budget. Utility requirements are not uniform statewide.

Open with new conditions 53 data centers listed Industrial power 9.39¢/kWh

Political climate and approval direction

Governor
Tony Evers (Democratic)
Legislative majority
House: Republican. Senate: Republican. Divided government.
State policy signal
Qualified incentives remain open in the retained statute. A candidate pledge to repeal them is a campaign position, not enacted law.
Local approval pressure
County moratoriums and pending city proposals need individual checks.

Decision to watch: Track any actual repeal bill and the local ordinance separately. Preserve the award documents and identify changes affecting expansions or later purchases.

Government facts checked 2026-10-09: NGA governor directory and NCSL party composition (updated 2026-10-06). Policy signals summarize retained evidence with the source dates below; this supplement does not reverify every policy. Party control adds no incentive-access points.

Sources for this state's policy and local signals

Incentive requirements and project economics

Qualifying investment
Retained statute review: $50 million to $150 million within five years, depending on county population.
Employment or payroll
No universal job minimum established from the retained qualification summary. WEDC certification and other statutory conditions apply.
Timing and duration
Five-year investment test. No program sunset is recorded in the retained sales-tax statute review.
What the benefit covers
Qualified data-center equipment and electricity sales/use tax exemption. No sunset does not mean a project can skip certification.

Budget implication: Use the correct county investment tier and serving utility. The reviewed We Energies contract applies at 100 MW+, while other utility territories need separate terms.

Wisconsin State Legislature, July 2023 (primary; retained October 7 review); Wisconsin State Legislature, July 2023 (primary; retained October 7 review); Wisconsin State Legislature (primary; retained October 7 review). These are selected qualification conditions, not a complete eligibility determination.

Rules used in the scenario screen

  • Effective State incentive program

    The retained statute provides qualified data center sales and use tax relief, including electricity, subject to certification.

    Load: No numerical threshold used in this screen. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Wisconsin State Legislature, July 2023 (primary)

  • Effective We Energies

    Large customers face a 15-year term and full generation costs. The collateral condition depends on credit rating.

    Load: at least 100 MW. Effective from: not established in this record. Ends: no fixed end recorded.

    Last source review: . Retained from the initial source review. Review due: 2026-11-07.

    Public Service Commission of Wisconsin, April 2026 (primary)

Supporting research and local context

Background from the initial October 7, 2026 review, with later source checks marked on each entry. These background entries can contain multiple statuses; they do not independently add points. Local coverage is incomplete.

Wisconsin's sales tax exemption for qualified data centers covers electricity and has no sunset date (Wisconsin State Legislature, July 2023). Under a tariff approved in April 2026, We Energies customers of 100 MW or more face a 15-year minimum term and pay 100% of their generation costs (Public Service Commission of Wisconsin, April 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Projects must invest $50 million to $150 million within 5 years, by county population, and be certified by the Wisconsin Economic Development Corporation (Wisconsin State Legislature, July 2023; Wisconsin State Legislature).

Review recorded 2026-10-07. Retained from the initial source review.

Republican governor candidate Tom Tiffany pledges to repeal the tax breaks, a campaign promise, not a bill (Wisconsin Watch, August 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Operators rated below A- must post cash or credit-line collateral for We Energies service, a rule now unchallenged after Oracle moved to drop its lawsuit (Wisconsin Watch, August 2026). A Wisconsin Policy Forum report author said no approved rate framework for large data centers exists outside We Energies and Alliant territory (Wisconsin Watch, September 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Twenty-one counties adopted moratoriums by September 2026, with 8 more drafted or pending (UW-Madison Extension, September 2026). Janesville enacted a one-year moratorium (Kaukauna Community News, September 2026). Milwaukee's proposed one-year moratorium goes to the full Common Council on October 13 (Urban Milwaukee, October 2026).

Review recorded 2026-10-07. Retained from the initial source review.

Back to state finder and comparison · Compare power costs

How the scores work

This is a narrow incentive application access score, not a national ranking of data center friendliness. The question is whether a new project has an application path in the reviewed evidence. We do not calculate tax savings, approval probability or investment returns.

  • 2 of 2: the reviewed program offers an application path subject to its ordinary certification, investment, employment and other requirements.
  • 1 of 2: the reviewed path requires an additional invitation, agency consent order or newly imposed commitment process. This is an editorial category, not a measure of the cost of compliance.
  • 0 of 2: new applications are paused. This says nothing about an existing project's agreement.
  • Unscored: the source needs rechecking, the review is overdue for the assessed date, or no effective rule supports a score. Unknowns are never treated as open access.

All points come from that one criterion. No weights or bonus points apply to low industrial prices, facility counts, incomplete local coverage or assumed available power. Equal scores are ties, displayed alphabetically. Access sorting places scored states first, unscored states next and states with potential permit or grid holds in a separate final group. A hold is never averaged into an incentive score.

The rule screen uses facility utility demand in MW. A rule with an MVA threshold remains unresolved without a power factor; utility territory, aggregation and load-factor conditions also need confirmation. Proposed, future, expired and rescinded rules do not count as current restrictions. Leaving demand blank keeps potentially relevant rules visible. Existing leases are not assigned new-development scores; expansions need a separate review.

Every state still needs a jurisdiction-specific permission check, a utility-approved delivery date and commercial terms. Our source set does not establish those outcomes. Send your project requirements for a location-specific shortlist.

Evidence, dates and maintenance

October 9, 2026 expansion: added all 50 states' industrial power benchmarks, prior-year changes, an editable annual-spend screen and a CSV export with its assumptions. Added incentive qualification and budget implications for all 20 reviewed policy profiles, with selected primary-source checks dated individually. Added contract cash exposure, cooling and water comparisons, workload screening and a site evidence checklist. Power coverage is nationwide; policy coverage remains 20 states.

The utility comparison has 35 tariff, utility and wholesale-network entries. The earlier October 9 utility update verified PPL LP-6, NOVEC HV-2 and TVA's capacity-charge framework and narrowed ComEd and OEC gaps. Each entry keeps its own date and unresolved terms. This expansion does not change incentive access scores or establish power availability.

The original October 7, 2026 research is retained in the supporting context for each state. The structured rules identify their sources, scope, policy status, effective and end dates where known, last source review and next review date. A retained review date comes from that original research record; it does not mean the source was fetched again in this update. Records marked Source reopened in this update were checked directly for the stated rule.

Primary sources include statutes, agency program pages, orders and utility publications. Some retained rules rely on legal analysis or news reporting; the source type is shown beside the link. Replacement primary sources verify Arizona's incentive pause, Nevada's additional commitment process and Ohio's pause on new requests. All 20 reviewed states have an incentive access score in the base snapshot.

Targeted Texas policy check, October 9: reopened the ERCOT presentation and TCEQ letter, and read the adopted October 8 rule in the official Texas Register when the PUCT filing PDFs could not be fetched. The three rules now show the October 9 review. Added ERCOT's September 24 notice with the October 12 RFI response deadline. The primary-source search did not identify a later notice lifting either hold; that search is not confirmation of every project's current approval status.

The state policy comparison uses an October 7, 2026 base snapshot, with Texas screened at October 9. Only the stated Texas subjects received this later check; other conditions keep their individual source dates. The utility directory also shows its own review dates. Neither is a live policy or rate feed. Review dates are editorial follow-up targets, not promises of an automated refresh. We retain future and proposed actions separately and do not assume that an audit meeting ends a pause. Report a correction with the state, rule and source. Naming a company or project is not a claim that space or power is available.

Methodology v1.0, October 7, 2026: added structured evidence, incentive access scores, demand-based rule screening and source-review flags. A same-day source repair verified Arizona (0/2), Nevada (1/2) and Ohio (0/2); the scoring method and state coverage are unchanged. Download the evidence and source records (JSON).

Sources

  1. US Energy Information Administration, Electric Power Monthly, Table 5.6.B, January to July 2026, released September 24, 2026.
  2. Data Center Map, USA data centers by state, read October 7, 2026.
  3. National Conference of State Legislatures, Subsidizing servers, updated April 2026.
  4. State statutes, executive orders, utility commission orders, utility tariffs and news reports, linked in each state profile.

Back to state finder and comparison

Have a requirement measured in megawatts?

Send us the load, the markets and the date you need it energized. A senior advisor replies within one business day with the questions that matter and a plan for the search.

Our advisory is free to tenants. We are compensated by the provider you choose, and we disclose that on every shortlist. How we are paid