Project facts
| Address | 326 W 64TH ST, Chicago, IL |
|---|---|
| Jurisdiction | City of Chicago, IL (Cook County) |
| Operator named in the records | Not named. The filer is usually a contractor, engineer or single-purpose company. |
| Furthest step on record | Building permit issued, December 22, 2014 |
| Capacity stated in a filing | None stated |
| Floor area stated | None stated |
| Site area stated | None stated |
| Records on file | 1, from June 10, 2014 to June 10, 2014 |
Records on file
| Filed | Type and status | What the record says | Source |
|---|---|---|---|
| Building permit Building permit issued | INTERIOR ALTERATIONS AT EXISTING HOSPITAL TO INCLUDE DATA CENTER RELOCATION AND NEW EXTERIOR DIESEL FUEL GENERATOR AS PER PLAN Applicant: GREGG, TIMOTHY M | Record |
Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.
Cite this page
Data Center Scouts, "Data center project at 326 W 64th St, Chicago, IL," https://datacenterscouts.com/data-center-projects/illinois/326-w-64th-st-chicago/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.
All Illinois projects · Latest notable filings · Project tracker