Project facts
| Address | 8131 PINEBROOK DR, San Antonio, TX 78230 |
|---|---|
| Jurisdiction | Bexar County, TX (City of San Antonio) |
| Operator named in the records | Not named. The filer is usually a contractor, engineer or single-purpose company. |
| Furthest step on record | Building permit issued, April 3, 2025 |
| Capacity stated in a filing | None stated |
| Floor area stated | None stated |
| Site area stated | None stated |
| Records on file | 1, from April 3, 2025 to April 3, 2025 |
Records on file
| Filed | Type and status | What the record says | Source |
|---|---|---|---|
| Building permit Issued | UHS Data Center Applicant: MCFARLIN ELECTRIC COMPANY, LLC | Record |
Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.
Cite this page
Data Center Scouts, "Data center project at 8131 Pinebrook Dr, San Antonio, TX," https://datacenterscouts.com/data-center-projects/texas/8131-pinebrook-dr-san-antonio/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.
All Texas projects · Latest notable filings · Project tracker