CoreSite data center at 427 S La Salle St, Chicago, IL

Every public record we hold for this address, newest first, with a link to the original document. Last change on record: June 16, 2025.

Project facts

Address427 S LA SALLE ST, Chicago, IL
JurisdictionCity of Chicago, IL (Cook County)
Operator named in the recordsCoreSite
Furthest step on recordBuilding permit issued, August 19, 2025
Capacity stated in a filingNone stated
Floor area statedNone stated
Site area statedNone stated
Records on file3, from June 2, 2009 to June 16, 2025

Records on file

FiledType and statusWhat the record saysSource
Building permit
Building permit issued
DDS / 2019 CBRC: INTERIOR ALTERATIONS TO 2ND FLOOR TENANT SPACE (SUITE201) IN AN EXISTING DATA CENTER AS PER PLANS.(OCCUPANCY GROUP: B / TYPE 1A CONSTRUCTION) CONSULTANT REVIEWER: V3 COMPANIES OF IL
Applicant: CORESITE REAL ESTATE CH1, LLC
Record
Building permit
Building permit issued
REPLACE FOUR LIEBERT UNITS WITH TWO, 30 TON, AND TWO, 20 TON, AIR COOLED, REMOTE, R407C, LIEBERT UNITS, LOCATED ON THE ROOF, AND SERVING THE DATA CENTER FLOOR.
Applicant: CORESITE
Record
Building permit
Building permit issued
STRUCTURAL FLOOR UPGRADE TO 2ND FLOOR DATA CENTER AS PER PLANS. NO MEP.
Applicant: CHRISTOPHER J DOWNES
Record

Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.

Cite this page

Data Center Scouts, "CoreSite data center at 427 S La Salle St, Chicago, IL," https://datacenterscouts.com/data-center-projects/illinois/427-s-la-salle-st-chicago/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.

All Illinois projects · Latest notable filings · Project tracker

Have a requirement measured in megawatts?

Send us the load, the markets and the date you need it energized. A senior advisor replies within one business day with the questions that matter and a plan for the search.

Our advisory is free to tenants. We are compensated by the provider you choose, and we disclose that on every shortlist. How we are paid