Project facts
| Address | 201 MAIN AVE, Clifton City, NJ, 07014 |
|---|---|
| Jurisdiction | New Jersey (statewide NJDEP air permits) |
| Operator named in the records | Not named. The filer is usually a contractor, engineer or single-purpose company. |
| Furthest step on record | Air permit on file, September 4, 2024 |
| Capacity stated in a filing | None stated |
| Floor area stated | None stated |
| Site area stated | None stated |
| Records on file | 2, from date not stated to date not stated |
Records on file
| Filed | Type and status | What the record says | Source |
|---|---|---|---|
| Issued | Air permit Approved | 201 MAIN AVE DATA CENTER: (GP-005A) Emergency Generators Burning Distillate Fuels | Record |
| Not stated | Air permit Air permit on file | CLIFTON DATA CENTER | Record |
Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.
Cite this page
Data Center Scouts, "Data center project at 201 Main Ave, Clifton City, NJ," https://datacenterscouts.com/data-center-projects/new-jersey/201-main-ave-clifton-city/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.
All New Jersey projects · Latest notable filings · Project tracker