Project facts

Address197 Foster ST, Brighton, MA 02135
JurisdictionCity of Boston, MA (Suffolk County)
Operator named in the recordsNot named. The filer is usually a contractor, engineer or single-purpose company.
Furthest step on recordBuilding permit issued, August 31, 2022
Capacity stated in a filing1 MW (Capacity stated in the filing)
Floor area statedNone stated
Site area statedNone stated
Records on file3, from date not stated to date not stated

Records on file

FiledType and statusWhat the record saysSource
Issued Building permit
Closed
Replacement of a 500kW UPS with a new 500kW UPS at Boston College's data center
Applicant: Philip Ostrow
Record
Issued Building permit
Open
Provide new redundant electrical service to the existing Data Center including construction of a new electrical room, structural upgrades, sprinkler, HVAC and sitework.
Applicant: Christopher M Mccarrier
Record
Issued Building permit
Open
Upgrade the existing air sampling system in St. Clement's Hall datacenter to VESDA-E.
Applicant: Tom Tracy
Record

Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.

Cite this page

Data Center Scouts, "Data center project at 197 Foster St, Brighton, MA," https://datacenterscouts.com/data-center-projects/massachusetts/197-foster-st-brighton/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.

All Massachusetts projects · Latest notable filings · Project tracker

Have a requirement measured in megawatts?

Send us the load, the markets and the date you need it energized. A senior advisor replies within one business day with the questions that matter and a plan for the search.

Our advisory is free to tenants. We are compensated by the provider you choose, and we disclose that on every shortlist. How we are paid