Project facts
| Address | 42376 PATRIOT PARK DR, LEESBURG, VA |
|---|---|
| Jurisdiction | Loudoun County, VA |
| Operator named in the records | Not named. The filer is usually a contractor, engineer or single-purpose company. |
| Furthest step on record | Building permit issued, May 22, 2026 |
| Capacity stated in a filing | None stated |
| Floor area stated | 413,099 sq ft |
| Site area stated | None stated |
| Records on file | 38, from July 22, 2024 to March 19, 2026 |
Records on file
| Filed | Type and status | What the record says | Source |
|---|---|---|---|
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for the office area and Phase 1 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 9 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 18 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 17 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 13 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 14 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 15 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 5 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 8 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 6 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 11 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 10 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 12 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 7 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 4 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 16 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 2 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 3 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 14 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 18 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 17 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 15 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 13 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 16 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for the office area and Phase 1 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 10 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 8 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 2 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 5 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 7 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 12 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 4 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 3 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 6 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 9 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Data Center Architectural and Structural Tenant Fit-Out for Phase 11 of the data center. There are a total of 18 phases in this project. | Record | |
| Building permit Issued | Third building on the campus. CURRENT: CORE/SHELL 3-STORY FLEX WAREHOUSE AND COMMERICAL OFFICE. FUTURE PURPOSE OF SPACE: 3-STORY SINGLE TENANT COMPUTER DATA CENTER. | Record | |
| Building permit Issued | Third building on the campus. CURRENT: CORE/SHELL 3-STORY FLEX WAREHOUSE AND COMMERICAL OFFICE. FUTURE PURPOSE OF SPACE: 3-STORY SINGLE TENANT COMPUTER DATA CENTER. | Record |
Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.
Cite this page
Data Center Scouts, "Data center project at 42376 Patriot Park Dr, Leesburg, VA," https://datacenterscouts.com/data-center-projects/virginia/42376-patriot-park-dr-leesburg/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.