Project facts

Address3501 ED BLUESTEIN BLVD NB BLDG TXEO1, AUSTIN, TX 78725
JurisdictionCity of Austin, TX (Travis County)
Operator named in the recordsNot named. The filer is usually a contractor, engineer or single-purpose company.
Furthest step on recordWork finaled, July 10, 2006
Capacity stated in a filingNone stated
Floor area stated204,564 sq ft
Site area statedNone stated
Records on file6, from March 5, 2003 to August 21, 2018

Records on file

FiledType and statusWhat the record saysSource
Building permit
Expired
add a redundant ups in support of manufacturing data centers
Applicant: NXP USA, Inc.
Record
Planning case
Approved
add a redundant ups in support of manufacturing data centers
Applicant: NXP
Record
Building permit
Final
Interior Remodel To Create OfficeSupport For Data Center
Applicant: DPR Construction
Record
Building permit
Final
Remodel Existing Loading Dock & Storage To Create Ups Rooms Office & Support Space For Data Center
Applicant: DPR Construction
Record
Building permit
Final
Change Of Use And Interior Remodel From Manufacturing To Data Center
Applicant: DPR Construction, Inc.
Record
Building permit
Final
Relocate Data Center
Applicant: NXP USA, Inc.
Record

Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.

Cite this page

Data Center Scouts, "Data center project at 3501 Ed Bluestein Blvd Nb Bldg Txeo1, Austin, TX," https://datacenterscouts.com/data-center-projects/texas/3501-ed-bluestein-blvd-nb-bldg-txeo1-austin/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.

All Texas projects · Latest notable filings · Project tracker

Have a requirement measured in megawatts?

Send us the load, the markets and the date you need it energized. A senior advisor replies within one business day with the questions that matter and a plan for the search.

Our advisory is free to tenants. We are compensated by the provider you choose, and we disclose that on every shortlist. How we are paid