Data center project at 1975 And 1985 NW Sigman Road; 1980, Rockdale County, GA

Every public record we hold for this address, newest first, with a link to the original document. Last change on record: August 8, 2024.

Project facts

Address1975 and 1985 NW Sigman Road; 1980, 1736, 1670, 1726 and 1716 NW Lester Road; and 1634, 1632 and 1630 NW Farmer Road PARCELS: 0210010059, 021001003A, 0210010060, 021001003H, 0210010063, 021001003G, 021001003F, 021001003C, 0210010003, 021001003B, Rockdale County, GA
JurisdictionRockdale County, GA
Operator named in the recordsNot named. The filer is usually a contractor, engineer or single-purpose company.
Furthest step on recordZoning or planning review, August 8, 2024
Capacity stated in a filingNone stated
Floor area statedNone stated
Site area stated52.78 acres
Records on file1, from August 8, 2024 to August 8, 2024

Records on file

FiledType and statusWhat the record saysSource
Zoning
Heard 2024-08-08
To amend the Future Land Use Map from High-Density Residential to Technology Park for the development of a data center. To Rezone 52.78 acres from R-1 (Single-Family Residential) to O-I (Office- Institutional) for the development of a data center. To authorize a Special Use Permit for an Electric...
Applicant: SDP Acquisitions, LLC OWNER: Lisa Holtzclaw Pippin, Charles and Donna Martin, and Trenton Lee Pippin
Record

Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.

Cite this page

Data Center Scouts, "Data center project at 1975 And 1985 NW Sigman Road; 1980, Rockdale County, GA," https://datacenterscouts.com/data-center-projects/georgia/1975-and-1985-nw-sigman-road-1980-rockdale-county/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.

All Georgia projects · Latest notable filings · Project tracker

Have a requirement measured in megawatts?

Send us the load, the markets and the date you need it energized. A senior advisor replies within one business day with the questions that matter and a plan for the search.

Our advisory is free to tenants. We are compensated by the provider you choose, and we disclose that on every shortlist. How we are paid