Wholesale data center advisory for tenants and landowners, from 1 MW to campus scale

Illinois data center projects

Data center project at 840 S Canal St, Chicago, IL

Every public record we hold for this address, newest first, with a link to the original document. Last change on record: April 5, 2024.

Project facts

Address840 S CANAL ST, Chicago, IL
JurisdictionCity of Chicago, IL (Cook County)
Operator named in the recordsNot named. The filer is usually a contractor, engineer or single-purpose company.
Furthest step on recordBuilding permit issued, April 11, 2024
Capacity stated in a filingNone stated
Floor area stated14,000 sq ft
Site area statedNone stated
Records on file10, from April 23, 2015 to April 5, 2024

Records on file

FiledType and statusWhat the record saysSource
Building permit
Building permit issued
SCOPE: NONSTRUCTURAL INTERIOR ALTERATION.LOCATIONS: 0 RESIDENTIAL UNIT(S), 1 NON-RESIDENTIAL UNIT(S), 7TH FLOOR. EXPANSION OF EXISTING 7TH FLOOR OFFICE SPACE IN AN EXISTING DATA CENTER. WORK TO INCLUDE MECHANICAL (VAVS) AND ELECTRICAL. NO STRUCTURAL WORK. INSTALL NEW FINISHES AND
Applicant: SERVERFARM
Record
Building permit
Building permit issued
**FIRE ALARM PERMIT**INSTALLATION OF A PRE-ACTION SYSTEM SERVING BSMT, 1ST, 2ND, 3RD, 4TH, AND 7TH FLOORS OF A HIGH-RISE CLASS-E BUSINESS BUILDING. DATA CENTER SHALL BE PROTECTED WITH VESDA SAMPLING DETECTION.
Applicant: PHOENIX FIRE SYSTEMS INC
Record
Building permit
Building permit issued
CBRC SPR 2019: INTERIOR ALTERATIONS TO AN EXISTING DATA CENTER AS PER PLANS ON BASEMENT, 1ST, 2ND, 3RD, 4TH, 7TH FLOOR AND ROOF EQUIPMENT REPLACEMENT. STRUCTURAL PEER REVIEW INCLUDED. (OCCUPANCY E / CONSTRUCTION TYPE 1A) **CERTIFIED PLANS CORRECTIONS: CONDITIONAL PERMIT SUBJECT TO FIELD INSPECTIONS **
Applicant: SERVER FARM
Record
Building permit
Building permit issued
REPURPOSE 2000 CIRCUITS IN THE EXISTING DATA CENTER ON THE 4TH FLOOR. JOB# 2750003
Applicant: CONTINENTAL ELECTRICAL CONSTRU
Record
Building permit
Building permit issued
SPR 2019: INTERIOR DEMO TO THE BASEMENT, 1ST, 2ND, 3RD, 7TH FLOORS AND REMOVAL OF EQUIPMENT AND DUNNAGE TO THE ROOF OF DATA CENTER AS PER PLANS. (OCCUPANCY E / CONSTRUCTION TYPE 1A)
Applicant: SERVER FARM
Record
Building permit
Building permit issued
SC 2019 CBRC: INTERIOR ALTERATIONS TO EXISTING STORAGE AREA IN THE 4TH FLOOR OF AN EXISTING DATA CENTER AS PER PLANS. (OCCUPANCY E / CONSTRUCTION TYPE 3B)
Applicant: BOLDIZSAR, ALBERTO M
Record
Building permit
Building permit issued
SELF CERT: INTERIOR ALTERATIONS TO 4TH FLOOR DATA CENTER TO INCLUDE AHU REPLACEMENT IN THE MECHANICAL PENTHOUSE, LOADING DOCK ALTERATIONS AS PER PLAN. STRUCTURAL PEER REVIEW
Applicant: LAY, SCOTT P
Record
Building permit
Building permit issued
SELF CERT: INTERIOR ALTERATIONS TO 4TH FLOOR DATA CENTER AND SUPPORTING INFRASTRUCTURE LOCATED ON 4TH FLOOR AND BASEMENT. STRUCTURAL PEER REVIEW INCLUDED.
Applicant: NATALE, JOHN E
Record
Building permit
Building permit issued
5TH FLOOR INTERIOR BUILDOUT OF 14,000 SF OF DATA HALL SPACE, SUPPORTING INFRASTRUCTURE ON 5TH FLOOR AND BASEMENT, INSTALL ONE NEW GENERATOR TO BE INSTALLED ON EXISTING STRUCTURAL STEEL WHICH WAS PERMITTED UNDER #100639202. CONDITIONAL PERMIT SUBJECT TO FIELD INSPECTION.
Applicant: LAY, SCOTT P
Record
Building permit
Building permit issued
INTERIOR RENOVATION 5TH FLOOR TO SERVE AS DATA CENTER, CONSTRUCTING COMPUTER ROOM AREAS, ELECTRICAL AND MECHANICAL EQUIPMENT ROOMS INCLUDING SERVICE SPACES,ALL FULLY SPRINKLED.RENOVATION ALSO INCLUDES CONSTRUCTION OF ACCESSORY ELECTRICAL SPACES IN THE BASEMENT PER PLANS.
Applicant: SF CH1 LL
Record

Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.

Cite this page

Data Center Scouts, "Data center project at 840 S Canal St, Chicago, IL," https://datacenterscouts.com/data-center-projects/illinois/840-s-canal-st-chicago/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.

All Illinois projects · Latest notable filings · Project tracker

Have a requirement measured in megawatts?

Send us the load, the markets and the date you need it energized. A senior advisor replies within one business day with the questions that matter and a plan for the search.

Our advisory is free to tenants. We are compensated by the provider you choose, and we disclose that on every shortlist. How we are paid