Project facts
| Address | 22235 Loudoun County Parkway, Ashburn, VA |
|---|---|
| Jurisdiction | Loudoun County, VA |
| Operator named in the records | Not named. The filer is usually a contractor, engineer or single-purpose company. |
| Furthest step on record | Building permit issued, May 20, 2025 |
| Capacity stated in a filing | None stated |
| Floor area stated | 2,242,904 sq ft |
| Site area stated | None stated |
| Records on file | 10, from October 29, 2024 to January 17, 2025 |
Records on file
| Filed | Type and status | What the record says | Source |
|---|---|---|---|
| Building permit Issued | Phase 2 Tenant Interiors buildout of the LC11 Data Center building. Phase 2 includes mechanical and electrical rooms and equipment on Level 3 to support turnover of 1 of 2 Data Halls on Level 3. | Record | |
| Building permit Issued | Phase 4 Tenant Interiors buildout of the LC11 Data Center building. Phase 4 includes mechanical and electrical rooms and equipment on Level 2 to support turnover of 1 of 4 Data Halls, as well as tenant spaces on Level 1. | Record | |
| Building permit Issued | Phase 3 Tenant Interiors buildout of the LC11 Data Center building. Phase 3 includes mechanical and electrical rooms and equipment on Levels 2 to support turnover of 1 of 4 Data Halls. | Record | |
| Building permit Issued | Phase 1 Tenant Interiors buildout of the LC11 Data Center building. Phase 1 includes mechanical and electrical rooms and equipment on Levels 1 - 3 to support turnover of 1 of 4 Data Halls. | Record | |
| Building permit Issued | Phase 3 Tenant Interiors buildout of the LC11 Data Center building. Phase 3 includes mechanical and electrical rooms and equipment on Levels 2 to support turnover of 1 of 4 Data Halls. | Record | |
| Building permit Issued | Phase 1 Tenant Interiors buildout of the LC11 Data Center building. Phase 1 includes mechanical and electrical rooms and equipment on Levels 1 - 3 to support turnover of 1 of 4 Data Halls. | Record | |
| Building permit Issued | Phase 4 Tenant Interiors buildout of the LC11 Data Center building. Phase 4 includes mechanical and electrical rooms and equipment on Level 2 to support turnover of 1 of 4 Data Halls, as well as tenant spaces on Level 1. | Record | |
| Building permit Issued | Phase 2 Tenant Interiors buildout of the LC11 Data Center building. Phase 2 includes mechanical and electrical rooms and equipment on Level 3 to support turnover of 1 of 2 Data Halls on Level 3. | Record | |
| Building permit Issued | A THREE-STORY DATA CENTER BUILDING SHELL. | Record | |
| Building permit Issued | A THREE-STORY DATA CENTER BUILDING SHELL. | Record |
Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.
Cite this page
Data Center Scouts, "Data center project at 22235 Loudoun County Parkway, Ashburn, VA," https://datacenterscouts.com/data-center-projects/virginia/22235-loudoun-county-parkway-ashburn/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.