Wholesale data center advisory for tenants and landowners, from 1 MW to campus scale

AI and hyperscale

Hyperscale colocation and AI data center capacity

Campus-scale capacity is leased years ahead, often before the building exists, and AI has changed what a data hall has to deliver. This guide covers how hyperscale and AI leases work, what 100 kW-plus racks demand from a facility, and how to secure capacity when most of it is already spoken for.

Key takeaways

  • Hyperscale colocation is wholesale leasing at campus scale: whole buildings or multi-megawatt phases, usually committed before construction finishes.
  • AI changed the product. Rack-scale GPU systems draw well over 100 kW per rack and need liquid cooling, which many existing halls cannot deliver.
  • Most new capacity in primary markets is preleased. Tenants who start late take what is left, or wait for the next phase.
  • Power timing decides the search. Energized, liquid-ready capacity is the scarcest product in the market and is priced that way.

What hyperscale colocation is

Hyperscale colocation is the top end of the wholesale market. Instead of a suite or a hall, the tenant leases a dedicated building or a phase of a campus, often tens of megawatts at a time, from a developer or operator that builds and usually runs the facility. The largest cloud providers built this market. They self-build some capacity and lease the rest, because leasing adds capacity faster and keeps their capital for servers and chips.

AI companies, GPU clouds and large enterprises now lease the same way. The commercial structure is familiar from wholesale leasing: rent per kW of critical IT capacity, power billed on top, long terms. What differs is the scale, how early the commitment is made, and the facility the tenant needs.

Who is leasing at campus scale

Cloud providers still take most of the capacity, but they are no longer alone. JLL estimates 2026 demand at 59% hyperscalers, 11% neoclouds (GPU cloud providers) and 7% pure-play AI companies, with the typical enterprise requirement at 500 kW to 3 MW (JLL, August 2026). CBRE expects demand to shift toward 25 to 75 MW sites for inference and enterprise AI, and reports growing interest in 2 to 20 MW urban infill sites (CBRE, H1 2026).

Leases disclosed in 2026 show what campus-scale AI commitments look like:

Landlord and tenantCapacityTerms disclosedSource
Galaxy and CoreWeave, West Texas526 MW critical IT committed. Phase I of 133 MW delivered on schedule, rent from Q2 202615 years plus two 5-year extensionsGalaxy, July 2026
Hut 8 and an investment-grade tenant, Nueces County, Texas352 MW IT in May, a second 352 MW in July15-year triple net, $9.8 billion base term for the first phase, energization from Q1 2027Hut 8, May 2026
TeraWulf and Anthropic, Hawesville, KentuckyAbout 401 MW critical IT20 years, about $19 billion, in service from the second half of 2027TeraWulf, July 2026
Applied Digital and an investment-grade hyperscaler, Delta Forge 1300 MW critical IT15 years, about $7.5 billion, operations from mid-2027Applied Digital, April 2026
CleanSpark and Meta, Sandersville, Georgia175 MW critical IT20-year triple net, about $6.6 billion contracted, 3% annual escalator, rent assumed from late 2027CleanSpark, September 2026
Host Digital, northeastern Oklahoma43 MW critical IT15-year take-or-pay, about $1.25 billion, delivery targeted for Q1 2027August 2026
As announced or filed by the companies. Contract values can include more than base rent.

The pattern: 15 to 20 year terms with extension options, delivery one to two years after signing, and credit support where the tenant's balance sheet is thin. The largest tenants' commitments dwarf any single campus. Oracle reported $260 billion of leases signed but not yet started, substantially all data centers, running 15 to 19 years (Oracle 10-K), and CoreWeave reported $38.5 billion (CoreWeave 10-K). Those tenants are competing for the same pipeline you are.

What AI racks demand from a facility

A decade ago an enterprise rack drew 5 to 10 kW. Rack-scale GPU systems draw more than ten times that, and each generation goes higher:

SystemPower per rackBasis
NVIDIA GB200 NVL72Up to 132 kWVertiv and NVIDIA reference design (Vertiv, October 2024)
NVIDIA GB300 NVL72Up to 142 kWSchneider Electric and NVIDIA reference design (Schneider Electric, September 2025)
NVIDIA Vera Rubin NVL72About 180 to 220 kWAnalyst estimate; NVIDIA has not published an official figure (SemiAnalysis, February 2026). NVIDIA says it ships in the second half of 2026
Future racksUp to 1 MWNVIDIA's roadmap for 800-volt DC power distribution targets 1 MW IT racks from 2027 (NVIDIA, May 2025)
Reference designs and estimates, not measured draw. Your sustained load depends on configuration and utilization.

At these densities air cooling is out. CBRE notes that 100 kW GPU servers can only be cooled by a closed-loop liquid cooling system, and that converting an air-cooled hall to liquid can delay fit-out by more than six months (CBRE, H1 2026). NVIDIA designs its Vera Rubin generation racks for 45°C warm-water inlet, which lets many sites reject heat with dry coolers instead of chillers (NVIDIA, March 2026). Most of the market is not there yet: the average rack in AFCOM's 2026 operator survey drew 27 kW, and 36% of operators had liquid cooling deployed (AFCOM, 2026).

For a tenant, that turns into a short list of facility questions that decide whether a hall can take the deployment at all:

  • Power per rack and per row. The sustained limit for your contiguous footprint, not the building's best-case figure.
  • Liquid cooling. Whether direct-to-chip cooling is installed or only designed for, who owns the coolant distribution units, the facility water supply temperature and flow per rack, and how much heat can still go to air.
  • Structure. Floor loading for dense, liquid-filled racks, and clear height for overhead busway, cable trays and piping.
  • Electrical design. Busway capacity, distribution voltage, and whether redundancy can be reduced for training halls to save cost.
  • Network. Space and pathways for the dense fiber that GPU clusters need between racks and to the outside world.
  • The next generation. Whether the hall can take a denser system in two years without a rebuild.

Preleasing: capacity is committed before it is built

Large blocks of finished capacity barely exist. Almost everything a campus-scale tenant can lease is still under construction, and most of that is already committed:

  • Primary markets: 80.4% of the 7,481 MW under construction was preleased in the first half of 2026, and less than 1,500 MW of future capacity remained unclaimed, about six months of demand (CBRE, August 2026).
  • North America overall: JLL counts 66 GW under construction, 95% pre-committed, and says most tenants signing today are contracting for 2028 deliveries (JLL, August 2026).
  • What is left in finished buildings: across the Americas, the largest single availability in an operating facility was 15 MW, and only 28 availabilities exceeded 5 MW (Cushman & Wakefield, H1 2026). Worldwide, only seven operating colocation facilities had 20 MW or more available, and none of them was in the Americas (Cushman & Wakefield, May 2026).

So a search for 10 MW or more is really a search of the construction pipeline. The question is not only which building, but which phase, which delivery date, and how firmly that date is committed.

For a tenant, three things follow:

  1. Start earlier than feels necessary. Work backward from the date you need power energized, not from the date you want to sign.
  2. Commit in stages. A first phase with rights of first offer on later phases secures growth without paying for it before you need it.
  3. Price certainty against delivery risk. A future phase may cost less than energized space today, but only if the delivery date is enforceable.

Power is the binding constraint

Every hyperscale search ends up as a power search. Cushman & Wakefield puts the average time to secure power for new large loads at 5.0 years in the Americas (May 2026), and CBRE says power procurement takes more than ten years in some markets (CBRE Midyear Review, August 2026).

Utilities and regulators are also changing the terms of a large connection. Those obligations reach tenants through the lease:

WhereRuleWhat it means for a tenant
Virginia (Dominion)New GS-5 rate class for customers of 25 MW and up from January 1, 2027, with minimum charges of 85% of contracted transmission and distribution demand and 60% of generation demand (Virginia SCC, November 2025)Minimum bills that a landlord will pass through as power floors
Ohio (AEP Ohio)Data center tariff for loads of 25 MW and up: minimum billing demand, a ramp of up to four years, a term of the ramp plus eight years, and collateral (AEP Ohio)Long commitments and credit requirements behind any new campus
Georgia (Georgia Power)Special terms for new customers over 100 MW, including contracts up to 15 years and minimum bills (Georgia PSC, January 2025)Same pattern: the utility wants the load paid for even if it never shows up
Texas (ERCOT)Senate Bill 6 requires new large loads of 75 MW and up connected after 2025 to accept curtailment during firm load shed (Bracewell summary). In August 2026 the governor paused approvals of new data center interconnections pending a state audit (Texas Tribune)Ask how a Texas campus handles curtailment, and whether its power timeline depends on queue approvals still pending

The response from developers is to bring power with them. CBRE reports developers weighing behind-the-meter generation where utility delays run past contracted delivery dates (CBRE, H1 2026). Cleanview counts 59 announced behind-the-meter data center projects totaling about 90 GW, mostly gas, of which about 2 GW was operating in mid-2026 (Cleanview, May 2026). Announced is not operating. If a campus depends on onsite or bridge power, ask who owns and fuels it, what it costs per kWh, what emissions permits it needs, and exactly how and when it hands over to the grid.

Lease terms specific to AI capacity

Density and cooling commitments
Contracted kW per rack and per row, liquid cooling capacity, supply temperature and flow, with remedies if the facility cannot deliver them.
Cooling equipment ownership
Who buys, owns, maintains and replaces the coolant distribution units and secondary loop, and who is liable for a leak.
Delivery tied to hardware
A delivery date and ramp that match your GPU shipments, with rent credits for delay. Idle hardware waiting for a hall is expensive.
Redundancy and pricing
Lower redundancy for training halls should carry lower rent. Get the redundancy level and the price for each hall in writing.
Technology refresh
The right to upgrade to denser systems, and the operator's obligation to support higher power and cooling when you do.
Credit support
Letters of credit, deposits or prepayment scaled to your credit profile. Newer AI companies often face higher security requirements, which are negotiable.
Sublease and assignment
The right to sublease capacity if demand shifts, so a long commitment does not become a stranded one.

Frequently asked questions

What is hyperscale colocation?

Leasing data center capacity at campus scale, such as whole buildings or phases of tens of megawatts, from a developer or operator rather than building it yourself. Cloud providers created the market, and AI companies now use it too.

How big is a hyperscale data center?

There is no single threshold. CBRE describes a shift toward AI campuses of 500 MW and more, and says site selectors now prefer sites of 250 MW or more on 125 acres or more. Campuses are built in phases, so a tenant can still lease one building or one phase of tens of megawatts.

What rack density does AI need?

NVIDIA's GB200 and GB300 NVL72 reference designs run up to about 132 to 142 kW per rack, and the Vera Rubin generation is estimated at 180 to 220 kW. Inference on smaller servers can run far lower. Specify the systems you will deploy, not an average, and plan for the next generation.

Can a smaller AI company lease hyperscale capacity?

Yes. Operators lease by phase, and many campuses serve several tenants. Expect credit review and security requirements scaled to your balance sheet. An advisor can help position the requirement and the credit support.

How long does it take to secure AI data center capacity?

If energized, liquid-ready capacity is available, leasing can take weeks to a few months. If you need new construction, the timeline follows the utility and the build schedule, often measured in years.

Sources

  1. CBRE, North America Data Center Trends H1 2026, August 27, 2026, and Midyear Review 2026.
  2. JLL, Data center demand exceeds expectations in H1 2026, August 11, 2026.
  3. Cushman & Wakefield, Americas Data Center Update H1 2026 and 2026 Global Data Center Market Comparison.
  4. NVIDIA technical blog, Vera Rubin POD, March 16, 2026, and 800 V HVDC architecture, May 20, 2025.
  5. Vertiv, GB200 NVL72 reference architecture; Schneider Electric, GB300 NVL72 reference designs; SemiAnalysis, Vera Rubin analysis.
  6. AFCOM, State of the Data Center 2026 executive summary.
  7. Virginia SCC, order in Dominion's biennial review; AEP Ohio, data center tariff; Georgia PSC, large-load rule; Bracewell, Texas Senate Bill 6; Texas Tribune, data center projects frozen pending audit, August 3, 2026.
  8. Cleanview, Behind-the-meter data centers, May 2026.
  9. Company announcements and filings linked in the lease table above, and Oracle's Form 10-K and CoreWeave's Form 10-K.

Have a requirement measured in megawatts?

Send us the load, the markets and the date you need it energized. A senior advisor replies within one business day with the questions that matter and a plan for the search.

Our advisory is free to tenants. We are compensated by the provider you choose, and we disclose that on every shortlist. How we are paid