| Address | 22275 LOCKRIDGE RD, STERLING, VA |
|---|---|
| Jurisdiction | Loudoun County, VA |
| Operator named in the records | Not named. The filer is usually a contractor, engineer or single-purpose company. |
| Furthest step on record | Building permit issued, May 24, 2024 |
| Capacity stated in a filing | None stated |
| Floor area stated | None stated |
| Site area stated | None stated |
| Records on file | 1, from December 10, 2023 to December 10, 2023 |
Records on file
| Filed | Type and status | What the record says | Source |
|---|---|---|---|
| Building permit Issued | THE PROPOSED PROJECT IS A 3-STORY, SINGLE TENANT, PHASED INTERIOR BUILD-OUT OF AN EXISTING SHELL BUILDING FOR USE AS A DATA CENTER - WHICH WILL HOUSE COMPUTERS, RELATED INFRASTRUCTURE, ADMINISTRATIVE/OFFICE AREAS, AND DATA HALL WITH ASSOCIATED AIR HANDLING & ELECTRICAL EQUIPMENT IN PHASE 1. SUBSEQUENT DATA HALL AREA(S) WITH ASSOCIATED AIR HANDLING & ELECTRICAL EQUIPMENT ROOMS SHALL BE CONTRUCTED IN SUCCESSIVE PHASES (REFER TO ARCHITECT'S PHASING PLAN). PARTIAL/TEMPORARY OCCUPANCY WITH ASSOCIATED INSPECTIONS SHALL BE MADE AT THE COMPLETION OF EACH PHASE, FOLLOWED BY FINAL INSPECTIONS AT THE END OF THE LAST PHASE TO ACCOMMODATE TENANT OCCUPANCY OF THE ENTIRE BUILDING INTERIOR. THE DRAWINGS, IN CONCERT WITH THE SPECIFICATIONS, COMPRISE THE CONTRACT DOCUMENTS OUTLINING THE DESIGN INTENT AND PROJECT SCOPE, AND MAY BE SUPPLEMENTED BY FURTHER INFORMATION ISSUED BY ARCHITECT. THE BUILDING'S AUTOMATIC DRY-PIPE SPRINKLER SYSTEM SHALL BE OPERATIONAL BEFORE OCCUPANCY OCCURS. | Record |
Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.
Cite this page
Data Center Scouts, "Data center project at 22275 Lockridge Rd, Sterling, VA," https://datacenterscouts.com/data-center-projects/virginia/22275-lockridge-rd-sterling/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.
All Virginia projects · Latest notable filings · Project tracker