Colorado data center projects

Flexential data center at 8636 South Peoria Street, Parker Area, CO

Every public record we hold for this address, newest first, with a link to the original document. Last change on record: April 8, 2021.

Project facts

Address8636 SOUTH PEORIA STREET, PARKER AREA, CO 80112
JurisdictionColorado APCD (statewide)
Operator named in the recordsFlexential
Furthest step on recordWork finaled, November 27, 2024
Capacity stated in a filingNone stated
Floor area statedNone stated
Site area statedNone stated
Records on file5, from March 4, 2014 to April 8, 2021

Records on file

FiledType and statusWhat the record saysSource
Issued Air permit
Final approval issued
FLEXENTIAL CORP - COMPARK DATA CENTER: final approval issued (PRMT FA ISS 1), permit 21DG0377Record
Issued Air permit
Construction permit issued
FLEXENTIAL CORP - COMPARK DATA CENTER: construction permit issued (PRMT ISS 1), permit 21DG0377
Applicant: FLEXENTIAL CORPORATION
Record
Air permit
Application received
FLEXENTIAL CORP - COMPARK DATA CENTER: application received (PRMT APPL), permit 21DG0377
Applicant: FLEXENTIAL CORPORATION
Record
Air permit
Application received
FLEXENTIAL CORP - COMPARK DATA CENTER: application received (PRMT APPL), permit 16DG0774
Applicant: FLEXENTIAL CORPORATION
Record
Air permit
Application received
FLEXENTIAL CORP - COMPARK DATA CENTER: application received (PRMT APPL), permit 14DG0493
Applicant: FLEXENTIAL CORPORATION
Record

Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.

Cite this page

Data Center Scouts, "Flexential data center at 8636 South Peoria Street, Parker Area, CO," https://datacenterscouts.com/data-center-projects/colorado/8636-south-peoria-street-parker-area/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.

All Colorado projects · Latest notable filings · Project tracker

Have a requirement measured in megawatts?

Send us the load, the markets and the date you need it energized. A senior advisor replies within one business day with the questions that matter and a plan for the search.

Our advisory is free to tenants. We are compensated by the provider you choose, and we disclose that on every shortlist. How we are paid