Key takeaways
- None of the eight utilities has spare power. Each one's own plan shows a shortfall or a build program to close one.
- Every one now charges large loads before the power flows: minimum bills, upfront payments, collateral or a capacity charge.
- The new gas plants that serve these loads arrive from 2028 to 2032. A pause elsewhere does not bring them sooner.
- The destination states have new governors too. Alabama's says data centers pay every cost. Kansas had not been called.
What the pause states' new governors said
Gina Hinojosa won in Texas on a moratorium on new data centers and approvals until the legislature acts. Keisha Lance Bottoms won in Georgia on a statewide pause on new construction. Amy Acton won in Ohio on a conditional moratorium with utility and labor requirements. Their own words and sources are in our governors guide.
None of this is law yet. A pause still needs a legislature, an executive order or a utility commission. But a project signing land today energizes in 2029 or later. The question of where else to go is being asked now.
The contract you would sign
These are the large-load rules each utility has filed or had approved. A threshold is who the rules apply to. It is not a promise of service.
| Utility | Applies at | Main terms | Status |
|---|---|---|---|
| Evergy (Kansas, Missouri) | 75 MW and up | 12-year term after up to 5 years of ramp. Minimum bill at 80% of expected demand. Collateral of two years of minimum bills, reduced for strong credit. | Approved in both states, November 2025 (KCC) |
| TVA (Tennessee Valley) | Above 5 MW of data center load | Capacity Commitment Charge of $1.521 million per MW, paid before the contract starts, for a first pool of up to 2,000 MW. Firm power over 100 MW for a new customer needs Board approval. | In effect October 1, 2026 (TVA Board) |
| Entergy Louisiana | 70 MW and up, 80% load factor | Block demand charges and a minimum bill. Large deals such as Meta's add upfront payments, termination charges and a parent guaranty. | Tariff in effect (Entergy Louisiana) |
| Duke Energy (Carolinas) | 50 MW and up, 80% load factor | Nonrefundable upfront payment for facilities that serve only you. Deposits and security for shared upgrades such as transmission. | North Carolina settlement, order expected mid-November 2026 (Duke) |
| Alabama Power | 150 MW and up for state review | Negotiated contracts with minimum bills, minimum terms, upfront payments and collateral. The figures are redacted in public filings. | Commission votes within 90 days, since October 2026 (Alabama PSC) |
| OG&E (Oklahoma) | 75 MW and up | Long-term commitments, minimum billing demand, customer-funded upfront costs and a customer protection charge. | Proposed. Hearing January 12, 2027 (OGE 10-Q) |
| PSO (Oklahoma, AEP) | 75 MW and up, set by state law | PSO says data centers would start paying the cost to serve them before they connect, with upfront guarantees and long payment commitments. | Pending in the rate case, order expected late 2026 (PSO) |
| GRDA (Oklahoma) | Load above an agreed firm amount | You bring or contract your own supply above the firm amount, and pay for transmission studies and upgrades. | In effect May 2026 (GRDA) |
Arithmetic, not a quote. Under TVA's rate, a new 50 MW request pays the charge on the 45 MW above the first 5 MW. At $1.521 million per MW that is about $68 million, before the contract takes effect. Your local power company's own terms come on top.
When the power shows up
Each utility's plan says it needs more generation than it has. These are the dates its own filings give for closing the gap.
- OG&E needs 1,922 MW by winter 2031/32. About 1,000 MW is contracted. A 755 MW gas plant filed for approval on October 27, 2026 (10-Q).
- PSO is short of its summer requirement by 470 MW in 2028 and 1,766 MW in 2029 before new resources (OCC testimony). It is seeking 4,000 MW for 2029 (AEP 10-Q).
- GRDA had 2,136 MW of resources against a 2,123 MW requirement in 2025, before its new 420 MW gas unit (GRDA).
- Alabama Power is short of its winter target by 1,179 MW in 2029 (IRP). It bought an 880 MW gas plant and is seeking more for 2032.
- Entergy plans about 24 GW of new resources. It has filed 5,278 MW of gas plants, about $12.9 billion, for a second Meta campus, with a decision expected December 2026 (10-Q).
- TVA needs 11 to 32 GW of new capacity by 2040 and is short in every scenario it modeled (IRP).
- Evergy shows a Missouri summer shortfall from 2027. It has about 2,600 MW of signed data center agreements and six gas units due from spring 2029 to 2032 (10-Q).
- Duke says it has an "immediate capacity need" and reaches its 22% winter reserve target in 2032 (resource plan).
A pipeline or a signed contract is demand for power, not a supply of it. We never add figures that use different definitions.
The destination states have new governors too
Moving a project across a state line moves it to a different set of politics. From our governors guide:
- Alabama: Tommy Tuberville won. His plan is no tax breaks, developers pay every cost, and a community that says no gets a no.
- Tennessee: Marsha Blackburn won on a ratepayer protection plan, local choice and water disclosure.
- South Carolina: Alan Wilson won. He opposes a moratorium and wants approved projects to generate their own energy.
- Kansas: not called when we checked on November 4. Cindy Holscher, who proposed a pause, led Ty Masterson, who opposes a moratorium, by about half a point.
Local rules matter as much as state ones. Check the moratorium tracker for counties and towns that have already acted.
What to ask before you commit
- A signed agreement with a date. A study or a place in the queue is not power. Ask for the energization date in writing.
- The plant behind the date. If the date depends on a gas plant still waiting for approval, your schedule depends on that approval.
- The money due before power. Model the minimum bill, collateral or capacity charge as a cost of the site, not a footnote.
- The exit cost. Termination charges run for the remaining term. Know the number before you sign.
For a buyer-side view of the same filings, with the shortfall figures in one table, see Colocation Scout's utility shortfall table.
Sources
Every figure comes from the utility's SEC filing, its own site, its filed resource plan or its state regulator, checked November 5, 2026. News coverage helped find figures but is never the source.
- OGE Energy, Q3 2026 Form 10-Q.
- Public Service Company of Oklahoma, direct testimony, OCC case PUD 2025-000064, September 12, 2025; data center rates page.
- American Electric Power, Q3 2026 Form 10-Q.
- Grand River Dam Authority, 2025 continuing disclosure; Schedule WP-SS.
- Alabama Power, 2025 Integrated Resource Plan; Alabama PSC, Docket 33709.
- Entergy, Q3 2026 Form 10-Q; Entergy Louisiana, Schedule LLHLFPS-L.
- Tennessee Valley Authority, 2026 Integrated Resource Plan; Board resolution on rates, August 20, 2026.
- Evergy, Q3 2026 Form 10-Q; Kansas Corporation Commission, large load tariff order, November 6, 2025.
- Duke Energy, 2026 Carolinas Resource Plan, Appendix C; large load settlement release.
The $68 million TVA figure is our arithmetic from the published rate. Nothing on this page is legal or rate advice.