| Address | 12396 GRANT ST, Thornton, CO |
|---|---|
| Jurisdiction | Adams County, CO (City of Thornton) |
| Operator named in the records | |
| Furthest step on record | Building permit applied for, September 23, 2025 |
| Capacity stated in a filing | None stated |
| Floor area stated | None stated |
| Site area stated | None stated |
| Records on file | 1, from September 23, 2025 to September 23, 2025 |
Records on file
| Filed | Type and status | What the record says | Source |
|---|---|---|---|
| Building permit Expired | Addition of electrical and mechanical systems to expand datacenter space at existing facility. | Record |
Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.
Cite this page
Data Center Scouts, "Google data center at 12396 Grant St, Thornton, CO," https://datacenterscouts.com/data-center-projects/colorado/12396-grant-st-thornton/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.
All Colorado projects · Latest notable filings · Project tracker