Project facts
| Address | 32 AVENUE OF THE AMERICAS, Manhattan, NY 10013 |
|---|---|
| Jurisdiction | New York City, NY (DOB NOW, all five boroughs) |
| Operator named in the records | Not named. The filer is usually a contractor, engineer or single-purpose company. |
| Furthest step on record | Building permit issued, January 28, 2026 |
| Capacity stated in a filing | None stated |
| Floor area stated | 3,000 sq ft |
| Site area stated | None stated |
| Records on file | 1, from January 28, 2026 to January 28, 2026 |
Records on file
| Filed | Type and status | What the record says | Source |
|---|---|---|---|
| Building permit Signed-off | Air conditioning unit replacement on the 7th floor Data Center. No change in use egress and occupancy. Applicant: RUDIN MANAGEMENT CO., INC. | Record |
Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.
Cite this page
Data Center Scouts, "Data center project at 32 Avenue Of The Americas, Manhattan, NY," https://datacenterscouts.com/data-center-projects/new-york/32-avenue-of-the-americas-manhattan/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.