Project facts
| Address | 1025 D Street NW, Quincy, WA |
|---|---|
| Jurisdiction | Washington (statewide, SEPA Register) |
| Operator named in the records | CyrusOne |
| Furthest step on record | Zoning or planning review, July 27, 2017 |
| Capacity stated in a filing | 5.7 MW (Generator nameplate, summed from stated ratings) |
| Floor area stated | 920,000 sq ft |
| Site area stated | None stated |
| Records on file | 1, from date not stated to date not stated |
Records on file
| Filed | Type and status | What the record says | Source |
|---|---|---|---|
| Issued | Zoning MDNS | SEPA determination: MDNS Applicant: CyrusOne | Record |
Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.
Cite this page
Data Center Scouts, "CyrusOne data center at 1025 D Street NW, Quincy, WA," https://datacenterscouts.com/data-center-projects/washington/1025-d-street-nw-quincy/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.