Project facts
| Address | 243 Charles ST, Boston, MA 02114 |
|---|---|
| Jurisdiction | City of Boston, MA (Suffolk County) |
| Operator named in the records | Not named. The filer is usually a contractor, engineer or single-purpose company. |
| Furthest step on record | Building permit issued, March 7, 2024 |
| Capacity stated in a filing | None stated |
| Floor area stated | None stated |
| Site area stated | None stated |
| Records on file | 1, from date not stated to date not stated |
Records on file
| Filed | Type and status | What the record says | Source |
|---|---|---|---|
| Issued | Building permit Open | Installation of Ansul Clean Agent System (Sapphire Suppression System (FK-5-1-12, Novec 1230) will be installed to protect the 310 sq.ft. Data Center Room. Fire alarm system Conduit and associated wiring to complete installation. Installation of 3 F/A modules above Fire Suppression System Applicant: Paul Maiuri | Record |
Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.
Cite this page
Data Center Scouts, "Data center project at 243 Charles St, Boston, MA," https://datacenterscouts.com/data-center-projects/massachusetts/243-charles-st-boston/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.
All Massachusetts projects · Latest notable filings · Project tracker