Project facts

Address44595 LOW LATENCY LN, STERLING, VA
JurisdictionLoudoun County, VA
Operator named in the recordsNot named. The filer is usually a contractor, engineer or single-purpose company.
Furthest step on recordBuilding permit issued, September 17, 2025
Capacity stated in a filingNone stated
Floor area statedNone stated
Site area statedNone stated
Records on file2, from December 5, 2024 to December 15, 2024

Records on file

FiledType and statusWhat the record saysSource
Building permit
Issued
Construction of "SDC Fitout Scope No.1" within the new construction of a 4-story data center Core-&-Shell building. The new construction data center "Core-&-Shell" is currently under review by Loudoun County under permit case number BLDC-2024-055894. Marked-up colored drawings are provided under this permit and similarly under the BLDC-2024-055894 permit to clearly delineate the "Core-&-Shell" scopes versus the "SDC Fitout Scope No.1" scopes.Record
Building permit
Issued
New construction of a 4-level data center facility.Record

Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.

Cite this page

Data Center Scouts, "Data center project at 44595 Low Latency Ln, Sterling, VA," https://datacenterscouts.com/data-center-projects/virginia/44595-low-latency-ln-sterling/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.

All Virginia projects · Latest notable filings · Project tracker

Have a requirement measured in megawatts?

Send us the load, the markets and the date you need it energized. A senior advisor replies within one business day with the questions that matter and a plan for the search.

Our advisory is free to tenants. We are compensated by the provider you choose, and we disclose that on every shortlist. How we are paid