Washington data center projects
23 projects and 57 public records from 2 permit or planning sources in Washington, each linked to its source. Latest record filed date not stated.
Updated By the Data Center Scouts advisory team
Projects by latest record
| Latest record | Project | Operator named | Furthest step | Records |
|---|---|---|---|---|
| Not stated | 4405 Grant Rd East Wenatchee, WA | Sabey | Zoning or planning review 3.7 MW stated | 1 |
| Not stated | 3625 1st Ae S Seattle, WA | Not named | Zoning or planning review | 1 |
| Not stated | 301 Virginia St Seattle, WA | Not named | Zoning or planning review | 1 |
| Not stated | 1525 Broadway Street Po Box 128 Longview, WA | Not named | Zoning or planning review | 1 |
| Not stated | 1515 Port Industrial Way Quincy, WA | Microsoft | Zoning or planning review | 2 |
| Not stated | 9221 Tyndall Rd Moses Lake, WA | Not named | Zoning or planning review | 1 |
| Not stated | 1023 39th Ave SE Puyallup, WA | Not named | Zoning or planning review 5 MW stated | 1 |
| Not stated | 875 Urban Industrial Way Building E & F East Wenatchee, WA | Microsoft | Zoning or planning review | 5 |
| Not stated | 875 C Urban Industrial Way Ste #201 East Wenatchee Wenatchee, WA | Microsoft | Zoning or planning review | 1 |
| Not stated | 532 B St NE Quincy, WA | Not named | Zoning or planning review | 3 |
| Not stated | 422767 SR 20 Usk, WA | Not named | Zoning or planning review | 1 |
| Not stated | 422767 Highway 20 Usk, WA | Not named | Zoning or planning review | 1 |
| Not stated | 501 Port Industrial Way Quincy, WA | Microsoft | Zoning or planning review | 2 |
| Not stated | 2200 M Street NE Quincy, WA | Sabey | Operating 12.5 MW stated | 4 |
| Not stated | 1415 Maple Ave SW Renton, WA | Not named | Zoning or planning review | 2 |
| Not stated | 3555 Grant Road East Wenatchee, WA | Not named | Zoning or planning review 12.5 MW stated | 1 |
| Not stated | 1500 Port Industrial Parkway Quincy, WA | Microsoft | Zoning or planning review | 1 |
| Not stated | 935 Road L.4 SE Moses Lake, WA | Not named | Zoning or planning review | 2 |
| Not stated | 1980 SR 903 Washington | Not named | Zoning or planning review | 1 |
| Not stated | 1025 D Street NW Quincy, WA | CyrusOne | Zoning or planning review 5.7 MW stated | 1 |
| Not stated | 2101 Rd M NE Quincy, WA | Vantage Data Centers | Zoning or planning review | 1 |
| Not stated | 1500 M Street NE Quincy, WA | Not named | Zoning or planning review | 1 |
| Not stated | 1010 Yahoo Way Quincy, WA | Not named | Operating | 2 |
Moratoriums, bans and rule changes
- Pierce County: Emergency Ordinance 2026-577: Prohibiting New and Expanded Data Centers. Adopted (emergency) August 25, 2026. Source
Other recent records without a street address
Agenda items, statewide air registers and records that name a parcel or facility rather than an address. The latest 20 are listed.
| Filed | Where | Type and status | What the record says | Source |
|---|---|---|---|---|
| Issued | Washington | Zoning DNS | Code Amendment 2026-3 OCC 17.20 Definitions & 17.220 District Use Chart Data Centers Applicant: Okanogan County | Record |
| Issued | Washington | Zoning DNS | Data Center General Order Applicant: Washington State Department of Ecology | Record |
| Issued | Washington | Zoning DNS | Malaga Cooling Water Disposal Facility Applicant: Chelan Douglas Regional Port Authority | Record |
| Issued | Washington | Zoning DNS | City of Longview WA Industrial Districts Zoning Uses Amendments Applicant: City of Longview Community Development Department | Record |
| Issued | Washington | Zoning MDNS | EAT12-13-14 Data Center Campus Microsoft Applicant: Microsoft Corperation | Record |
| Issued | Washington | Zoning DNS, REVISED | SEPA determination: DNS, REVISED Applicant: Tony Welsh for Actapio, Inc. | Record |
| Issued | Washington | Zoning DNS, REVISED | SEPA determination: DNS, REVISED Applicant: Vantage Data Centers | Record |
| Issued | Washington | Zoning DNS | SEPA determination: DNS Applicant: Wenatchee City of | Record |
| Issued | Washington | Zoning DNS | SEPA determination: DNS Applicant: Vantage Data Centers | Record |
| Issued | Washington | Zoning DNS | SEPA determination: DNS Applicant: Sabey Data Center Properties | Record |
| Issued | Washington | Zoning DNS | SEPA determination: DNS Applicant: City of Snoqualmie, Nancy Tucker | Record |
| Issued | Washington | Zoning ODNS-M | SEPA determination: ODNS-M Applicant: Douglas Coover, Harrison Medical Center; | Record |
| Issued | Washington | Zoning MDNS | SEPA determination: MDNS Applicant: City of Quincy | Record |
| Issued | Washington | Zoning ODNS | SEPA determination: ODNS Applicant: Intergate Columbia II, LLC, Sabey Intergate | Record |
| Issued | Washington | Zoning ADDEND, DNS | SEPA determination: ADDEND, DNS Applicant: Sabey Intergate, Quincy LLC | Record |
| Issued | Washington | Zoning ODNS/NOA | SEPA determination: ODNS/NOA Applicant: Jay Reeves | Record |
| Issued | Washington | Zoning ODNS/NOA-M | SEPA determination: ODNS/NOA-M Applicant: Tierpoint LLC | Record |
| Issued | Washington | Zoning ADDEND, EIS | SEPA determination: ADDEND, EIS Applicant: Benaroya Companies. Mark Johnson by PKJB Architectural Group | Record |
| Issued | Washington | Zoning CONSULT | SEPA determination: CONSULT Applicant: Washington State Dept of Information Services | Record |
| Issued | Washington | Zoning ADOPT, DNS | SEPA determination: ADOPT, DNS Applicant: Port of Chelan County/Yahoo! Inc, R Terry Johnson | Record |
Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.
Cite this page
Data Center Scouts, "Washington data center projects," https://datacenterscouts.com/data-center-projects/washington/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.
Have a requirement measured in megawatts?
Send us the load, the markets and the date you need it energized. A senior advisor replies within one business day with the questions that matter and a plan for the search.
Our advisory is free to tenants. We are compensated by the provider you choose, and we disclose that on every shortlist. How we are paid