Wholesale data center advisory for tenants and landowners, from 1 MW to campus scale

Delivery model

Powered shell data centers: what the landlord delivers, what you build, and what it costs

A powered shell is a data center building with utility power brought to it and most of the inside left to the tenant. It trades a larger upfront investment for control, lower rent and a design that is yours. Here is how it works and when it beats a turnkey hall.

Key takeaways

  • In a powered shell the landlord delivers the building and utility power. The tenant designs, funds and installs the electrical and mechanical fit-out, and usually operates it.
  • Rent is far lower than turnkey because the tenant carries the fit-out capital. The model pays off only for teams that can design, procure, build and run critical infrastructure.
  • Schedule risk moves to you. Long-lead electrical equipment and commissioning sit on your critical path, not the landlord's.
  • Get the power commitment in writing: megawatts at the building, feed redundancy, energization date and the remedy if that date slips.

What is a powered shell data center?

A powered shell is a finished building envelope built to data center standards, with utility power delivered to the site. Structure, roof, slab and floor loading are designed for data center equipment. The power path from the utility is in place or contractually committed. What is missing is the critical infrastructure inside: the switchgear, UPS systems, generators, power distribution and cooling that turn a building into a data hall.

The tenant, or an operator working for the tenant, completes that fit-out. It is one point on a spectrum of delivery models, and the terms are used loosely, so always confirm the scope in writing.

ModelWhat exists when you signWho finishes it
Powered landLand with a documented path to utility powerA developer or self-building tenant builds everything
Powered shellThe building and utility powerThe tenant designs and installs electrical and mechanical systems
Warm shellThe building, power and some shared infrastructure, such as a central plant or generator yardThe tenant completes the halls. Scope varies widely by landlord
Turnkey wholesaleA finished, commissioned data hallNothing. The tenant installs IT equipment
Pop-up or modularA powered site, with no buildingFactory-built modules are set on a pad and connected

What the landlord delivers and what you deliver

The line between landlord work and tenant work is drawn in the lease, usually in a work letter. This is a typical split. Your lease may move items across it.

Scope itemPowered shellTurnkey wholesale
Building structure, roof, slab and floor loadingLandlordLandlord
Utility service to the site, substation or main switchgearLandlordLandlord
Medium-voltage distribution inside the buildingVariesLandlord
UPS, generators, low-voltage switchgear, busway and PDUsTenantLandlord
Cooling plant, air handling, liquid cooling distributionTenantLandlord
Fire detection and suppression in the hallsVariesLandlord
Site security and perimeterLandlordLandlord
Commissioning of critical systemsTenantLandlord
Operating and maintaining critical systemsTenantLandlord or its operator

Who leases powered shells

  • Hyperscalers and large cloud platforms with standard designs, their own supply chains and operations teams. For them a shell is the fastest way to deploy a design they have built many times.
  • AI companies and GPU clouds whose liquid-cooled designs differ from what landlords build speculatively, and who want to own the cooling architecture.
  • Operators who lease a shell and fit it out as turnkey halls for their own tenants.
  • Enterprises, rarely. It suits an enterprise with an experienced facilities team and a long-lived, predictable requirement. Most enterprises are better served by a turnkey hall.

Powered shell vs turnkey vs build-to-suit

Powered shellTurnkey wholesaleBuild-to-suit
Your capitalHigh: you fund the fit-outLow: equipment and cabling onlyLow to moderate, depending on structure
RentLowestHighestSet from the project cost and the landlord's return
Design controlFull inside the shellLimited to the operator's optionsFull, agreed before construction
Schedule riskYours after shell deliveryThe operator'sShared, set out in the development agreement
Operating burdenYoursThe operator'sAgreed in the lease
Typical termLong, to amortize your fit-outShorter terms are possibleLong

Rent and fit-out costs

Powered shell rent is usually quoted per square foot per year on a triple net basis, rather than per kW per month (datacenterHawk). It is far below turnkey rent because the expensive part of a data center is not the building. The CRE Finance Council puts mechanical, electrical and plumbing systems at 60 to 70% of development cost, and, citing KBRA, the building shell at 20 to 30% (CREFC, January 2026). In a powered shell, most of that 60 to 70% is yours.

Published cost figureScopeSource
$17.6 million per MW average; $8.9 to $23.3 million rangeAll-in greenfield build in the US and Canada, excluding chips and GPUs. The average is for the most modern facilities; the range is from the full guide. Up 21% per MW since late 2024Cushman & Wakefield, September 2026
$11.3 million per MWShell and core only, global average forecast for 2026. JLL adds that AI tenant fit-out can reach $25 million per MWJLL, January 2026
$4 to $8 million per MW, against $12 to $13 million for turnkeyDevelopment cost of a powered shell versus a turnkey facility, 2025datacenterHawk, February 2025
These figures measure different scopes and years, so they do not reconcile with each other. Use them to size the order of magnitude of your fit-out, not to budget it. Our construction cost guide explains each scope.

The practical comparison is total cost over the term: shell rent plus your fit-out capital and its financing, operating staff and maintenance, against a turnkey rent that bundles all of it. Cushman & Wakefield's 2026 guide puts power infrastructure at 21% of greenfield cost and cooling at 12%, the two largest systems a shell tenant installs.

Northern Virginia dominates this product. datacenterHawk counted about 100 of the roughly 130 powered shell deals it tracked worldwide in that market. One example: COPT Defense reports 33 data center shells totaling 6.3 million square feet in Northern Virginia, leased to a single Fortune 100 cloud customer on triple net leases signed before development started (COPT Defense 10-K).

What drives the schedule

Once the shell is delivered, your clock starts. The long poles are electrical equipment and commissioning. Cushman & Wakefield's 2026 guide, using Gilbane data, lists these lead times:

EquipmentLead time
Pad-mounted transformers68 to 113 weeks
Generators60 to 100 weeks
Medium-voltage switchgear38 to 63 weeks
Low-voltage switchgear36 to 60 weeks
UPS systems36 to 42 weeks
Source: Cushman & Wakefield, 2026 Data Center Development Cost Guide, citing Gilbane. The same guide, using Bureau of Labor Statistics producer prices, reports switchgear up 60% and generators up 33% since December 2021.

Delays are common. In Uptime Institute's 2026 supplier survey, 83% of suppliers reported disruption to build projects and 58% reported delays of at least three months (Uptime Institute, August 2026). If a transformer takes two years to arrive, order it before you sign the lease, or ask the landlord which equipment it has already reserved.

Lease terms that matter in a powered shell

Power delivery commitment
Megawatts available at the building, voltage, the number and independence of utility feeds, the energization date, and rent abatement or termination rights if that date slips.
Work letter
Exactly what the landlord builds, to what specification, by when. Floor loading, clear height, generator yard space, fuel storage, cooling tower or dry cooler space, and conduit paths all belong here.
Tenant improvement allowance
Any landlord contribution to fit-out, how it is paid, and how it affects rent.
Equipment ownership and restoration
Who owns the equipment you install, whether you must remove it at the end of the term, and whether the landlord can buy it. Restoration obligations can cost millions if left vague.
Permits and operating rights
Generator air permits, fuel storage, noise limits and 24-hour access. A generator you cannot run is not backup power.
Utility account
Whether you contract with the utility directly or buy power through the landlord, and how large-load tariff obligations, such as minimum demand charges, are allocated.
Expansion
Rights to adjacent shells or land, and the power that goes with them, so your second phase is not a new negotiation.
Term, renewals and exit
A term long enough to recover your investment, renewal options at known pricing, and assignment or sublease rights if plans change.

Rent, power billing, renewal and exit terms common to every wholesale lease are in our data center leasing guide.

Questions to ask before you sign

  • Is utility power energized at the building today? If not, what is the utility's committed date, and what does the utility's agreement actually commit to?
  • How many megawatts can the building take, at what voltage, from how many independent feeds?
  • What is the structural floor load rating, and is it enough for liquid-cooled racks and their coolant?
  • Where do generators, fuel, heat rejection and electrical rooms go, and are they permitted?
  • Which long-lead equipment have you ordered, and which is my responsibility?
  • What must be removed or restored at lease end?
  • What land and power is reserved for my expansion, and at what price?

Frequently asked questions

What is the difference between a powered shell and a warm shell?

A powered shell provides the building and utility power. A warm shell adds some infrastructure, such as a central cooling plant, a generator yard or medium-voltage distribution. Landlords use both terms differently, so compare the work letters rather than the labels.

Is a powered shell cheaper than turnkey space?

The rent is lower, but you fund and run the fit-out. Compare the full cost over the term: rent, your capital and its financing cost, operations staff, maintenance and the value of design control. For teams that already design and run data centers, a shell often wins. For most enterprises, turnkey does.

Who operates a powered shell data center?

Usually the tenant, or an operator the tenant hires. The landlord maintains the building and site. The lease should say who is responsible for each system.

Can an enterprise lease a powered shell?

Yes, if it has, or will hire, the engineering and operations capability. Many enterprises with shell-scale requirements choose a turnkey hall or a build-to-suit instead, which keeps operations with a specialist.

Sources

  1. Cushman & Wakefield, 2026 Data Center Development Cost Guide release, September 3, 2026, and the guide itself.
  2. CRE Finance Council, Data Center E-Primer, January 2026.
  3. JLL, 2026 Global Data Center Outlook, January 5, 2026.
  4. datacenterHawk, Understanding powered shell data centers, February 19, 2025.
  5. COPT Defense Properties, Form 10-K for 2025.
  6. Uptime Institute, Annual Survey 2026: supplier view, August 2026.

Have a requirement measured in megawatts?

Send us the load, the markets and the date you need it energized. A senior advisor replies within one business day with the questions that matter and a plan for the search.

Our advisory is free to tenants. We are compensated by the provider you choose, and we disclose that on every shortlist. How we are paid