Project facts
| Address | 43855 LIGHT SPEED PLZ, STERLING, VA |
|---|---|
| Jurisdiction | Loudoun County, VA |
| Operator named in the records | Not named. The filer is usually a contractor, engineer or single-purpose company. |
| Furthest step on record | Building permit issued, April 30, 2026 |
| Capacity stated in a filing | None stated |
| Floor area stated | 412,905 sq ft |
| Site area stated | None stated |
| Records on file | 34, from April 11, 2025 to May 29, 2025 |
Records on file
| Filed | Type and status | What the record says | Source |
|---|---|---|---|
| Building permit Issued | New data center build. Phase 11 | Record | |
| Building permit Issued | New data center build. Phase 16 | Record | |
| Building permit Issued | New data center build. Phase 18 | Record | |
| Building permit Issued | New data center build. Phase 13 | Record | |
| Building permit Issued | New data center build. Phase 17 | Record | |
| Building permit Issued | New data center build. Phase 15 | Record | |
| Building permit Issued | New data center build. Phase 7 | Record | |
| Building permit Issued | New data center build. Phase 4 | Record | |
| Building permit Issued | New data center build. Phase 5 | Record | |
| Building permit Issued | New data center build. Phase 9 | Record | |
| Building permit Issued | New data center build. Phase 8 | Record | |
| Building permit Issued | New data center build. Phase 10 | Record | |
| Building permit Issued | New data center build. Phase 6 | Record | |
| Building permit Issued | New data center build. Phase 12 | Record | |
| Building permit Issued | New data center build. Phase 3 | Record | |
| Building permit Issued | New data center build. Phase 2 | Record | |
| Building permit Issued | New data center build. Phase 5 | Record | |
| Building permit Issued | New data center build. Phase 7 | Record | |
| Building permit Issued | New data center build. Phase 17 | Record | |
| Building permit Issued | New data center build. Phase 18 | Record | |
| Building permit Issued | New data center build. Phase 11 | Record | |
| Building permit Issued | New data center build. Phase 16 | Record | |
| Building permit Issued | New data center build. Phase 13 | Record | |
| Building permit Issued | New data center build. Phase 12 | Record | |
| Building permit Issued | New data center build. Phase 6 | Record | |
| Building permit Issued | New data center build. Phase 9 | Record | |
| Building permit Issued | New data center build. Phase 10 | Record | |
| Building permit Issued | New data center build. Phase 15 | Record | |
| Building permit Issued | New data center build. Phase 8 | Record | |
| Building permit Issued | New data center build. Phase 4 | Record | |
| Building permit Issued | New data center build. Phase 2 | Record | |
| Building permit Issued | New data center build. Phase 3 | Record | |
| Building permit Issued | New data center build.304000000 | Record | |
| Building permit Issued | New data center build.304000000 | Record |
Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.
Cite this page
Data Center Scouts, "Data center project at 43855 Light Speed Plz, Sterling, VA," https://datacenterscouts.com/data-center-projects/virginia/43855-light-speed-plz-sterling/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.