Project facts
| Address | 4405 Grant Rd, East Wenatchee, WA 98802 |
|---|---|
| Jurisdiction | Washington (statewide, SEPA Register) |
| Operator named in the records | Sabey |
| Furthest step on record | Zoning or planning review, July 15, 2026 |
| Capacity stated in a filing | 3.7 MW (Generator nameplate, summed from stated ratings) |
| Floor area stated | None stated |
| Site area stated | None stated |
| Records on file | 1, from date not stated to date not stated |
Records on file
| Filed | Type and status | What the record says | Source |
|---|---|---|---|
| Issued | Zoning DNS, REVISED | Integrate Columbia II Applicant: Sabey Data Center Properties | Record |
Every row comes from a public permit, air-quality or planning record, linked to its source. A permit shows that work was proposed or approved. It does not show that space is available or that a building is finished. Capacity figures carry the basis the filing gives.
Cite this page
Data Center Scouts, "Sabey data center at 4405 Grant Rd, East Wenatchee, WA," https://datacenterscouts.com/data-center-projects/washington/4405-grant-rd-east-wenatchee/, updated October 9, 2026. Source records are linked on the page. Journalists and researchers are welcome to use this data with a link back.