Project facts
| Address | 222 W ADAMS ST, Chicago, IL |
|---|---|
| Jurisdiction | City of Chicago, IL (Cook County) |
| Operator named in the records | Not named. The filer is usually a contractor, engineer or single-purpose company. |
| Furthest step on record | Building permit issued, October 22, 2010 |
| Capacity stated in a filing | None stated |
| Floor area stated | None stated |
| Site area stated | None stated |
| Records on file | 1, from September 17, 2010 to September 17, 2010 |
Records on file
| Filed | Type and status | What the record says | Source |
|---|---|---|---|
| Building permit Building permit issued | INTERIOR ALTERATIONS TO EXISTING OFFICE BUILDING ON THE 35TH FLOOR DATA CENTER TO UPGRADE THE UPS AND MECHANICAL SYSTEMS, INCLUDING NEW DRY COOLERS ON THE 36TH FLOOR ROOF AS PER PLANS. Applicant: WILLIAM BLAIR & COMPANY LLC | Record |
Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.
Cite this page
Data Center Scouts, "Data center project at 222 W Adams St, Chicago, IL," https://datacenterscouts.com/data-center-projects/illinois/222-w-adams-st-chicago/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.