Wholesale data center advisory for tenants and landowners, from 1 MW to campus scale

Land and power

Powered land: what it is, what it is worth, and how to prove it

Powered land is a site with a documented path to the electricity a data center needs. It is the scarcest input in the industry right now. Here is how buyers grade it, what it sells for, and how to get the highest price for yours.

Have a site? Four answers get you a reply.

Tell us where it is and where the power stands. A senior advisor replies within one business day. We do not ask for an exclusive.

Use the full form

Nothing you send is published, and we agree what can be shared before any introduction. Privacy

Key takeaways

  • Powered land is defined by paper, not proximity. A signed utility agreement with a date is the standard buyers pay most for.
  • Power sets the price, not acreage. Cushman & Wakefield puts powered land in primary US markets at $584,000 per MW in 2026.
  • Utility megawatts are not IT megawatts. Tenants pay for the IT load left after cooling and building systems.
  • Raw land to shovel-ready can take three to seven years. The documents you hold decide where you are on that path.
  • The highest price comes from proof, the right buyer and a deal that pays more as power milestones are hit. Headline price per acre is only part of it.

What is powered land?

Powered land is a development site with a documented, deliverable path to the electricity a data center needs, before any building goes up. The power can come from the local utility, from generation on the site, or both. What makes land "powered" is the paper: a utility study, a letter, a signed agreement, or power that is already on.

Land next to a substation is not powered land on its own. Neither is a parcel with a request sitting in the utility's queue. Buyers treat those as land with potential, and they price them that way.

The term caught on because power became the bottleneck. A hyperscale campus takes one to three years from planning to commissioning. The transmission lines, substations and transformers to serve it take five to fifteen years, according to the IEA as cited by CBRE Investment Management (June 2026). New large loads in the Americas now wait an average of 5.0 years for power (Cushman & Wakefield, May 2026). In Atlanta, JLL puts the wait for a 50 MW connection at about five years (Bisnow, January 2026).

Demand keeps growing. Hines Research estimates that about 40,000 more acres of powered land will be needed over the next five years (Hines). Operating data centers already occupy roughly 20,000 acres worldwide, per the same research (Bisnow, January 2026).

How buyers grade powered land: six stages

"Powered" covers everything from a first call with the utility to power already flowing. Buyers sort sites by the strongest document on file. Each stage up the list is worth more, because it removes risk and time.

StageTypical documentWhat it provesWhat it does not prove
1. Near powerA map of nearby substations and linesThe geography could workThat any capacity is spare
2. In the queueA large-load request or application, often with a depositThe utility has a formal request and a place in lineAny capacity, cost or date
3. StudiedA load or facilities studyWhat the utility would build, with a rough cost and scheduleA commitment. A study is evidence, not a promise
4. Intent to serveA will-serve or capacity letterThe utility intends to serve a stated load, often with conditionsBinding megawatts or dates. Read the conditions
5. ContractedA signed electric service or interconnection agreementContracted megawatts, a ramp schedule, costs and collateralThat the upgrades finish on time. Track the milestones
6. EnergizedPower on at the sitePower you can use nowHow much more is available for later phases
Utilities name these steps differently. The order is the same in most of the US.

Ask for the document, not the description. "200 MW available" means little without the agreement behind it and the date the power arrives. Cushman & Wakefield's 2026 cost guide warns that some land marketed as "power only" will not see power until 2033 or later (2026 Development Cost Guide).

Energized land versus powered land

Energized land is stage six: the substation is built and power is on at the site. It is the narrowest and most valuable kind of powered land. A buyer can start building against a date that has already happened.

Most land sold as "powered" is not energized. It sits at stage three, four or five, with a study, a letter or a signed agreement and a future date. Both can be good assets. They are different assets, and the listing should say which one it is.

Energized land still needs three numbers. How many megawatts are on today. How many more the utility has committed, and by when. And how much of the substation is spare for later phases.

What a utility agreement has to say

A signed agreement is what moves land from "studied" to "contracted". Buyers read it line by line. These are the terms they look for.

  • Contract capacity. The megawatts the utility commits to deliver, at what voltage and from which substation.
  • The ramp. How many megawatts arrive in each year, with dates.
  • The term. How many years the customer is bound after the ramp.
  • The minimum bill. The share of contract capacity paid for every month, used or not.
  • Collateral. The cash, letter of credit or guarantee due at signing.
  • Upgrade costs. What the utility builds, what the customer pays for, and when.
  • Exit and transfer. What it costs to leave, and whether the capacity can pass to a buyer or tenant.

Utilities now publish these terms for large loads. Three examples show how much is committed at signing.

Utility ruleApplies toTermMinimum billCollateral and exit
AEP Ohio, Schedule DCTData centers of 25 MW or moreA ramp of up to four years, plus eight yearsA demand floor of up to 85% of contract capacityCollateral equal to 50% of total minimum charges, unless credit tests are met. Exit fee of 36 months of minimum charges, available after year five
Dominion Virginia, GS-5 (from January 2027)Customers of 25 MW or more14 years, with an optional ramp85% for delivery and 60% for generationNot summarized here. See the order
Missouri large-load tariffsLarge-load customers of Evergy and Ameren Missouri12 years, with an optional ramp of up to five moreA monthly demand charge set at 80% of the agreed levelCollateral of two years of minimum monthly bills. An exit fee applies
Published terms as we read them on November 10, 2026. Each service agreement sets its own. Read yours with counsel.

Two points matter most to a seller. First, the party that signs carries the minimum bill and the collateral. That is why many landowners stop at a study or letter and let the buyer sign. Second, capacity does not always follow the land. AEP Ohio, for example, lets a customer ask to assign up to 25% of its contract capacity to another data center customer, and only if the utility finds it feasible. Ask your utility in writing how a sale or lease changes the agreement before you market the site.

Does onsite generation count as powered land?

It can. Some developers no longer wait for the grid. They pair the land with gas turbines or engines, solar and batteries on the site, or with generation next door. AES, for example, markets sites with a grid connection only, sites paired with nearby generation, generation behind a shared grid connection, and generation added to speed up the utility's service (AES).

The proof is different. Look for air permits, a firm fuel supply, confirmed equipment delivery slots and a plan for when units are down for maintenance. A turbine order is not power. Neither is a gas pipeline nearby.

Utility megawatts versus IT megawatts

Two numbers get mixed up in almost every listing. Utility capacity is the total power the site can draw. IT capacity is what is left for servers after cooling, power losses and building systems. Tenants lease and pay for IT capacity.

The gap is large. Hut 8's Beacon Point campus needs about 500 MW of utility power for 352 MW of IT load (Hut 8, May 2026). As a simple illustration, 100 MW of utility power at a PUE of 1.3 supports about 77 MW of IT load. Always say which number you mean.

The ramp matters as much as the total. For example, 300 MW that arrives as 50 MW in 2028 and the rest by 2031 is a different asset from 300 MW energized next year. Buyers price the schedule, not just the headline.

What powered land is worth

Cushman & Wakefield puts the average price of powered land in primary US markets at $584,000 per MW in 2026. That is up 51% in a year and 35% above the five-year average of $433,000 per MW (2026 Development Cost Guide).

Per acre, the change is even sharper. Land that sold for $10,000 to $30,000 an acre before the rush now trades at $200,000 to $1 million an acre, according to JLL's Jason Bell (Bisnow, January 2026). Recorded 2026 sales ran from about $150,000 an acre in Morris, Illinois to $9.4 million an acre in Ashburn, Virginia. The full list is in our table of 2026 data center land sales.

The buyer changes the price too. Among the ten largest land buyers Cushman & Wakefield tracked, hyperscalers paid about seven times more per acre than land developers (Americas Data Center Update H1 2026). End users pay for certainty and speed. Developers who buy earlier price in the risk they will carry.

Arithmetic, not an appraisal. At the primary-market average, 200 MW of committed power works out to about $117 million. The average covers primary markets only. Every site prices on its own power stage, date and costs.

What moves a site up or down:

  • Power stage and date. A signed agreement with a near date beats a bigger number backed only by a study.
  • Upgrade costs and who pays. Substations, line work and collateral can be a large share of the deal.
  • Distance to the substation and line voltage. Altus Group found sites within half a mile of a substation trade at about twice the price of comparable sites 2 to 5 miles away. Sites on 230 kV or 500 kV lines carry about a 2.4x premium over sites served at 138 kV or lower (Altus Group, updated August 2026).
  • Utility terms. Minimum bills, long contract terms and collateral shift risk to whoever signs for the load.
  • Zoning and community. Data center use allowed by right, or a credible path to approval. Our state-by-state comparison tracks moratoriums, tax breaks and large-load rules in 20 states.
  • Fiber and water. Diverse fiber routes nearby, and water for the cooling design or a design that needs little.
  • Acreage that fits the megawatts. Hines uses one acre for every three to four megawatts (Hines). CBRE reports site selectors asking for 250 MW or more on 125 acres or more (CBRE, 2026).

Who buys powered land

  • Hyperscalers. AWS, Microsoft and Meta all bought data center land in early 2026, per Cushman & Wakefield's record of sales.
  • Data center developers and operators. Stack, Digital Realty, NTT, Equinix and Cologix were among the 2026 buyers on the same list.
  • Powered-land developers. Firms that assemble land, secure power and entitlements, then sell or lease to end users. Tract bought 343 acres in Morris, Illinois in January 2026. WiredRE told Bisnow it aims to buy enough land for 10 GW.
  • Investors and brokerages. JLL has about 100 people working on powered land, and CBRE has part of its data center team on it, per Bisnow.
  • AI and GPU cloud companies. Usually through an operator, a powered shell or pop-up modules placed on a powered site.

Naming a buyer here is not a claim that it is looking at any particular site.

How to turn land into powered land

  1. Size the load. Pick a target in megawatts and a ramp. A 30 MW site and a 300 MW site are very different conversations with the utility.
  2. Talk to the utility early. File a large-load request. Dominion Energy says loads under 50 MW can often be served from existing distribution within one to two years. Larger loads likely need new transmission and a substation, with service staged over time (Dominion Energy).
  3. Get the study done. Load studies can take up to a year, according to JLL (Bisnow). Budget for deposits.
  4. Turn the study into a commitment. Negotiate the service agreement. Expect minimum bills, collateral and milestones.
  5. Entitle the site. Zoning, environmental review and community engagement. Local pushback canceled 25 data center projects in 2025, four times the year before, according to Heatmap as reported by Bisnow.
  6. Confirm fiber and water. Carrier routes and distances (check carriers near your site), and a water source or a low-water cooling plan.
  7. Build the data room. See the checklist below.

From acquisition to shovel-ready, JLL puts the whole path at three to seven years (Bisnow). You do not have to finish it to sell. Many owners sell or lease at the study or letter stage, at a lower price, to a developer who carries the rest.

Thinking about operating on your own land? Model the power bill, cooling water and connection costs with our landowner operating cost estimator. Unknown costs stay labeled as unknown.

The powered land data room

Buyers and operators ask for the same documents every time. Having them ready shortens diligence and signals a serious seller.

  • Utility correspondence, study results, and any will-serve letter or service agreement
  • The megawatt ramp schedule, energization dates and collateral terms
  • A one-line diagram and substation plan, if one exists
  • Title, an ALTA survey and any easements
  • A zoning letter or the current entitlement status
  • A Phase I environmental report, wetland and flood maps, and geotechnical data
  • A fiber map with carriers and distances
  • Water and sewer capacity letters
  • Tax incentives the site qualifies for

How to get the highest price for powered land

The best price is not always the biggest number on the first offer. It is the deal most likely to close, on time, with value left for you. These steps move a site toward the top of its range.

  1. Move up a stage before you sell, if you can wait. Each stage in the table above removes risk for the buyer, and the price follows. Altus Group, reviewing verified data center land sales, found committed power capacity to be the strongest driver of price (Altus Group). If you cannot wait, sell at the stage you are at and let the price step up later (step 5).
  2. Build the data room before you go to market. Title, survey, zoning, utility papers, environmental and flood data, all in one place. See the checklist above. A clean package shortens diligence and tells buyers the seller is serious.
  3. Market megawatts and a date, not acres. State the utility megawatts, the IT megawatts they support and the ramp schedule. Buyers price power and timing. Vague claims get discounted or ignored.
  4. Reach the buyers who pay the most. Among the ten largest land buyers Cushman & Wakefield tracked, hyperscalers paid about seven times more per acre than land developers (see above). Hyperscalers pay for certainty and speed. Getting a site in front of several qualified buyers at once beats waiting for one unsolicited offer.
  5. Tie the price to power milestones. Lowndes, a law firm that advises landowners, recommends writing the contract so the price rises when the site reaches a utility milestone or key approval. It also recommends deposits that become non-refundable in stages as the buyer's diligence progresses (Lowndes, March 2026).
  6. Charge for time. Options, exclusivity and diligence extensions tie up your land. Price them for the uncertainty. Use paid extensions linked to objective progress, regular status reports and a firm outside date (Lowndes).
  7. Keep some upside on large tracts. Sell a first phase now and reserve later phases at higher prices. Or agree an extra payment if the buyer secures a utility commitment, an entitlement or a resale within a set period (Lowndes).
  8. Keep the buyer's work if the deal fails. Ask that studies and diligence the buyer paid for become part of your site package if it walks away (Lowndes). The next buyer starts further along, and that is worth money.
  9. Protect the land you keep. Get paid for access across retained land, limit any cooperation to specific steps, and refuse permanent easements you have not approved (Lowndes). A sale that hurts the neighboring acres you still own can cost more than it earns.

Headline price is one number of several. Weigh every offer on price, certainty, timing and the odds it closes. A higher price with a long free option and soft deposits can be worth less than a lower, firm one. Take real estate and legal advice before you sign. See sale, option, ground lease or partnership for how each structure trades cash now against upside later.

Powered land for sale: what the listing should state

A buyer searching for powered land for sale is sorting dozens of sites. The ones that get a call answer the same questions up front. Put these in the first page of the package.

State thisSay it like thisNot like this
Power stage"Signed electric service agreement" or "facilities study complete""Power available"
Megawatts"120 MW utility capacity, about 90 MW of IT load""Up to 500 MW possible"
Dates"40 MW in 2028, 120 MW by 2030""Near-term power"
Who serves itThe utility, the substation and the line voltage"Close to transmission"
Costs still owedUpgrade costs, collateral and who pays themNothing said
Zoning"Data center use allowed by right" or the approval still needed"Favorable county"
What is offeredSale, ground lease, option or partnership, and for how many acres"Open to offers"
The megawatt and date figures are examples of the form, not a real site.

We do not list land, and we do not publish sites. We take a site with real power paper to the operators, developers and tenants whose requirements it fits. Send yours in four answers.

Red flags in a powered land listing

  • Megawatts with no date.
  • "Power available" with no document behind it.
  • Utility megawatts quoted as IT megawatts.
  • A study presented as a commitment.
  • A queue position with lapsed deposits or missed milestones.
  • No zoning path, or a town already fighting a data center.
  • Onsite generation with no air permit or firm fuel supply.

Powered land vs. powered shell vs. turnkey

ModelWhat you getWho builds the data centerTime to IT load
Powered landLand with a documented path to powerThe buyer or tenant builds everythingLongest. The building and fit-out are still ahead
Powered shellA building with utility power deliveredThe landlord builds the shell. The tenant fits it outShorter. Fit-out only
TurnkeyA finished, commissioned data hallThe operatorShortest

Unlock your land's long-term value

We help landowners partner with data center operators through ground leases and development partnerships. Across 25 years in the data center business, we have built deep industry roots and close relationships with operator executives. We put those relationships to work to help you negotiate strong lease and partnership terms.

We have tenants lined up and ready to sign leases for sites that meet their location, power and delivery requirements. Matching your property with that demand gives operators a concrete reason to pursue your site. Running bitcoin miners on energized power? See how mining sites convert to AI data centers.

  • We read your power documents the way a tenant's engineers will.
  • We introduce the site to operators, developers and tenants where there is a fit.
  • We do not ask for an exclusive. We do not appraise land.

Before any engagement, we agree in writing who we work for and how we are paid. See how we differ from a real estate broker.

Find the right operator partner for your land

Share your site's location, acreage, power status and partnership goals. A senior advisor replies within one business day to explore a ground lease or development partnership that fits your property and our active tenant demand.

Developers and brokers with several sites: pick the count below and list the sites in the notes. We reply with where to send the package. We do not ask for an exclusive.

Or call 844-506-2299

Incomplete information is fine. Nothing you send is published, and we agree what can be shared before any introduction. Privacy

Frequently asked questions

What does powered land mean for data centers?

Powered land is a site with a documented, deliverable path to the electricity a data center needs, before a building goes up. The documents decide it: a utility study, a will-serve letter, a signed service agreement, or power that is already on. Land that is only near a substation does not qualify.

What is energized land?

Energized land is a site where the substation is built and power is already on. It is the last of the six stages buyers use to grade powered land, and the most valuable. Most land marketed as powered has a study, a letter or a signed agreement with a future date, and is not yet energized.

What should a utility agreement for powered land include?

The contract capacity in megawatts, the ramp by year, the term, the minimum bill, the collateral, the upgrade costs and who pays them, and the exit and transfer terms. Published large-load rules show the scale. AEP Ohio's data center tariff runs eight years after a ramp of up to four. Dominion's GS-5 class in Virginia carries a 14-year term from January 2027. See what a utility agreement has to say.

Is powered land the same as a powered shell?

No. Powered land has no building. A powered shell is a building with utility power delivered, and the tenant installs the data center equipment inside.

How much is powered land worth?

Cushman & Wakefield puts powered land in primary US markets at $584,000 per MW in 2026. Recorded 2026 sales ran from about $150,000 to $9.4 million an acre. Each site prices on its own power stage, energization date, upgrade costs and location. Nothing here is an appraisal.

How many acres does a megawatt need?

Hines uses one acre for every three to four megawatts. CBRE reports site selectors looking for 250 MW or more on 125 acres or more, closer to two megawatts an acre. Check whether a figure counts utility power or IT load.

How long does it take to get power to land?

It depends on size and the grid. Dominion Energy says loads under 50 MW can often be served within one to two years, while larger loads need new transmission and a substation. Across the Americas, new large loads wait an average of 5.0 years for power. JLL puts the full path from acquisition to shovel-ready at three to seven years.

How do I get the highest price for my powered land?

Move the site up a power stage if you can wait, and have the data room ready before you market it. Present megawatts and an energization date, not just acres. Put it in front of several qualified buyers, including hyperscalers, which paid the most per acre in Cushman & Wakefield's tracking. Then structure the deal so the price rises as power milestones are hit, and charge for options and extensions. Take real estate and legal advice before signing.

Can I sell land that only has a power study?

Yes, usually to a developer who will carry the rest of the process, at a lower price than land with a signed agreement. Present the study as a study. Buyers will check.

Do you buy, list or appraise land?

No. We connect powered sites with operators, developers and tenants who fit them. A conversation with us is not an appraisal or legal advice.

Sources

  1. Hines Research, Power Play: The Emerging Powered Land Opportunity and the full report.
  2. Bisnow, If You Entitle It, They Will Come: How Powered Land Plugs CRE Into The Data Center Boom, January 29, 2026. Source for the JLL, Hines acreage, WiredRE and Heatmap figures cited above.
  3. CBRE Investment Management, Powered Land, June 29, 2026, citing the IEA.
  4. Cushman & Wakefield, 2026 Data Center Development Cost Guide; Americas Data Center Update H1 2026; 2026 Global Data Center Market Comparison, May 2026.
  5. Dominion Energy, data center service requests.
  6. CBRE, US Real Estate Market Outlook Midyear Review 2026: Data Centers.
  7. Hut 8, Beacon Point lease announcement, May 6, 2026.
  8. AES, Powered Land Solutions.
  9. Lowndes, Beyond Price Per Acre: A Landowner's Guide to Maximizing Value in a Data Center Site Sale, March 16, 2026.
  10. Altus Group, Where Value Is Created in Data Center Land, updated August 19, 2026.
  11. AEP Ohio, Data Center Tariff (Schedule DCT), read November 10, 2026.
  12. Virginia State Corporation Commission, final order in PUR-2025-00058, November 25, 2025. Source for the GS-5 terms.
  13. Missouri Public Service Commission, Utility Tariffs for Large Load Customers, read November 10, 2026.

The $117 million figure, the 77 MW illustration and per-acre prices are our arithmetic from the published figures. Nothing on this page is an appraisal or legal advice.